Project: Maintenance of C-01 Base Oil Tank at CFP Tank Farm Area LOBP
Prev. Today’s
Description Of Work Progress Progress Total Remarks
Progress Pictures
Equipment Deployed Staff Labour
Deployed Deployed
Mobile Crane 0 Project Manager 0 Rescuers 4
-
Representative
Representative
Abdul Hadi
Ali RAZA Shell Pakistan Ltd.
Naseem & Son