Cadangan 

Peningkatan Dan Pelebaran Jalan Di Jalan Yew Dan Jalan Sungai Besi
(Di Antara Bulatan Kampung Pandan Dengan Lebuhraya Sungai Besi Dan Lebuhraya 
KL‐Seremban) Kuala Lumpur (Reka Dan Bina) (2020/A115)

No. Qty Unit Rate Amount Remarks


Description

1. To supply and install Proposed Relocation of 1 No. 383 mtrs 428.00 163,924.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 1)
( Matchline CH. 300 to CH. 900 )

2. To supply and install Proposed Relocation of 1 No. 370 mtrs 428.00 158,360.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 2)
( Matchline CH. 300 to CH. 900 )

3. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 1)
( Matchline CH. 300 to CH. 900 )

4. To Proposed Cut and Joint 11kV underground 2 Lot 2,400.00 4,800.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 2)
( Matchline CH. 300 to CH. 900 )

5. To supply and install Proposed Relocation of 1 No. 45 mtrs 428.00 19,260.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 3)
( Matchline CH. 900 to CH. 1200 )

6. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 3)
( Matchline CH. 900 to CH. 1200 )

7. To supply and install Proposed Relocation of 1 No. 20 mtrs 428.00 8,560.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 4)
( Matchline CH. 1200 to CH. 1500 )
Cadangan Peningkatan Dan Pelebaran Jalan Di Jalan Yew Dan Jalan Sungai Besi
(Di Antara Bulatan Kampung Pandan Dengan Lebuhraya Sungai Besi Dan Lebuhraya 
KL‐Seremban) Kuala Lumpur (Reka Dan Bina) (2020/A115)

No. Qty Unit Rate Amount Remarks


Description
8. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00
electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 4)
( Matchline CH. 1200 to CH. 1500 )

9. To supply and install Proposed Relocation of 1 No. 57 mtrs 428.00 24,396.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 5)
( Matchline CH. 1200 to CH. 1500 )

10. To supply and install Proposed Relocation of 1 No. 57 mtrs 428.00 24,396.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 6)
( Matchline CH. 1200 to CH. 1500 )

11. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 5)
( Matchline CH. 1200 to CH. 1500 )

12. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 6)
( Matchline CH. 1200 to CH. 1500 )

13. To supply and install Proposed Relocation of 1 No. 16 mtrs 428.00 6,848.00


(CIRCUIT) 11kV underground electrical cable inside
1 No. 150mm HDPE (PN10) Ducts By Open Trench
Excavation Method using 3C x 240mm2 
XLPE/SWA/PVC/AL.  (Cable No. 7)
( Matchline CH. 1500 to CH. 1693 )

14. To Proposed Cut and Joint 11kV underground 2 Lot 2,080.00 4,160.00


electrical cable to Existing TNB cable (3C x 240mm2
XLPE/SWA/PVC/AL) the exact locations of cables
jointing to be determined at site. (Cable No. 7)
( Matchline CH. 1500 to CH. 1693 )

15. To carry out pilot hole for All 11kV HT cables. 1 Lot 6,500.00 Rate Only

16. To restore existing turfing and excavate for all 1 Lot 10,000.00 Rate Only
the existing surfaces.
Cadangan Peningkatan Dan Pelebaran Jalan Di Jalan Yew Dan Jalan Sungai Besi
(Di Antara Bulatan Kampung Pandan Dengan Lebuhraya Sungai Besi Dan Lebuhraya 
KL‐Seremban) Kuala Lumpur (Reka Dan Bina) (2020/A115)

No. Qty Unit Rate Amount Remarks


Description
17. To restore existing road premix with proper 1 Lot 78,000.00 78,000.00
crush-run and spec. (For 7 Nos Cable)

18. To carry out 11kV HT cable splicing and jointing 1 Lot 8,000.00 8,000.00
between the new cables. (Brand : REPL)

19. The location of the electrical joint pit shall be 1 Lot 15,000.00 15,000.00
marked on stainless steel plate and placed on
top of the joint location.

20. To provideInsulation Test on High Voltage 1 Lot 7,000.00 7,000.00


Equipment (cables)as per specifications and as
per standard safety requirement.

21. To standby chargeman competent persons for HT Se 1 Lot 20,000.00 20,000.00

22. To provide Professional Engineer endorsement for M 1 Lot 25,000.00 25,000.00


of statement and shop drawings.

23. To provide all time traffic management at site 1 Lot 32,000.00 32,000.00
with full time supervisor.

24. Testing & commissioning. 1 Lot 15,000.00 15,000.00

Total Amount 635,504.00