Professional Documents
Culture Documents
Construction Specifications For Duct Fiber Optic Cable Communication Rou...
Construction Specifications For Duct Fiber Optic Cable Communication Rou...
Construction Specifications For Duct Fiber Optic Cable Communication Rou...
Confidential
Content
Confidential 1
1. Duct FOC technical proposal
1.1、Duct route Re-measurement
1.1.1、Duct route re-measurement should be led by appointed location approved by the related ministries
and local authorities.
1.1.2、 Ensuring duct route is safe and reliable, constructing and maintaining easily.
1.1.3 、The duct route re-measurementshould be based on the approved construction design. Itwill
check and ratify the route’s detail directions, locations and methods of laying the duct.
1.1.4 、Check and ratify the exact locations, quantity and treatment measure of the adopted prevention
measurewhen duct is crossing obstacle and special route section, such as railways, main roads,
underground duct etc.
1.1.5、Check and ratify the location of the manhole (handhole) and the arrangement of the pipe.
1.2.1、Road surface excavation: The surface of cement and asphalt roads need to be cut by the cutting
machine and the cutting line shall be straight while the width is as required in the design.
1.2.2 、Depth of pipe burying
Note: The depth of duct trench should meet the requirement of trench depth above according to
Confidential 2
the number of pipe and its arrangement method.
1.2.3 、Duct trench
Confidential 3
1.4 Special road section handling
Across bridge
Confidential 4
Mechanical drilling is adopted for crossing main road and railway as the following diagram:
Confidential 5
1.5.8、If the manhole/handhole is located in city area, its lid must be 1-2cm higher than the soil
surface and 3-5cm higher if located on the sidewalk of highway. But if it is located in the fields,
orchards, the lid must be 30cm higher than the soil surface.
Confidential 6
1.7、Sub-duct laying
It consists of four Φ32/28mm plastic sub-duct in one PVC pipe. One Sub-duct can
accommodate only one line of FOC. The Sub-duct must be inserted into the intended pipe based
on the requirement, and inserted into the relative pipe according to the route direction at turning
handhole, and 8-10cm of sub-duct is spared in every handhole.
1.11、FOC splicing
refer to the technical requirement
of direct buried FOC
A. “Melting connection” is
adopted as the fiber splicing method.
In FOC splicing, joint box is used to
protect FOC connection, distribution
and fiber joint sealing.
B. FOC formula and joint location should be checked before splicing FOC, and spare enough
FOC to meet the requirement. After ensuring that there is no abnormal condition such as fiber core
broken during the laying process, then process the splicing according to the serial of fiber colors,
and avoid wrong splicing.
C. Strength member placed at the FOC joints must be firmly set and reliable to avoid damage
from external force to FOC,
D. After FOC has been firmly installed; the minimum curvature radius must not be 10 times
smaller than its outer diameter.
E. The average splicing attenuation in both sides of the fiber should be ≤0.08dB.
Confidential 8
1.13、Jointbox installation diagram
Confidential 10