Professional Documents
Culture Documents
ArcelorMittal (2014) CS 020 - Port of Piombino North and South Quays, Italy
ArcelorMittal (2014) CS 020 - Port of Piombino North and South Quays, Italy
ArcelorMittal (2014) CS 020 - Port of Piombino North and South Quays, Italy
+1.00
+0.50
• demolition of the pier Ex-Ilva. The
3.50
1.35
0.00 m 0.00
Drain Ø300 mm
-1.00
Tie rod n°1 Ø 60
demolition material will be reused for the
Backfill
Duct c/c1.93 m ASF 600 L=30.95 m execution of ecological islands in the sea;
Darsena grande variable level -0.90 ~ -5.80
after removing of polluted soil One of the criteria for the choice of the
Anchor beam
Epoxy coating
1.80 x 1.35 m deep retaining structure of the quay walls
over 4.00 m of the North and South Docks was to
Silty Sand guarantee its imperviousness during its
Cathodic protection Roxan®Plus system into
system the interlock of AZ 28-700
L = 34.00 m
HEA 1000
SPT 15 service life of 100 years. A cost-effective
L = 14.00 m
c/c 1.79 m solution, with low maintenance costs that
-12.00 fulfils the criteria is a steel wall system
-13.00 HZ®-M/AZ® in combination with a sealing
-15.00
HZ 1080M C-14
+1.00 m to - 6.00 m HZ 1080M C-12
system.
- 6.00 m to -16.00 m HZ 1080M C-14 S 355 JO+M
The quay wall for the functional berths
Borelog S4
8.7
4.58 4.58
4
1.93
1.93
1.93
1.93
Tie rod Lmin= 23.30
1.93
1.93
1.93
1.93
+0.30
0.60
0.60
+0.90
+0.60
0.60
0.60
V4
5.65
of water coming from the surrounding plant
+0.30
1.90
1.90
HZ 88
0M A-12 1.90
AZ 19
-700 L=
L=14.00
6.00
Steel Sheet Piles
AZ 13-700 L=6.00 m
128.68 +0.60
involved the construction of two small
AZ 19
Sedim
-700
L=6.00 AZ 19
-700
L=6.00 A1
46.42 46.25 Anchor beam 1.80 x 1.35m
A2
A3 basins (7 x 40 m, resp. 42 x 40 m). In both
constructions the bottom level of the basin is
entation 35.14
N°11 Steel sheet piles N°11 Steel sheet piles
1.43
1.87
Steel
1.93
1.87
1.93
1.43
General layout drawing. Darsena Grande perimeter walls and partitions of the basins were
built with a combined wall using Ø 800 mm
steel tubes, 10 mm thick, and AZ 13-770
In order to improve the performance and level, by steel tie-rods connected to an anchor
intermediate sheet piles.
durability of the sheet pile wall the joint venture pile installed about 30.5 m behind the main wall.
CMC-SALES proposed an alternative design The HEA 1000 beams used as anchor piles are
during the tender period for the main quay wall: 14 m long, extending between the levels +1.00
the new HZ 1080MC-14 / AZ 28-700, where above and -13.00 m below water level.
the length of the RH connectors on the back The next step in the optimization process of
flange covered only the segment with maximum the original specification was to increase the
stresses. Additionally, as the 34.0 m long HZ-M steel grade: the king piles HZ-M were supplied
king piles exceeded slightly the maximum rolling in S 355 JO + M, and the AZ infill sheets in
length of the Luxemburgish mill, ArcelorMittal’s S 355 GP, thus enhancing the bending moment
technical support team proposed to optimize the capacity of the wall.
king pile over the depth by splicing a lighter HZ
1080MB beam on the bottom part of the king Moreover, a temporary jetty to protect the
pile, where the bending moments are smaller. Magona Dock was created with a row of
re-used PU 25, 13.50 m long, taken from the
Consequently, the king pile can be subdivided contractor’s own stock. A perpendicular wall The works were performed by the joint venture
into four different sections, from made of sheet piles at the back stiffened the CMC Cooperativa Muratori e Cementisti
main wall. (CMC) of Ravenna and Sales SpA.
+1.00 m to -6.00 m HZ 1080M C-12 / AZ 28-700
The soil is made up of layers of silty sand The fruitful collaboration with ArcelorMittal
-6.00 m to -16.00 m HZ 1080M C-14 / AZ 28-700 allowed optimizing the productivity of the work
and sandy silt to a depth of -21.0 m below
-16.00 m to -17.50 m HZ 1080M C-12 / AZ 28-700 medium sea level, and lenses of “calcarenite” and ensuring the quality of the product offered
(limestone), or more commonly referred to as on following aspects:
-17.50 m to -33.00 m HZ 1080M B-12 / AZ 28-700
“panchina” (bench), with a thickness varying • reduction of lead times optimized by the
The sheet piles were shipped by rail to from 50 cm to 120 cm traced in different levels proximity of the ArcelorMittal Piombino
07.2014 - CS 020 - Piombino Harbour - GB
ArcelorMittal’s mill in Piombino, which is located in depth. premises to the construction site;
directly next to the construction site. The The driving of the main quay wall was carried • no interference with the port traffic
RZD/RZU connectors were seal-welded and the from the sea through a motor barge crane, a guaranteed through the supply of the
sealing system Roxan®Plus was applied into the vibratory hammer PTC 100 HFV and hydraulic sheet piles by rail directly from the plant of
interlocks of the AZ infill sheet piles hammer IHC S70 to drive to the final level. ArcelorMittal Piombino;
(water-swelling product in the free interlocks) A specific driving template enabled the correct • technical assistance with the design of the
in this premises. Furthermore, the splicing of the positioning of the king piles. The anchor piles anchor piles, and the driving template for
HZ-M king piles was also carried out there. were driven from land with a vibratory hammer the HZ-M king piles.
The main quay wall was realized by driving the PTC 50 HFV hanging on a Linkbelt type crane. The construction works started in March 2012
steel sheet piles with a length of 34.0 m, and Due to the quite unfavourable surrounding and the civil works are still running.
tied back at elevation +0.50 m above water environmental conditions (salinity and brackish