DIREKTORAT JENDERAL ENERGI BARU TERBARUKAN

DAN KONSERVASI ENERGI (DJEBTKE)


KEMENTERIAN ENERGI DAN SUMBERDAYA MINERAL

PEMBANGUNAN DAN REVITALISASI


PEMBANGKIT LISTRIK TENAGA MIKRO HIDRO (PLTMH)
DI PROVINSI JAMBI
DEVELOPMENT AND REVITALIZATION MICRO HYDRO POWER GENERATION (PLTMH)
IN JAMBI PROVINCE
UNDP melalui proyek MTRE3-Market Transformation through UNDP through the MTRE3-Market Transformation through Design and
Design and Implementation of Appropriate Mitigation Actions in Implementation of Appropriate Mitigation Actions in the Energy Sector
the Energy Sector bersama EBTKE-ESDM dan Pemerintah Provinsi in cooperation with EBTKE-ESDM and the Provincial Government of
Jambi dengan dukungan dari Bank Jambi dan Baznas, bekerjasama Jambi with support from Bank Jambi and Baznas , in collaboration to
untuk implementasi SDG’s di Provinsi Jambi, yaitu pemanfaatan the implementation of Sustainable Development Goals (SDG’s) in Jambi
Energi Baru Terbarukan (EBT) yang dapat mendukung pengentasan Province. It encourage development of Renewable Energy (RE) that can
kemiskinan dan penyejahteraan masyarakat melalui peningkatan support poverty alleviation and community welfare through increased
akses terhadap energi. access to energy.

Kerjasama Pemanfaatan EBT ini diaplikasikan dalam program This cooperation is to develop Microhydro Power Generation (PLTMH)
Pembangunan baru PLTMH di di desa Lubuk Bangkar Kecamatan in Lubuk Bangkar village, Batang Asai District, Sarolangun Regency and
Batang Asai Kabupaten Sarolangun dan revitalisasi 3 PLTMH di desa revitalization of 3 PLTMH in Ngaol village, Air Liki village & Air Liki Baru
Ngaol, desa Air Liki & Desa Air Liki Baru, Kecamatan Tabir Barat, village, West Tabir district, Merangin Regency.
Kabupaten Merangin.

PLTMH Jambi
TAHAPAN APLIKASI PLTMH DI PROVINSI JAMBI / Phase of Application of PLTMH Jambi PENENTUAN DESA LOKASI PLTMH / Determining of PLTMH Location

Studi Akses Terhadap Energi di Provinsi Jambi Access to Energy Study in Jambi Province 1. Lokasi desa yang belum memiliki aliran listrik dan atau 1. The village that has not electricity yet and or has not been
Desk study, wawancara dan diskusi langsung bekerjasama Desk study, interview and discuss with Pemprov Jambi and belum terjangkau jaringan listrik PLN. reached by PLN’electricity network.
dengan Pemprov Jambi dan PT. PLN. Diperkuat dengan PT. PLN. Database extracted from BPS and National Team for Jika desa tersebut memiliki pembangkit listrik swadaya If the village has a community-owned power station, then the
data BPS dan Tim Nasional Percepatan Penanggulangan Accelerating Poverty Reduction (TNP2K) masyarakat, maka kondisi dan infrastukturnya akan condition and infrastructure will be considered in determining
Kemiskinan (TNP2K) Juni-Agustus 2017
menjadi pertimbangan penentuan lokasi. the location.
Juni-Agustus 2017
Initial Survey of Potential Locations of Microhydro
Survey Awal Lokasi Potensi PLTMH In cooperation with Pemprov Jambi dan PT. PLN 2. Desa dengan kondisi infrastruktur terbatas sehingga 2. Village with poor infrastructure which limited the access of
Bekerjasama dengan Pemprov Jambi dan PLN Agustus 2017 membatasi akses pembangunan, diantaranya adalah development, including the limitation of electricity infrastructure
Agustus 2017 keterbatasan infrastruktur listrik. Database extracted from BPS and National Team for
Review and Preliminary Selection of PLTMH
Review dan Penentuan Awal Lokasi PLTMH Data desa miskin di Provinsi Jambi menggunakan Accelerating Poverty Reduction (TNP2K)
Locations
Dilakukan bersama Pemprov Jambi, PLN, Bank Jambi, basis data Tim Nasional Percepatan Penanggulangan
In cooperation with Pemprov Jambi, EBTKE-ESDM, PT. PLN,
EBTKE-ESDM dan Baznas Bank Jambi and Baznas Kemiskinan (TNP2K) dan data dari BPS. 3. Meet the requirements of disadvantaged communities and
September 2017 September 2017 diserve to recieve zakat.
Launching / Peluncuran Program Kerja Sama 3. Memenuhi persyaratan masyarakat tertinggal yang layak
Launching and Signing Letter of Intent (LoI)
& Penandatanganan Letter of Intent (LoI) mendapatkan hak atas zakat. 4. Has potential application of renewable energy generation.
PLTMH Jambi
Pembangunan Microhydro September 2017
Villages with hilly land contours and have water resources to
September 2017 4. Memiliki potensi aplikasi pembangkit listrik energi generate electricity (PLTMH).
Joint Survey with Dinas ESDM Jambi and PT. PLN terbarukan.
Survey Lanjutan Bersama Dinas ESDM Provinsi
To Determine whether the village has been or has not Desa dengan kontur tanah berbukit dan memiliki sumber
Jambi dan PT. PLN
Menentukan dan memastikan apakah desa tersebut sudah
been included in the PLN electricity network development daya air untuk membangkitkan tenaga listrik (PLTMH).
plan in the near future.
atau belum masuk ke dalam rencana pembangunan
October-November 2017
jaringan listrik PLN dalam waktu dekat.
DETAIL APLIKASI PLTMH JAMBI / Detail Application of PLTMH Jambi
Oktober-November 2017 Survey of Community Social Economic
Survey Sosial Ekonomi Masyarakat Designing social economy program sector to increase Pembangunan baru PLTMH di Desa Lubuk Bangkar Kecamatan Batang Asai
Merancang kegiatan tambahan di sektor ekonomi untuk community income from the utilization of electrical energy Kabupaten Sarolangun
meningkatkan pendapatan masyarakat secara langsung October-November 2017 The new construction of Micohydro Power Generation in Lubuk Bangkar village, Batang Asai District, Sarolangun Regency
maupun tidak langsung dari pemanfaatan energi listrik
Pembangunan baru infrastruktur Pembangunan jaringan Menghasilkan listrik yang dapat dimanfaatkan
Oktober-November 2017 Preparation of Design and Tender PLTMH PLTMH, pintu air dan pipa penstock listrik baru untuk 283 rumah tangga, 2 sekolah, 5 masjid
October - December 2017
Penyusunan Design dan Tender PLTMH dan musholla, 1 balai desa dan 5 gardu/
Development microhydro infrastuctures, Construction of new power grid
Oktober - Desember 2017 water intake weir and penstock pipe posyandu.
Development of Microhydro in Lubuk Bangkar
Pembangunan Infrastruktur Microhydro Lubuk February-July 2018 Generate electricity for 283 households, 2 schools, 5
Bangkar Revitalization of Microhydro at Ngaol Village, Air mosques and musholla, 1 vilage hall and 5 posyandu
Februari-Juli 2018 Liki Village and Air Liki Baru Village
February-June 2018
Revitalisasi di Desa Ngaol, Air Liki, Air Liki Baru
Februari-Juni 2018 Study Ability to Pay Electricity Fee Pengadaan Turbin, Generator dan Peningkatan kapasitas masyarakat, pelatihan
Determination of contribution for microhydro operation 60 kW kepada operator dan pembentukan lembaga
Studi Kemampuan Membayar Biaya Listrik Pembangunan Power House Baru
Penentuan iuran untuk operasional dan perawatan and maintenance desa pengelola PLTMH
Kapasitas listrik 60kW
microhydro February-April 2018
Februari-April 2018 New Turbine, Generator and Power Community development, training to operator and
Microhydro Institutional Establishment and House of 60 kW power capacity establishment of village organization.
Pembentukan Kelembagaan & Training Operator Training to Operator
Mei dan Juli 2018
May and July 2018
Revitalisasi PLTMH di desa Ngaol, Kecamatan Tabir Barat, Kabupaten Merangin
Peresmian Revitalisasi Microhydro di Ngaol, Air Inauguration of Microhydro Revitalization in
Revitalization of Micohydro Power Generation in Ngaol village Tabir Barat District, Merangin Regency
Liki, Air Liki Baru Ngaol, Air Liki and Air Liki Baru
Juli 2018 July 2018 Penggantian bak penampung air, Menghasilkan listrik yang dapat dimanfaatkan
pintu air dan pipa penstock untuk 244 rumah tangga, 1 masjid, 10 musholla,
Peresmian PembangunanMicrohydro Lubuk Inauguration of Microhydro Development in
Bangkar Lubuk Bangkar 1 pesantren, 1 panti jompo, 2 sekolah, 2 balai
Replacing water reservoir , water intake
Agustus 2018 August 2018 weir and penstock pipe adat dan 1 kantor desa.

Generate electricity for 244 households, 1 mosque, 10


mushollas, 1 pesantren, 1 nursing house, 2 schools, 2
balai adat and 1 village hall

Penggantian Turbin, Generator, Power Peningkatan kapasitas masyarakat, pelatihan


House dan penyempurnaan komponen 40 kW
kepada operator dan pembentukan lembaga
electrical mechanical
desa pengelola PLTMH
Kapasitas 40kW
Community development, training to operator and
Replacing turbine, generator, power house and
establishment of village organization.
improving electrical mechanical componets of
40kW power capacity
Revitalisasi PLTMH di desa Air Liki, Kecamatan Tabir Barat, Kabupaten Merangin
Revitalization of Micohydro Power Generation in Ngaol village Tabir Barat District, Merangin Regency

Pembangunan baru dan relokasi Penambahan jaringan listrik Menghasilkan listrik yang dapat dimanfaatkan
bendungan, pintu air, pipa penstock untuk 126 rumah tangga, 2 sekolah, 1 masjid, 5
dan penampungan air Improving power line
musholla dan 1 kantor desa
Development and relocation
microhydro infrastuctures, water intake Generate electricity for 126 households, 2 schools, 1
weir, penstock pipe and water reservoir mosque, 5 muholla and 1 village hall

Penggantian dinamo generator dan


penyempurnaan komponen electrical Peningkatan kapasitas masyarakat, pelatihan
40 kW
mechanical kepada operator dan pembentukan lembaga
Kapasitas 40 kW desa pengelola PLTMH

Replacing dynamo generator and Community development, training to operator and


improving electrical mechanical establishment of village organization.
componets of 40 kW power capacity

Revitalisasi PLTMH di Air Liki Baru, Kecamatan Batang Asai Kabupaten Merangin
Revitalization of Micohydro Power Generation in Air Liki Baru village Tabir Barat District, Merangin Regency

Pembangunan baru dan relokasi Menghasilkan listrik yang dimanfaatkan untuk


bendungan, pintu air, pipa penstock 153 rumah tangga, 1 Sekolah, 1 masjid, dan 1
dan penampungan air
kantor desa
Development and relocation
microhydro infrastuctures, water intake Generate electricity for 153 households, 1 school, 1
weir, penstock pipe and water reservoir mosque, and 1 village hall

Perbaikan turbin, generator dan


penyempurnaan komponen electrical 40 kW Peningkatan kapasitas masyarakat, pelatihan
mechanical
kepada operator dan pembentukan lembaga
Kapasitas 40 kW desa pengelola PLTMH
Repairing turbine, generator and
Community development, training to operator and
improving electrical mechanical
componets of 40 kW power capacity establishment of village organization.

‘Mendukung Energi Berkeadilan’


PROJECT MANAGEMENT OFFICE
Menara Ravindo 6th Floor
Jl. Kebon Sirih Kav. 75 p. +62 21 3160457
Jakarta Pusat 10340 f. +62 21 3162949
Indonesia w. www.mtre3.id