Doc. No.

:
MEASUREMENT
Rev. No. : 2
OF Page : 1 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

MEASUREMENT
OF
PAYMENT

(Mechanical Work)

CONTRACTOR JOB NO. : XXXXX

PROJECT NAME :

CLIENT :

SITE :

2 17-Sep-2015 Revision

1 31-Oct-2014 Revision

REV. DATE DESCRIPTION PRPD CHKD APPD QA CLIENT


Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 2 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

MEASUREMENT OF PAYMENT
(Mechanical Work)

This measurement of payment(mechanical work) shall be applied for measurement of (construction


direct cost for) Subcontractor Progress Payment.

The calculation for Progress Payment is as below:


Progress Payment = Work Quantity * Unit Price * Weighted Factor of applicable Stage/Step

The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.

Unit Price is identified according to each contract between Contractor and Subcontractors.

Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.

Contents

1. Vessel ( Code : C15100 , Unit : Ton )


2. Tray Assembling ( Code : C15210 , Unit : M2 )
3. Mechanical Internal Assembling ( Code : C15220 )
4. Filling/Packing ( Code : C15230, Unit : M3 )
5. Refractory & Lining ( Code : C15240 )
6. Platform & Support ( Code : C15250, Unit : Ton )
7. Heat Exchanger ( Code : C15300, Unit : Ton )
8. Air Fin Cooler ( Code : C15310, Unit : Ton )
9. Storage Tank ( Code : C15400, Unit : Ton )
10. Cooling Tower ( Code : C15510, Unit : Ton )
11. Crane and Hoist ( Code : C15520, Unit : Ton )
12. Conveyor (Excluding PCS) ( Code : C15530, Unit : Ton )
13. Others – General Machinery ( Code : C155Z0, Unit : Ton )
14. Rotary Machinery ( Code : C15600, Unit : Sets )
15. Combustion Equipment ( Code : C15700 )
16. Packaged Equipment ( Code : C15800 , Unit : Ton )
17. Water Treatment System ( Code : C15900 , Unit : Ton )
18. Miscellaneous Equipment ( Code : C15A00 , Unit : Ton )
19. Grouting Work ( Code : C15B10 , Unit : M3 )
20. Equipment Heavy Lift ( Code : C15W00, Unit : Set )
21. Demolition ( Code : C15Y00, C15Z00 , Unit : Ton )
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 3 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

1. Vessel ( Code : C15100 , Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

2. Tray Assembling ( Code : C15210 , Unit : M2 )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

3. Mechanical Internal Assembling ( Code : C15220 )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15221 : Demister for Vessel (Unit : M2)
- C15222 : Mechanical Internals (Unit : Ton)

4. Filling/Packing ( Code : C15230, Unit : M3 )


Stage Weighted Factor Remark
Erection 80
Punch Clear / Final Inspection 20
Total 100
[ Applied Sub Code ]
- C15231 : Metal Packing
- C15232 : Ceramic Packing
- C15233 : Catalyst Powder
- C15234 : Liquid
- C15235 : Resin
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 4 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

5. Refractory & Lining ( Code : C15240 )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15241 : Brick (Unit : Pcs)
- C15242 : Castable (Unit : M3)
- C15243 : Resin (Unit : M2)
- C15244 : Anchor Support (Unit : Ton)

6. Platform & Support ( Code : C15250, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15251 : Platform
- C15252 : Support

7. Heat Exchanger ( Code : C15300, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15320 : Shell & Tube H/E (Including Double Pipe H/E)
- C15330 : Hair-pin Tube H/E
- C15340 : Plate type H/E
- C15350 : Cold Box
- C15360 : Electrical Heater
- C153Z0 : Others
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 5 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

8. Air Fin Cooler ( Code : C15310, Unit : Ton )


Stage Weighted Factor Remark
Erection 50
1 Alignment & Grouting
st
20
Final Alignment 20
Punch Clear / Final Inspection 10
Total 100

9. Storage Tank ( Code : C15400, Unit : Ton )


Stage Weighted Factor Remark
Erection (Including NDE/PWHT) 70
Pressure Test & Coating 20
Punch Clear / Final Inspection 10
Total 100
* In case coating is included in Scope of Work

10. Cooling Tower ( Code : C15510, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Alignment 20
Punch Clear / Final Inspection 10
Total 100

11. Crane and Hoist ( Code : C15520, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Load Test 20
Punch Clear / Final Inspection 10
Total 100

12. Conveyor (Excluding PCS) ( Code : C15530, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Alignment & Grouting 20
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 6 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

Punch Clear / Final Inspection 10


Total 100

13. Others – General Machinery ( Code : C155Z0, Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

14. Rotary Machinery ( Code : C15600, Unit : Sets )


Stage Weighted Factor Remark
Erection 50
1 Alignment & Grouting
st
20
Final Alignment 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15610 : Centrifugal Compressor
- C15620 : Reciprocating Compressor
- C15630 : Rotary Compressor
- C15640 : Air Compressor
- C15650 : Centrifugal Pump
- C15660 : Reciprocating Pump
- C15670 : Proportioning Pump
- C15680 : Rotary Pump
- C15690 : Sea Water Pump
- C156A0 : Fire Water Pump
- C156B0 : Vacuum Pump / Vacuum Compressor
- C156C0 : Blower and Fan
- C156D0 : Generator (STG/GTG)
- C156E0 : Agitator and Mixer
- C156Z0 : Others

15. Combustion Equipment ( Code : C15700 )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100
[ Applied Sub Code ]
- C15710 : Fired Heater (Reformer)
Doc. No. :
MEASUREMENT
Rev. No. : 2
OF Page : 7 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)

- C15720 : Boiler
- C15730 : Flare Stack
- C15640 : Incinerator
16. Packaged Equipment ( Code : C15800 , Unit : Ton )
Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

17. Water Treatment System ( Code : C15900 , Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

18. Miscellaneous Equipment ( Code : C15A00 , Unit : Ton )


Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100

19. Grouting Work ( Code : C15B10 , Unit : M3 )


Stage Weighted Factor Remark
Grouting 90
Punch Clear / Final Inspection 10
Total 100

20. Equipment Heavy Lift ( Code : C15W00, Unit : Set )


Stage Weighted Factor Remark
Erection Completed 100
Total 100

21. Demolition ( Code : C15Y00, C15Z00 , Unit : Ton )


Stage Weighted Factor Remark
Demolition 90
Final Inspection 10
Total 100