BL QUESTION 4A Cost Plan and Cost Checking
BL QUESTION 4A Cost Plan and Cost Checking
BL QUESTION 4A Cost Plan and Cost Checking
The following table shows the cost analysis of selected elements for a 6-storey office
building, which has been constructed in Pahang, tendered in October 2019. A 9- storey
building of similar category is proposed to be tendered in Marang, Terengganu in November
2023. Several elements need to be adjusted to suit the new project requirements of the
proposed building. Calculate new cost targets for the following elements.
Calculate new cost targets for each element based on the following information:
(20 marks)
QUESTION 2
Datok Rizal has engaged an architect to prepare a bungalow design. The cost limit for the
bungalow has been set at RM 2.2 million. When all elements have been cost-checked, it was
found that the cost limit is lower by RM 170,000.00. The cost check of the roof element
shows that the design is RM70,000.00 lower its cost target based on the specification given.
Propose and elaborate the remedial actions in such situation.
(10 marks)