Measurement of Payment (Mechanical Work)
Measurement of Payment (Mechanical Work)
:
MEASUREMENT
Rev. No. : 2
OF Page : 1 of 7
PAYMENT Date : 31-May-2018
(Mechanical Work)
MEASUREMENT
OF
PAYMENT
(Mechanical Work)
PROJECT NAME :
CLIENT :
SITE :
2 17-Sep-2015 Revision
1 31-Oct-2014 Revision
MEASUREMENT OF PAYMENT
(Mechanical Work)
The measurement of Work Quantity is referred to “appendix E (Definition and Measurement for Work)
– Sec. IV Appendix – Overseas standard contract and ITB” and calculated by discipline.
Unit Price is identified according to each contract between Contractor and Subcontractors.
Construction discipline is divided to each Work Stage/Step and Weighted Factor is decided by the
Work Stage/Step. Refer to following contents for Weighted Factor of Work Stage/Step.
Contents
- C15720 : Boiler
- C15730 : Flare Stack
- C15640 : Incinerator
16. Packaged Equipment ( Code : C15800 , Unit : Ton )
Stage Weighted Factor Remark
Erection 70
Inspection 20
Punch Clear / Final Inspection 10
Total 100