ID WBS Task Task Name Duration Start Finish Predecessors Aug '22 Sep '22

Mode 24 31 7 14 21 28 4
1 1 Adjudicacion de contrato 25 days Mon 8/08/22 Thu 1/09/22
2 1.1 Contratacion de personal 15 days Mon 8/08/22 Mon 22/08/22
3 1.2 EMO 15 days Mon 8/08/22 Mon 22/08/22
4 1.3 Compra de EPPs 15 days Mon 8/08/22 Mon 22/08/22
5 1.4 Compra de herramientas 15 days Mon 8/08/22 Mon 22/08/22
6 1.5 Compra de equipos 15 days Mon 8/08/22 Mon 22/08/22
7 1.6 Compra de casetas 2 days Mon 8/08/22 Tue 9/08/22
8 1.7 Instalacion de casetas 6 days Tue 23/08/22 Sun 28/08/22 6
9 1.8 Gestion de acreditacion de 4 days Tue 23/08/22 Fri 26/08/22 2
personal
10 1.9 Gestion de documentacion para 10 days Tue 23/08/22 Thu 1/09/22 2
permiso de trabajos
11 1.10 Movilizacion de equipos, 2 days Mon 29/08/22 Tue 30/08/22 2;7;8
herramientas y EPPs

Task Project Summary Manual Task Start-only Deadline

Project: SP-0644 - 2022 Split Inactive Task Duration-only Finish-only Progress


Date: Thu 4/08/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone