Professional Documents
Culture Documents
Report Tunnel Stability - Final
Report Tunnel Stability - Final
Report Tunnel Stability - Final
Tunnel Stability
22 June 2009
Document Status
Document Status
Document Status
Document Status
This document has been prepared by a division, subsidiary or affiliate of Jacobs Engineering U.K. Limited (“Jacobs”) in its professional capacity as
consultants in accordance with the terms and conditions of Jacobs’ contract with the commissioning party (the “Client”). Regard should be had to
those terms and conditions when considering and/or placing any reliance on this document. No part of this document may be copied or
reproduced by any means without prior written permission from Jacobs. If you have received this document in error, please destroy all copies in
your possession or control and notify Jacobs.
Any advice, opinions, or recommendations within this document (a) should be read and relied upon only in the context of the document as a
whole; (b) do not, in any way, purport to include any manner of legal advice or opinion; (c) are based upon the information made available to
Jacobs at the date of this document and on current UK standards, codes, technology and construction practices as at the date of this document. It
should be noted and it is expressly stated that no independent verification of any of the documents or information supplied to Jacobs has been
made. No liability is accepted by Jacobs for any use of this document, other than for the purposes for which it was originally prepared and
provided. Following final delivery of this document to the Client, Jacobs will have no further obligations or duty to advise the Client on any matters,
including development affecting the information or advice provided in this document.
This document has been prepared for the exclusive use of the Client and unless otherwise agreed in writing by Jacobs, no other party may
use, make use of or rely on the contents of this document. Should the Client wish to release this document to a third party, Jacobs may, at its
discretion, agree to such release provided that (a) Jacobs’ written agreement is obtained prior to such release; and (b) by release of the
document to the third party, that third party does not acquire any rights, contractual or otherwise, whatsoever against Jacobs and Jacobs,
accordingly, assume no duties, liabilities or obligations to that third party; and (c) Jacobs accepts no responsibility for any loss or damage
incurred by the Client or for any conflict of Jacobs’ interests arising out of the Client's release of this document to the third party.
Contents
1 Introduction 1
2 Background Information 2
2.1 Location 2
2.2 Site Layout 2
2.3 The Tunnel 2
2.4 Pumping Station Access 3
2.5 Security of Supply 3
3 Tunnel Condition 4
3.1 Inspection 4
3.2 General Geological Condition 4
3.3 Collapsed Zone 4
3.4 Tunnel Stability Assessment 4
4 Remedial Works 6
4.1 Options 6
4.2 Selected Option 6
5 Conclusions 8
6 References 9
The Prenton Service Tunnel is approximately 35m long and runs between a
pumping station adjacent to the Prospect Road/Tower Road reservoir site entrance
and the underground reservoir itself.
The tunnel was constructed in rock strata, is approximately 2.0m high and 1.5m
wide and carries 3 nr CI mains, 12”, 13” and 14”, as well as a 12” reservoir scour
pipe.
A collapse of rock has recently occurred over a short length of the tunnel and United
Utilities (UU) have appointed Jacobs to carry out an urgent investigation of the
tunnel to determine the cause of collapse, the extent of the problem, the risk to the
mains and to propose options for remedial work.
Once a preferred solution has been selected then subsequent work would involve
the development of the design of the remedial works, engaging a contractor to carry
out the work and implementing the solution.
2.1 Location
Water from the SR gravitates to the PS which then pumps the draw-off water up to
the Tower. The rising mains from the PS to the Tower are not located in the tunnel.
One of the cast irons mains in the tunnel has been duplicated with a fourth main in
the tunnel over the majority of the tunnel length. The mains in the tunnel have been
laid in a sand bed.
The tunnel is accessed from ground level via a stone, spiral staircase (29 no steps x
250mm) located in a small tower adjacent to the upper reservoir. UU have
designated the staircase/tower as a gas check zone and the staircase has
permanent electric lighting installed.
The depth from ground level to tunnel soffit at the spiral staircase is approximately
7m.
The base of the staircase accesses the tunnel at approximately one third of its 35m
length from the SR to the PS. The tunnel is curved in plan with an approximate 35°
change of direction as shown on the sketch in Appendix 2.
The tunnel collapse zone is located approximately 7m towards the PS from the
spiral staircase and the access road to the site passes over the tunnel at this point.
No noticeable signs of tunnel collapse have been recorded at surface.
The tunnel itself is approximately 1.5m wide and 2.0m high. It is unlined and has
been constructed using an arch shaped profile. The tunnel is terminated at the SR
end with a brick headwall.
Ventilation of the tunnel relies on natural air circulation from an access chamber at
the PS end to the spiral staircase access. There is no natural ventilation in the
tunnel dead end section towards the SR.
At the PS end of the tunnel there is a square access chamber to the tunnel
approximately 1.2m x 1.2m in size. The cover from ground level to the crown of the
tunnel at the PS is approximately 3m.
Vibration from the submersible pumps is noticeable at ground level on the line of the
tunnel.
UU have no current plans to replace or uprate any of the mains in the tunnel or
elsewhere on the Prenton site. Any remedial works solutions for the tunnel would
thus need to developed for the medium to long term. Any remedial works options
involving interruption to supply through the CI mains in the tunnel would not be a
preferred solution.
3.1 Inspection
This inspection was undertaken by a Jacobs Tunnel Engineer with support from UU
personnel. Record photographs of the inspection are shown in Appendix 3.
The tunnel has been constructed through the Triassic Lower Keuper
Sandstone/Bunter Sandstone series – reddish in colour, mainly fine grained and
often current bedded. The Keuper and Bunter Sandstones are generally good,
stable tunnelling mediums and have yielded good stone for building. Recently, the
Keuper and Bunter Sandstones has been re-named by the British Geological Survey
as the “Sherwood Sandstone Group”.
Appendix 4 contains the geotechnical logging sheets that were used during the
inspection to record the rock mass characteristics.
The general rock mass along the tunnel comprised slightly weathered sandstone
with widely spaced joints. The sandstone was dry at the time of the inspection.
At around 7m from the bottom of the spiral staircase towards the PS a 4m long
section of the tunnel has collapsed with debris lying on top of the 14” main. The
collapse has resulted in a “cavern” approximately 1.8 – 2.0m wide and 2.0m high
above the 14” main. The collapse does not extend to ground level.
The cavern walls and roof consist of loose, unstable blocks of weathered sandstone
and extensive tree roots are evident. No groundwater was present during the
inspection but there was clear evidence that rainwater percolates into the tunnel
from the surface.
UU have confirmed that the rockfall was first noted some 6 months ago and that the
rock condition in the collapse zone appeared somewhat worse on the 11th June
inspection. This is a clear indication that the rock mass in the collapse zone is in a
highly unstable state.
From the data obtained during the inspection the tunnel stability of various locations
along the tunnel was assessed using the CSIR Rock Mass Classification1 and the
NGI Q System2. The results are given in Appendix 5.
The general tunnel rock mass was assessed as “poor” or “very poor” consistent with
a weathered rock mass near surface. However the limited span of the excavation
In the area of the collapse, it was difficult to obtain any meaningful data on the rock
mass condition because of the unstable and highly weathered condition of the
strata. However the collapse zone is evidently “very poor” or worse in nature and
permanent support is demanded in this area to prevent further collapse.
In tunnels excavated in jointed rock masses at relatively shallow depth, the most
common mode of failure are these involving wedges falling from the roof or sliding
from the sidewalls. Any wedge that is allowed to fall or slide will cause a reduction
in the restraint and the interlocking of the rock mass then this in turn will allow other
wedges to fall. This failure process will continue until natural arching in the rock
mass prevents further unravelling or until the tunnel is full of fallen material.
It was thus concluded that, with the exception of the collapse zone, the tunnel is in a
relatively stable condition and is likely to remain so.
4.1 Options
Following the investigation and analysis work on tunnel stability, it is evident that
remedial works need only be targeted at the collapse zone in the tunnel. Such
remedial works need to be implemented rapidly as further collapse could occur at
any time with resulting damage to the mains. Asset recovery would be difficult
should a complete tunnel collapse occur.
A number of options have been considered including relining of the tunnel with insitu
or sprayed concrete. These options would take some time to implement, would
probably involve letting of a contract and could cost substantial amounts.
Cheaper options such as completely filling of the collapsed zone using sand or
foamed concrete have also been considered. These options are less expensive but
have the disadvantage that the tunnel asset is effectively “lost” should the mains
ever need replacing.
Table 4.1 shows the full range of remedial works options considered with their
relative merits and costs.
On balance and in view of the urgent need to stabilise the collapse zone in the
tunnel, a solution involving filling of the “cavern” using foamed concrete is
considered the fastest and most cost-effective solution. This is shown on the sketch
in Appendix 7.
Brickwork bulkheads would need to be constructed either side of the collapse zone
prior to filling with low strength (5N/mm2) foamed concrete. Filling could be carried
out via a surface borehole but care would need to be taken when drilling this hole to
avoid further collapse. A 300mm layer of sand could be hydraulically placed in
advance of foam concrete filling. This sand layer would provide protection to the
upper 14” main.
To provide permanent thorough ventilation in the tunnel across the collapse zone it
is recommended that 3 nr 400mm dia uPVC ducts are placed across the collapse
zone as shown. These ducts could be used for future mains replacement.
Personnel access would be retained to either side of the collapse zone. However,
access via the spiral staircase would be difficult for plant and materials
• Based on our survey of 11 June 2009 the general rock mass condition along
the tunnel has been classified using rock mass rating techniques and the
tunnel rock is generally “poor” in nature. However, with a tunnel of this size
and in this rock, permanent support of the excavation would generally not be
necessary.
• The area of the collapse exhibits a different rock mass condition – “very
poor”. If the tunnel had been constructed nowadays, this section would
almost certainly demand a permanent lining.
• The tunnel collapse has been prompted by the low rock cover, the presence
of tree roots within the rock mass and the infiltration of groundwater.
• It is possible that further collapses of rock could occur in the near future.
• The preferred (and simplest option) is to infill the collapse zone with
lightweight foamed concrete of 5N/mm2 strength. This will prevent further
collapse of strata in the “very poor” rock section.
• The disadvantage to doing this is that access to the mains in the invert is lost
in the event of a failure. As this is an unlikely event, the preferred solution is
to insert 3 x 400mm dia plastic ducts through the foamed concrete collapse
section, laid on top of the existing pipes prior to concrete placing.
• The presence of the ducts through the foamed concrete infilled section also
allows airflow through the tunnel from the access chamber at the pumping
station end of the tunnel to the spiral staircase access.
Disc:
No.1 (180/48)
No.2 (300/20)
No.4 (250/78)
No.5 (150/90)
Tunnel alignment: N15W
Disc:
No.6 (162/74)
No.7 (240/72)
No.8 (154/89)
No.9 (90/82)
No.10 (45/86).
Tunnel alignment: N15W
Disc:
No.11 (228/45) and
No.12 (245/15).
Tunnel alignment: N50W
Disc:
No.13 (60/76)
No.14 (292/85)
No.15 (0/ 4)
No.16 (100/80) and
No.17 (250/84).
Tunnel alignment: N50W
Disc:
No.18 (230/78)
No.19 (180/84)
No.20 (230/89).
Tunnel alignment: N15W