FK4219 - Electrical - Primary Protection Test - 61
FK4219 - Electrical - Primary Protection Test - 61
FK4219 - Electrical - Primary Protection Test - 61
Version 6.0
Power Segment
Primary protection tests Issued 01/2022
System Information
Group : Common auxiliaries System : Medium voltage (MV)
Equipment code : Cabinet:
General preconditions
No. Description Result/Remarks Done Signature
MV cables are connected to MV switchgear and
1
alternator terminal box
HIPOT tests are done for MV cables, log files
2
are available
3 Loop checks are done for CTs and VTs, log files are available
(AA) No load data and curve comparison between FAT and SAT.
No. U1x100%FAT Ie [A] FAT U1x100%SAT Ie [A] SAT 1,60
1 0,07 0,01 0,11 0,01
1,40
2 0,25 0,48 0,25 0,45 1,20
3 0,50 1,16 0,50 1,17 1,00
4 0,70 1,75 0,70 1,80 0,80
5 0,95 2,64 0,95 2,74 0,60
6 1,00 2,94 1,00 3,02 0,40
7 1,10 3,19 1,10 3,35 0,20
(C) Differential protection test (ANSI 87G) outside differential protection zone
Preconditions:
- AVR disconnected
- NE switch of alternator open
No. Description Result/Remarks Done Signature
(D) Differential protection test (ANSI 87G) inside differential protection zone
Preconditions:
- AVR disconnected
- NER switch of alternator open
No. Description Result/Remarks Done Signature
(E) Earth- fault differential test (ANSI 87N) outside alternator protection zone - ONLY OPTIONAL
Preconditions:
- AVR disconnected
- Alternator CB is open
- NER switch of alternator closed in manual remote / local mode.
(F) Earth- fault differential protection test (ANSI 87N) within alternator protection zone
Preconditions:
- AVR disconnected.
- Alternator CB is open.
- NER of alternator closed in manual remote / local mode.
3 Start engine
6 Start engine
(G) Earth- fault protection test with Open Delta VT (ANSI 59N)
Preconditions:
- AVR disconnected
- Alternator CB is open
- NER switch is open
Note: This test may fail since earth fault current function (ANSI 87N) may work before open delta function works. To avoid
this, either bypass protection function related to 87N or put short links on both 87N CT terminals
(H) Undervoltage test (ANSI 27, to be carried out after synchronization on black MV bus bar)
Preconditions:
- AVR connected and in operation
- Alternator CB opened in operating position
- NER switch of alternator is open
- MV bus bar is black
No. Description Result/Remarks Done Signature
(I) Underfrequency test (ANSI 81, to be carried out after synchronization on black bus bar)
Preconditions:
- AVR connected and in operation
- Alternator CB opened in operating position
- NER switch of alternator is open
- MV busbar is black
4 Close alternator CB
(J) Overfrequency test (ANSI 81, to be carried out after synchronization on black bus bar)
Preconditions:
- AVR connected and in operation.
- Alternator CB opened in operation position.
- NER switch of alternator is open.
- MV Busbar is Black.
6 Close alternator CB
(K) Reverse Power Test (ANSI 32R, to be carried out in grid parallel operation) - ONLY OPTIONAL
Preconditions:
- AVR connected and in operation
- NER is in auto remote mode or locally closed if remote option not available
- Genset is synchronized to live busbar
(L) Overcurrent Protection Test (ANSI 51, to be carried out in grid parallel operation) - ONLY OPTIONAL
when direction is set in relay - Backup- test for differential protection
Preconditions:
- AVR connected and in operation
- NER is in auto remote mode or locally closed if remote option not available
- Genset is synchronized to live busbar
Remarks
Signatures
Date
Name
Signature
Position
MAN Energy Solutions SE Customer