Measurement of Payment (Steel Structure)
Measurement of Payment (Steel Structure)
:
MEASUREMENT
Rev. No. : 2
OF Page : 1 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)
MEASUREMENT
OF
PAYMENT
PROJECT NAME :
CLIENT :
SITE :
2 17-Sep-2015 Revision
1 31-Oct-2014 Revision
MEASUREMENT OF PAYMENT
(Steel Structure Work)
This measurement of payment(steel structure work) shall be applied for measurement of (construction
direct cost for) Subcontractor Progress Payment.
The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.
Unit Price is identified according to each contract between Contractor and Subcontractors.
Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.
Contents
3.
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 3 of 6
PAYMENT Date : 17-Sep-2015
(Steel Structure Work)
2. Erection of Equipment Support Structure / Other STR ( Code : C13200 / Unit : Ton )
In the case of steel structure work, apply to the below table. ( Code : C13A10, C13A20 )
Stage Weighted Factor Remark
Installation 60
Alignment / Bolting 15
Inspection(Incl. Grouting Work) 15
Punch Clear / Final Inspection 10
Total 100
*Note : Progress Measurement of chipping/padding shall not exceed 10% of total installation.
With the except of steel structure work, apply to below table. ( Code : C13A30 )
Stage Weighted Factor Remark
Work Completion 80
Punch Clear / Final Inspection 20
Total 100