Duration
No. Activities Manpower Equipment Remark
(day)
I PREPARATION WORK
Main crane
- Gate pass docmuments
Truck
3 Crane mob, assbly, load test and set at lifting position (Incl. JSA approved) 1 - Liftiting plan, MoS, JSA
Trailer
- Driver licence, quipment cert….
Folk lift
4 Mob labor, equipment and tools to site. Electr cable connection and arrangement for distribution panel 1 Gate pass documents
Plastic canvas
5 Removable Rain Protection Structure installation on top of HTER 0.5
Scaffold
Rigger : 2
Truck crane: 1
6 Transfer Support Ring to site 1 Crane operator: 1 Gate pass documents
Forklift: 1
Forklift operator: 1
7 Installation of scaffolding at platform +11.6m to HTER top flange 1 Scaffolder : 4 Safety harness: 4 200 m3 scaffoding
8 Installation scaffolding at Container, up to top flange 2 Scaffolder : 6 Safety harness: 6 600 m3 scaffoding
1 Shut down 0
Rigger: 2
4 Crane ready for operation 0
Crane operator: 1
Foreman: 1
Mobile Crane 250 Tons: 1
Hepler: 4
11 HTER Top Cover lifting (day time only) 1 Palang 10 Tons: 1 Crane required ≥160T
Rigger: 4
Safety harness: 10
Crane operator: 1
Foreman: 1
Torque wrench (<250 Nm): 2
13 Loosening M20 to seal stuffing box inner shell 1 Hepler: 2
Handtool, Spanding tool
Fitter: 2
M30 SS bolt: 8
Foreman: 1 SS shim: 8
14 Use M30 bolts to jack up Tube bundle in order to ensure tube buldle totally released 1 Hepler: 4 Caliper: 4 ( 1 at least)
Fitter: 4 Dial gauge: 8
Hand tools kit: 4
20 Cut and remove 16 pieces of liner upper part of insulation box (no.211) 1.5
Page 2 of 5
Foreman: 1 Cutting machine : 6
Fitter : 6 Grinding machine: 4
Duration
No. Activities Manpower Equipment Remark
(day)
21 Remove existing ceramic fiber of outter chamber 0.5 Foreman: 1 Cutting machine : 6
Fitter : 6 Grinding machine: 4
Hepler: 4 Safety Harness: 10
22 Open 3 holes (25x25mm) for checking the middle chamber 0.5
23 Cut and remove Linner lower part (212) ( 150mm from the top) 1.5
Fitter : 1
24 Backing strip cutting, rolling for the Linner lower part (212) 0.5 Cutting machine : 1
Hepler: 1
25 Tack Weld the Backing strip to the Linner lower part (212) 0.5
Cutting machine : 6
26 Insert and compress new ceramic fiber to the middle chamber 1 Foreman: 1
Grinding machine: 4
Fitter : 6
Welding machine: 2 Backing gas argon
Hepler: 4
Safety Harness: 10
27 Grinding and bevel at craked welding point between linner lower part (of Shell - no.212) and ellipsoidal head 1 Welder: 4
Face mask: 10
28 Weld and PT work the linner lower part (of Shell - no.212) and ellipsoidal head 1.5
29 Re-welding and PT work for the Linner lower part (212) 1 NDT inspector
31 Insert and compress the new ceramic fiber to the outter chamber 1 Foreman: 1
Cutting machine : 4
Fitter : 4
Grinding machine: 4
Hepler: 4
Welding machine: 2
Welder: 4
32 Fitting and Welding, PT work for 16 pieces of bottom plate 1.5 Safety Harness: 10
NDT Inspector
38 Welding, check straightness and PT work for inner part 1 Cutting machine : 6
Grinding machine: 4
Foreman: 2
Welding machine: 2
Fitter : 10
Handtool
Hepler: 4
Safety harness: 16
Welder: 4 Backing gas argon
Hydraulic jack 5 tons: 2
Page 3 of 5 Rigger: 2
Hydraulic jack 10 tons: 2
Crane operator: 1
Mobile crane: > 400 tons
NDT inspector
Duration
No. Activities Manpower Equipment
Cutting machine :6 Remark
(day) Grinding machine: 4
Foreman: 2
Welding machine: 2
Fitter : 10
Handtool
39 Cut and insert the new ceramic fiber on the inner part and compress to the bottom of TB 1 Hepler: 4
Safety harness: 16
Welder: 4 Backing gas argon
Hydraulic jack 5 tons: 2
Rigger: 2
Hydraulic jack 10 tons: 2
Crane operator: 1
Mobile crane: > 400 tons
40 Trial fit, fit up and tack weld Outer bottom part to the Tube Bundle 1 NDT inspector
41 Adjustment, Welding & check straightness and do PT for W38 Joint of Outter part 0.5
42 Insert the new ceramic fiber on the outer part and compress to the bottom of TB 0.5
44 Rotating the Tube Bundle and Weld the remain location of W39 - Do PT 0.5
46 Final inspection and ready for installation into the Pressure Shell 0.5
51 Inlet tubes Plugs removal and closing M40 caps of access tube stuffing box inner shell 0.5 Foreman: 2
Mobile crane ≥160 tons
Fitter : 4
Torque wrench (<250 Nm): 2
Hepler: 4
Handtool
Rigger: 2
Safety harness: 12
Scaffolder : 2
52 HTER Top Cover lifting / re-installation 0.5 Crane operator: 1
Page 4 of 5 Foreman: 2
Fitter : 6
Hepler: 4
Duration
No. Activities Manpower Equipment Remark
(day)
58 Removal of scaffolding from platform at hot spot level to HTER top flange 1
Page 5 of 5