Professional Documents
Culture Documents
Adobe Scan Jan 31, 2023
Adobe Scan Jan 31, 2023
Adobe Scan Jan 31, 2023
Date: 3/0/-20 23
S.No./NNB/Projects/Drainage/2022-2/D- I
to be
Subject: -Various issues of master drainage project Bharatpur,
discussed/resolved prior to or during course of its execution.
Ref: - Construction/Rehabilitation of City Flood Control Drain (CFCD), Ranjeet
drains in Deficient areas with
Nagar Flood Control Drain (RNFCD) and Storm
water
Sir,
traversing the total distance of 300 chains, it joins the main drain (unit-1) at
ch.206. With the F.S.L. of C.F.C.D (R.L. 558.70 ft.) is 0.5ft. Higher than the
F.S.L. of main drain (558.20 ft.) at the aforesaid confluence point ensuring no
back water of main drain in to C.F.C.D.". In DPR report FSL of Main Drain
has shown RL 558.20 ft but it is has mentioned 565.00 ft (172.212 Mtr.) in WRD
records. In TENDER DOCUMENT drawing CFCD invert level has provided
RL 170.420 Mtr. (At Ch. 8642), presently it has lowered down by 0.55 mtr i.e.,
169. 916 Mtr. Flood water may enter in Bharatpur City. At this location
drawing showing structure to be constructed for safe discharge of water from
CFCD in to Main Drain, has not provided in DPR/ TENDER DOCUMENT.
BMC
BMC
13. Similarly, Heeradas- Pushpvatika drain has proposed in the private land
along NH21 but no such drawing revenue map overlapped NH ROW, drain
alignment and private land provided in DPR.
14. In design drawing of open drain height of vertical walls has finalised but how
meet out problem of high or low ground level in vicinity of drain has
not provided.
15. In the lining work of canal, it has observed that bed of canal is much below
about 3.5 mtr) to nearby ground and water table is higher than bed level,
hydrostatic pressure and swelling of soil exhibiting pressure on slopes and
bed of canal. Safety measures shall be taken in construction of canal as per
manual for canal lining (GOI) copy enclosed.
16. Heeradas- Pushpvatika drain crossing Ram Nagar Do Mora canal at CB 262
at this location what arrangement has proposed not shown in DPR as well as
in TENDER DOCUMENT.
17. Similarly, drainage of L.B. Shastri Nagar and Malipura of Sewar has proposed
in to Alan Canal. L section and chainage of this canal has not provided in
DPR/ TENDER DOCUMENT. This canal has been levelled by local resident
beyond Sarson Anusandhan Kendra to meeting point of RNFCD and no
provision has taken in DPR and TENDER DOCUMENT for its de-silting and
making its profile as per WRD design.
18. CFCD construction is being taken
up in covered structure from Kali ki Bagichi
to Jagheena Gate. Its
length is 4845 Mtr. As per information available there are
only 4 nos. of de-silting chamber have been taken up in this length. There is
no specific lighting and ventilation systems has provided. During course
cleaning ventilation and lighting systems are must for workers health and
hygiene.
19. Inspection chambers to inspect of water flow and situation of
material, dissolved particles and status of drain
floating
intervals are also needed.
functionality
at particular
20. Similarly, in Pushpvatika Drain recently a
length
open of drain has been
modified into covered drain. It needs also similar treatment
above. Moreover that traffic
as discussed
plying
this covered portion. Because, at
arrangement is also to be
provided with
some stretches.
present suffice road width is not available in
21. Inlet details with its section and
level at which
during course of CFCD walls construction.opening
for inlet drain to
be
left
Otherwise it may cause of
problem to create an opening after completion of work.
22. In present scenario
of soil.
Bharatpur city facing the major problem of salt properties
Owing to it all
types of structures deteriorated. We have taken up
CFCD project in RCC structure, which may also face this kind of our
BMC
BM
problem after two to five years. To prevent CFCD, RCC and CC structures
from salt problem its treatment during course of work is must.
24. To prevent concrete from salty and increase durability, safety measures can be
adopted. Any expert solution in this context can be considered during course
of work.
In view of above facts and to resolve it, a joint meeting has been convened
with Executing Agency and Project Management Consultant on 08.02.2023 at
3 T | 20 23
(Bahadur Singh)
Executive Engineer (Projects)
Nagar Nigam Bharatpur
S.No/NNB/Projects/Drainage/2022-23/D- 2627 Date: 8/ 0/ 24S
Copy to following for kind information:
1. Hon'ble
Mayor, MC Bharatpur.
2. Chief
Engineer, UIT, Alwar.
3. Commissioner, MC, Bharatpur.
4. SE, MC, Bharatpur.