P-01

N&S Date: 2 January 2023


Weather Condition: Clear
DPR - Summary Sheet s

Client: SHELL PAKISTAN LTD.

Contractor: NASEEM & SON.

Project: Maintenance of C-01 Base Oil Tank at CFP Tank Farm Area LOBP

Prev. Today’s
Description Of Work Progress Progress Total Remarks

Permit issuance and Isolation. 100% - 100% Todaay : 2 January 2023


Cleaning of Tank 50% - 50% Blasting 0f 02 Plates and 24’ railing
completed.
Installation of net Screen 100% 100% i. Blasting of 38 plates completed & 10
Grit Blasting of tank & application of remaining.
Primer 80% 2% 82%
ii. Blasting of base plates for vertical post of
Welding of patch plates and doublers 100% 100%
Power Brushing of Welding Seam of railing done today.
bottom plates 100% iii. Yesterday : 2 January 2023
Inspection (VBT) of Bottom By Third Party 100% - 100% i. Re- Blasting of 06 plates & 27 Stair steps
Closing of expansion joint by sika - completed today & Primer applied.
Application of mid coat & Final coat of
ii. Blasting of 09 stair steps and primer
paint - applied.
Supply of gasket stud for Box up -
Removal of scaffolding -
Housekeeping & De-mobilization

Progress Pictures
Equipment Deployed Staff Labour
Deployed Deployed
Mobile Crane 0 Project Manager 0 Rescuers 4

Site Office 0 Construction Manager 0 Fabricator 0

Warehouse 0 Planning & Co-ordination Engr 0 Fitter 0

Paint Store 0 Manager HR / Admin 0 Grit blaster/Painter 2

Vehicles 0 Mechanical Engineer 1 Welder 0

Grinders 0 Trainee 0 Mechanical Tech 0

Compressor 1 Foreman / In-charge Rigger / Scaffold 2

Scaffolding with Planks 1 Supervisor 1 Helper 5

Paint MixtureMachine 1 Safety In-charge 1 Cook 0

Vacuum Machine 0 Fire Watcher 1 Driver 0

Hopper 1 Store Keeper 1 Office Boy 0

Hand Tools 10 Accountant/Site Admin 0 Painter 2

-
Representative
Representative
Abdul Hadi
Ali RAZA Shell Pakistan Ltd.
Naseem & Son