Doc. No.

:
MEASUREMENT
Rev. No. : 2
OF Page : 1 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)

MEASUREMENT
OF
PAYMENT

(Steel Structure Work)

CONTRACTOR JOB NO. : XXXXX

PROJECT NAME :

CLIENT :

SITE :

2 17-Sep-2015 Revision

1 31-Oct-2014 Revision

REV. DATE DESCRIPTION PRPD CHKD APPD QA CLIENT


Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 2 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)

MEASUREMENT OF PAYMENT
(Steel Structure Work)

This measurement of payment(steel structure work) shall be applied for measurement of (construction
direct cost for) Subcontractor Progress Payment.

The calculation for Progress Payment is as below:


Progress Payment = Work Quantity * Unit Price * Weighted Factor of applicable Stage/Step

The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.

Unit Price is identified according to each contract between Contractor and Subcontractors.

Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.

Contents

1. Erection of Pipe Rack ( Code : C13100 / Unit : Ton )


2. Erection of Equipment Support Structure / Other STR ( Code : C13200 / Unit : Ton )
3. Erection of Stack Support Structure ( Code : C13300 / Unit : Ton )
4. Erection of Duct Support Structure ( Code : C13400 / Unit : Ton )
5. Pipe Over Bridge ( Code : C13500 / Unit : Ton )
6. Platform & Access Way ( Code : C13600 / Unit : Ton )
7. Local Support ( Code : C13700 / Unit : Ton )
8. Miscellaneous Steel ( Code : C13800 / Unit : Ton, M3 )
9. Fabrication of Steel Structure ( Code : C13900 / Unit : Ton )
10. Steel Shelter ( Code : C13A00 / Unit : Ton, M2, M, Nos )
11. Demolition ( Code : C13Y00 / Unit : Ton )
12. Others ( Code : C13Z00 / Unit : Ton )

3.
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 3 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)

1. Erection of Pipe Rack ( Code : C13100 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

2. Erection of Equipment Support Structure / Other STR ( Code : C13200 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

3. Erection of Stack Support Structure ( Code : C13300 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

4. Erection of Duct Support Structure ( Code : C13400 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 4 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)

5. Pipe Over Bridge ( Code : C13500 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

6. Platform & Access Way ( Code : C13600 / Unit : Ton )


Stage Weighted Factor Remark
Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

7. Local Support ( Code : C13700 / Unit : Ton )

Stage Weighted Factor Remark


Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

8. Miscellaneous Steel ( Code : C13800 / Unit : Ton, M3 )

Stage Weighted Factor Remark


Installation 80
Punch Clear / Final Inspection 20
Total 100
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 5 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)

9. Fabrication of Steel Structure ( Code : C13900 / Unit : Ton )

Stage Weighted Factor Remark


Raw Material Inspection 30
Cutting 10
Welding 25
Painting Inspection 25
Delivery at Site 10
Total 100

10. Steel Shelter ( Code : C13A00 / Unit : Ton, M2, M, Nos )

In the case of steel structure work, apply to the below table. ( Code : C13A10, C13A20 )
Stage Weighted Factor Remark
Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.

With the except of steel structure work, apply to below table. ( Code : C13A30 )
Stage Weighted Factor Remark
Work Completion 80
Punch Clear / Final Inspection 20
Total 100

11. Demolition ( Code : C13Y00 / Unit : Ton )

Stage Weighted Factor Remark


Work Completion 80
Punch Clear / Final Inspection 20
Total 100

12. Others ( Code : C13Z00 / Unit : Ton )

Stage Weighted Factor Remark


Work Completion 80
Punch Clear / Final Inspection 20
Total 100
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 6 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)