Professional Documents
Culture Documents
Hazap
Hazap
Hazap
HAZOP REPORT
S19155-DAR-RX-001
Rev. A
REVISION RECORD
Kamran Shahzad
A 01-08-19 Draft Report – Issued for review Bilal Niazi
Khan Hussain
Vanguard Solutions Middle East (a GEXCON Company) Phone +971 4 367 1406
Office no. 18, AG-PF-24, Silver Tower Fax +971 4 366 4588
JLT, PO Box 35314 Email admin@vanguardsolutions.me
Dubai, UAE Website www.gexcon.com
FSA Treatment Facility – Ma’aden Wa’ad Al Shamal Phosphate Company – Turaif
HAZOP Report
LIST OF ACRONYMS
Abbreviation Description
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY
This Report contains the findings from HAZOP Workshops conducted for Ma’aden Wa’ad
Al Shamal Phosphate Company project FSA (Flourosilicic Acid) Treatment Facility.
The Hazard and Operability (HAZOP) Workshops were held for two days on July 24th &
25th 2019 at MWSPC office (Admin Building) Turaif, Saudi Arabia.
The HAZOP team comprised personnel from MWSPC Engineering, Project Management,
Instrumentation & Operations, and with facilitation by HAZOP Chairman, from Vanguard
Solutions Middle East.
HAZOP study was carried out for FSA Treatment Facility to address the Hazard &
Operability issues by identifying credible process deviations and evaluation of potential
hazards arising from the facility. It shall be noted that HAZOP study did not address any
design review, nor it is used to introduce additional equipment / further modifications to
increase operational flexibility etc. Such requests were recommended for outside HAZOP
review, unless it could be demonstrated that the review is necessary to address an
unacceptable safety concern or to enable the process to be operated according to the
design specification.
HAZOP study was carried out using conventional "Guideword based HAZOP"
methodology where specific parameters and associated guidewords are used.
Below are some of the important considerations followed over the course of this HAZOP
process.
- Scope of the HAZOP study has been limited to the current design as reflected on
P&IDs (IFC) made available to the HAZOP team during session.
- Risk ranking has been completed in accordance with the 5X5 HSE Risk Matrix
provided by MWSPC. While assigning probability and severity, the ‘worst case’ or the
‘governing case’ severity in a category is used. In general, ‘Safety’ is the ‘governing
case’.
- Where appropriate, the HAZOP team made recommendations either to minimize
safety / environmental impact, enhance operability or to evaluate / review further
certain aspects of the design to strengthen existing safeguards.
- In total seven (07) recommendations were made and proposed actions. The
recommendations were also risk ranked to facilitate prioritization of actions and their
close-out. All seven (07) recommendations were risk ranked for the ‘Medium’ risk
consequences. It is suggested that the HAZOP recommendations should be
completed on priority basis and should be in place before the facility is operated, for
the safe & reliable operation. Complete list of HAZOP recommendations is included in
table below;
Table 1-1: HAZOP Recommendations
4. Consider stopping of reaction feed and sparging blower (3600- PMT Medium
BLW-00/101) when exhaust fan damper is in closed position
through interlock.
5. Consider stopping of exhaust fan (3600-FAN-100) if discharge PMT Medium
damper (3600-ADVFXA-004) is closed through interlock.
6. Consider stopping of reaction feed and sparging blower (3600- PMT Medium
BLW-00/101) when exhaust fan (3600-FAN-100) is tripped
through interlock.
7. Consider providing new pressure transmitter at suction of PMT Medium
exhaust fan (3600-FAN-100) with high high-pressure interlock
to stop reaction feed and sparging blower (3600-BLW-
100/101)
8. Consider providing interlock for closing HV-7302 in case of PMT Medium
sludge pump (3600-PMP-300) tripping/stoppage to avoid
damage of sludge pump (3600-PMP-300) due to reverse flow
9. Consider providing interlock for tripping of CTSFT pump PMT Medium
(3600-PMP-200) in case of low low seal water pressure
10. Update P&ID (MD-512-3600-EG-PR-PID-3002) to reflect seal PMT Medium
water battery limit valve as normally open (NO) and isolation
valve on CTSFT pump (3600-PMP-200) as normally open
(NO).
11. Ensure operator/working personnel carry portable gas Operation Medium
detectors (O2 and CO2) all the time and evacuate area in
case of oxygen deficiency and update ERP accordingly. Also
ensure area if free of CO2 before startup of FSA treatment
facility.
12. It is recommended to conduct LOPA workshop for assessing Engineering Medium
the SIL level of all proposed interlocks and already
implemented interlocks in the DCS
2. INTRODUCTION
The design is to feed the calcium carbonate to react with 65% of the feed flourosilicic
acid feed, i.e. 53% excess of flourosilicic acid. The reaction pH is acidic.
Reactors feed is split with 60 to 70% going to the first reactor with the remaining going to
the second reactor. The reaction sludge is pumped to the top of the gypsum stack where
the solids in the sludge settle with the stacked gypsum and the sluiced water returns to the
decant water pond for reuse to slurry fresh gypsum in PAP.
The intention defines how the part of the process (being studied) is expected to
Intention operate. This can take a number of forms and can be either descriptive or
diagrammatic.
These are the reasons why deviations might occur. Once a deviation has been
Causes
shown to have a conceivable or realistic cause, it can be treated as meaningful.
Consequences These are the results of the deviations should they occur.
Hazards These are the consequences which can cause damage, injury or loss.
Guideword Description
Negation of the design intent (e.g. no flow when there should be;
No (Flow)
no pressure when there should be)
Less
Less of a physical property than there should be - Quantitative
(Flow, Pressure, Temp & decrease (e.g., lower flow rate than there should be)
Level)
Guideword Description
More
More of a physical property than there should be - Quantitative
(Flow, Pressure, Temp & increase
Level)
Reverse (Flow) Logical opposite of the design intent (e.g., reverse flow)
Other than Composition/Contamination /Deposition
Other Operations
Part of (Startup/Shutdown, Maintenance/Inspection, Isolation / Purging /
Testing etc.
Part of HSE
3.5. Methodology
A description of the approach used by the HAZOP Team is provided below. The process
systems are divided into Nodes. Each Node represents the system to be analysed. For
each Node that is defined the following process is carried out:
1. The process lines covered by the Node highlighted were highlighted on the relevant
P&IDs
2. A process engineering overview was provided to the HAZOP Team
3. The Node definition process parameters were input and checked for consistency.
4. The Deviation being assessed is selected. Brainstorming of all causes within the
Node for the Deviation in question are identified and recorded. If no causes are
identified, then this is stated as “no Credible Causes identified by the HAZOP team”
5. Once all the causes are recorded, each cause is individually analyzed and the
relevant consequences (Hazardous or Risk Events) are detailed without any benefit of
any installed safeguards in place. Wherever possible, these are recorded in a time
sequential manner so that a full history of the development of the consequences could
be recorded. If process functionality is available (and had not failed as defined by the
cause description) then these functions are considered to be still active and were not
recorded as they provide inherent designs.
6. The severity of any safety & environmental hazardous condition arising is recorded
using the definitions in MWSPC HSE Risk matrix. (Note: In some cases,
consequences included multiple Risk Events. If this is the case the highest severity
ranking of the safety & environmental hazardous condition is recorded in the required
field).
7. Safeguards that are defined on the P&ID’s or in associated issued Project documents
are then recorded.
8. Any recommendation required are then added to the worksheet and assigned to a
relevant company and department.
9. The next cause is then analyzed in the same way until all the causes, consequences
and safeguards had been assessed.
10. At this point the first cause and subsequent causes within the deviation are reviewed
with all defined safeguards in place for the cause in question and the likelihood of the
consequences achieving their hazardous result(s) (as defined in the Risked Events) is
recorded using the likelihood level guidance provided in MWSPC HSE Risk Matrix.
11. Once completed the next deviation is selected and the whole process was repeated
until all Nodes had been fully assessed.
The HAZOP Chairmen and HAZOP Team reviewed the wording of each entry into the
HAZOP recording system to ensure that sufficient information and understanding is
provided to meet the client requirements.
For each deviation identified as relevant to the node under consideration, the causes,
consequences (risk events) and safeguards are identified on the HAZOP worksheets.
Consequences are divided into safety, environment and commercial, and these are
assigned severity rankings.
Likelihood Description
A Almost certain - Very high, may occur at least several times per year
E D C B A
Likelihood
Node P&ID
Node Design Fluid Design Conditions/Parameters
No. P&ID No. Rev.
1 FSA Treatment Facility MD-512-3600-EG- C03 FSA, CTSFT Charging Pump (With VFD) - 3600-
PR-PID-3001 Decant Water PMP-200
Maximum design flow rate: 51 m3/hr
MD-512-3600-EG- C03 Nominal Flow rate: 39 m3/hr
PR-PID-3002
Operating Pressure: 7 bar
MD-512-3600-EG- C01 Power drive rated: 20 KW
PR-PID-3004 Head: 52.2 M
Reactor - 3600-REA-100/101
Design working/total volume: 379/557 M3
Residence time per reactor: 1 h
5. HAZOP RECOMMENDATIONS
Where appropriate, the HAZOP team made recommendations either to minimize safety /
environmental impact, enhance operability or to evaluate / review further certain aspects
of the design to strengthen existing safeguards.
Risk ranking has been completed in accordance with the 5X5 HSE Risk Matrix provided
by MWSPC. While assigning probability and severity, the ‘worst case’ or the ‘governing
case’ severity in a category is used. In general, ‘Safety’ is the ‘governing case’.
In total seven (07) recommendations were made and proposed actions. The
recommendations were also risk ranked to facilitate prioritization of actions and their
close-out. All seven (07) recommendations were risk ranked for the ‘Medium’ risk
consequences. It is suggested that the HAZOP recommendations should be completed on
priority basis and should be in place before the facility is operated, for the safe & reliable
operation. Complete list of HAZOP recommendations is included in table below:
Table 5-1: HAZOP Recommendations
Recommendations Responsibility Risk Ranking
6. REFERENCES
[1] HAZOP scope of work document for FSA Treatment facility provided by MWSPC.
[2] Lees' Process Safety Essentials, S. Mannan, Elsevier, 2014.
[3] Practical HAZOPs, Trips, and Alarms, D. McDonald, Elsevier, 2004.
[4] HAZOP and HAZAN, T. Kletz, IChemE, 2001.
[5] Guidelines for Hazard Evaluation Procedures, CCPS, AIChE, 2008.
[6] HAZOP: Guide to Best Practice, F. Crawley and B. Tyler, Elsevier, 2015.
[7] Application of HAZOP and What-If Safety Reviews, D. P. Nolan, Noyes, 1994.
[8] BS EN ISO 17776 - HAZOP
[9] IEC 61882 HAZOP Guide [2016]
[10] Loss Prevention in the Process Industries, S. Mannan, Elsevier, 2012.
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
1 FSA 1. No Flow (CTSFT) 1. Tripping of CTSFT pump 1. Stoppage of reaction leading None
Treatment (3600-PMP-200) to decrease pH with no 5 C Medium
Package significant impact
2. Possible drop in reactor level LIT-3201/3202 available with low level 1. Update P&ID MD-512-3600-EG-
leading to sludge pump alarm PR-PID-3002 to reflect tripping of
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) sludge pump at low low (LL)
sludge pump in case of low low level in suction pressure (PIT-4202)
4 D Low PMT
reactor
PIT-4202 available to trip (I-11) sludge
pump at low low suction pressure
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
3. Inadvertent closure of 1. Stoppage of reaction leading None
manual isolation valve in to decrease pH with no 5 C Medium
downstream of CTSFT significant impact
pump 2. Possible drop in reactor level LIT-3201/3202 available with low level
leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
sludge pump in case of low low level in 4 D Low
reactor
PIT-4201 available to trip (I-11) sludge
pump at low low suction pressure
3. Possible damage of CTSFT FQIT-2203 available to trip (I7) CTSFT
pump (3600-PMP-200) due to pump in case of no discharge flow from the
blocked discharge pump 5 C Medium
Open/close indication of HV-7301 available
on DCS
4. Possible CTSFT pump FQIT-2203 available to trip (I7) CTSFT
discharge line rupture due to pump in case of no discharge flow from the
high pressure pump
4 C Medium
Open/close indication of HV-7301 available
on DCS
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
3. Stoppage of reaction leading High pH alarm AIT-1201/1202 available
to increase pH with no AIT-1201/1202 available to stop (I-4 & I-5)
significant impact 5 C Medium
CTFST pump & HV-7301 in case of high
high pH in reactor
3. Inadvertent closure of 1. No reaction will take place if None
manual isolation valve in FSA is not fed leading to off- 5 E Low
FSA line spec product.
2. Possible drop in reactor level LIT-3201/3202 available with low level
leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
3. Stoppage of reaction leading High pH alarm AIT-1201/1202 available
to increase pH with no AIT-1201/1202 available to stop (I-4 & I-5)
significant impact 5 C Medium
CTFST pump & HV-7301 in case of high
high pH in reactor
3. No Flow (Decant 1. Tripping of decant water 1. High viscosity & solid FIT-2201 available to trip (I-2) CTSFT pump
Water) pump (207ZZ-PMP- contents in reactor and and HV-7301 closure in case of Low Low
101/102/103) potential damage of agitator flow of decant water 4 C Medium
Agitator motor overload protection provided
2. Increase in pH leading to AIT-1201/1202 available to stop (I-4 & I-5)
foaming in reactor and piping CTFST pump & HV-7301 in case of high
and potential damage of high pH in reactor
piping and LOC due to CO2 3 C Medium
gas and reaction sludge.
Minor environmental damage
and possible injury
2. Spurious closure of FV- 1. High viscosity & solid FIT-2201 available to trip (I-2) CTSFT pump
2201 contents in reactor and and HV-7301 closure in case of Low Low
potential damage of agitator flow of decant water 4 C Medium
Agitator motor overload protection provided
2. Increase in pH leading to AIT-1201/1202 available to stop (I-4 & I-5)
foaming in reactor and piping CTFST pump & HV-7301 in case of high
and potential damage of high pH in reactor
piping and loss of
3 C Medium
containment (LOC) due to
CO2 gas and reaction sludge.
Minor environmental damage
and possible injury
3. Inadvertent closure of 1. High viscosity & solid FIT-2201 available to trip (I-2) CTSFT pump
manual isolation valve in contents in reactor and and HV-7301 closure in case of Low Low
decant water line potential damage of agitator flow of decant water 4 C Medium
Agitator motor overload protection provided
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
4. No Flow (Sludge) 1. Tripping of sludge pump 1. High level in reactor leading LIT-3201 / 3202 available with high level
(3600-PMP-300) to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
2. Spurious closure of HV- 1. High level in reactor leading LIT-3201 / 3202 available with high level
7302 to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
2. Potential sludge pump Open/close indication of HV-7302 available 2. Consider providing tripping of
damage due to block on DCS sludge pump (3600-PMP-300) in
discharge case of high high discharge
4 C Medium PMT
pressure to avoid sludge pump
damage (3600-PMP-300) due to
block discharge
3. Possible Sludge pump Open/close indication of HV-7302 available
discharge line rupture due to on DCS 4 C Medium
high pressure
3. Inadvertent closure of 1. Possible Sludge pump PIT-4202 available to trip (I-11) sludge
4 C Medium
manual isolation valve in damage due to cavitation pump at low low suction pressure
suction line of sludge pump 2. High level in reactor leading LIT-3201 / 3202 available with high level
to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
4. Empty Reactor (3600-REA- 1. Possible Sludge pump PIT-4202 available to trip (I-11) sludge
4 C Medium
100/101) damage due to cavitation pump at low low suction pressure
2. Potential reactor agitators LIT-3201/3202 available with low level
damage (3600-AGI- alarm
100/101/102/103/104/105) LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
5. No Flow (Sparging 1. Tripping of sparging air 1. Possible reaction carryover to AIT-1201/1202 available to stop (I-4 & I-5)
air) blower (3600-BLW-100/101) piping and potential damage CTFST pump & HV-7301 in case of high
of piping and LOC due to high pH in reactor
3 C Medium
CO2 gas and reaction sludge.
Minor environmental damage
and possible injury
2. Inadvertent closure of 1. Possible reaction carryover to AIT-1201/1202 available to stop (I-4 & I-5)
manual isolation valve in piping and potential damage CTFST pump & HV-7301 in case of high
sparging air line of piping and LOC due to high pH in reactor
3 C Medium
CO2 gas and reaction sludge.
Minor environmental damage
and possible injury
2. Possible blowers (3600-BLW- None 3. Consider providing high
100/101) damage due to 4 C Medium discharge pressure protection for PMT
blocked discharge air blowers (3600-BLW-100/101)
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
6. No Flow (Exhaust 1. Closure of Suction damper 1. Possible release of CO2 into None 4. Consider stopping of reaction
gases) (3600-ADVFXA-003) the reactor surrounding area feed and sparging blower (3600-
which will lead to lack of 3 C Medium BLW-00/101) when exhaust fan PMT
oxygen effecting people in damper is in closed position
the surrounding area through interlock
2. Closure of damper (3600- 1. Possible release of CO2 into Damper (3600-ADFXA-001/002) are 4. Consider stopping of reaction
ADFXA-001/002) the reactor surrounding area mechanically locked open feed and sparging blower (3600-
which will lead to lack of BLW-00/101) when exhaust fan PMT
oxygen effecting people in damper is in closed position
the surrounding area through interlock
3 C Medium 12.It is recommended to conduct
LOPA workshop for assessing
the SIL level of all proposed
Engineering
interlocks and already
implemented interlocks in the
DCS
3. Closure of discharge 1. Possible release of CO2 into None 4. Consider stopping of reaction
damper (3600-ADVFXA- the reactor surrounding area feed and sparging blower (3600-
004) which will lead to lack of 3 C Medium BLW-00/101) when exhaust fan PMT
oxygen effecting people in damper is in closed position
the surrounding area through interlock
2. Possible exhaust fan damage None 5. Consider stopping of exhaust fan
due to surging (3600-FAN-100) if discharge
4 C Medium PMT
damper (3600-ADVFXA-004) is
closed through interlock
4. Tripping of exhaust Fan 1. Possible release of CO2 into None 6. Consider stopping of reaction
(3600-FAN-100) the reactor surrounding area feed and sparging blower (3600-
which will lead to lack of BLW-00/101) when exhaust fan PMT
oxygen effecting people in (3600-FAN-100) is tripped
the surrounding area through interlock.
3 C Medium 7. Consider providing new pressure
transmitter at suction of exhaust
fan (3600-FAN-100) with high
PMT
high-pressure interlock to stop
reaction feed and sparging
blower (3600-BLW-100/101)
7. Less Flow 1. Refer to No Flow (all
deviation) in this Node
8. More Flow (FSA) 1. Full opening of FV-2202 1. High level in reactor leading LIT-3201 / 3202 available with high level
to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
9. More Flow (Decant 1. Full opening of FV-2201 1. High level in reactor leading LIT-3201 / 3202 available with high level
Water) to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
10. More Flow (CTSFT) 1. Malfunction of pump VSD 1. High level in reactor leading LIT-3201 / 3202 available with high level
to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
2. Increase in pH leading to AIT-1201/1202 available to stop (I-4 & I-5)
foaming in reactor and piping CTFST pump & HV-7301 in case of high
and potential damage of high pH in reactor
piping and LOC due to CO2 3 C Medium
gas and reaction sludge.
Minor environmental damage
and possible injury
3. High viscosity & solid Agitator motor overload protection provided
contents in reactor and AIT-1201/1202 available to stop (I-4 & I-5)
potential damage of agitator CTFST pump & HV-7301 in case of high
high pH in reactor 4 C Medium
11. Reverse Flow 1. Tripping/Stoppage of sludge 1. Possible sludge pump None 8. Consider providing interlock for
(Sludge) pump damage due to reverse closing HV-7302 in case of
rotation sludge pump (3600-PMP-300)
4 C Medium PMT
tripping/stoppage to avoid
damage of sludge pump (3600-
PMP-300) due to reverse flow
12. Misdirected Flow 1. No Credible cause identified
13. High Pressure 1. Spurious closure of HV- 1. Possible damage of CTSFT FQIT-2203 available to trip (I7) CTSFT
(CTSFT) 7301 pump (3600-PMP-200) due to pump in case of no discharge flow from the
blocked discharge pump 5 C Medium
Open/close indication of HV-7301 available
on DCS
2. Possible CTSFT pump FQIT-2203 available to trip (I7) CTSFT
discharge line rupture due to pump in case of no discharge flow from the
high pressure pump 4 C Medium
Open/close indication of HV-7301 available
on DCS
2. Inadvertent closure of 1. Possible damage of CTSFT FQIT-2203 available to trip (I7) CTSFT
manual isolation valve in pump (3600-PMP-200) due to pump in case of no discharge flow from the
downstream of CTSFT blocked discharge pump 5 C Medium
pump Open/close indication of HV-7301 available
on DCS
2. Possible CTSFT pump FQIT-2203 available to trip (I7) CTSFT
discharge line rupture due to pump in case of no discharge flow from the
high pressure pump 4 C Medium
Open/close indication of HV-7301 available
on DCS
14. High Pressure 1. Spurious closure of HV- 1. Potential sludge pump Open/close indication of HV-7302 available
(Sludge) 7302 damage due to block on DCS 4 C Medium
discharge
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
2. Possible Sludge pump Open/close indication of HV-7302 available
discharge line rupture due to on DCS 4 C Medium
high pressure
15. High Pressure 1. Inadvertent closure of 1. Possible blowers (3600-BLW- None 3. Consider providing high
(Sparging air) manual isolation valve in 100/101) damage due to discharge pressure protection for
sparging air-line at blower blocked discharge air blowers (3600-BLW-100/101)
4 C Medium PMT
discharge or reactor inlet
when one reactor is in
service
2. Blockage of sparging 1. Possible reaction carry over AIT-1201/1202 available to stop (I-4 & I-5)
nozzles to piping and potential CTFST pump & HV-7301 in case of high
damage of piping and LOC high pH in reactor
3 C Medium
due to CO2 gas and reaction
sludge. Minor environmental
damage and possible injury
16. High Pressure 1. Closure of discharge 1. Possible exhaust fan damage None 5. Consider stopping of exhaust fan
(Exhaust gases) damper (3600-ADVFXA- due to surging (3600-FAN-100) if discharge
4 C Medium PMT
004) damper (3600-ADVFXA-004) is
closed through interlock
2. Possible release of CO2 into None 4. Consider stopping of reaction
the reactor surrounding area feed and sparging blower (3600-
which will lead to lack of 3 C Medium BLW-00/101) when exhaust fan PMT
oxygen effecting people in damper is in closed position
the surrounding area through interlock
17. Less Pressure 1. Tripping of CTSFT pump 1. Possible drop in reactor level LIT-3201/3202 available with low level 1. Update P&ID MD-512-3600-EG-
(CTSFT) (3600-PMP-200) leading to sludge pump alarm PR-PID-3002 to reflect tripping of
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) sludge pump at low low (LL)
sludge pump in case of low low level in 4 D Low suction pressure (PIT-4202) PMT
reactor
PIT-4202 available to trip (I-11) sludge
pump at low low suction pressure
2. Spurious closure of HV- 1. Possible drop in reactor level LIT-3201/3202 available with low level
7301 leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
sludge pump in case of low low level in 4 D Low
reactor
PIT-4202 available to trip (I-11) sludge
pump at low low suction pressure
3. Inadvertent closure of 1. Possible drop in reactor level LIT-3201/3202 available with low level
manual isolation valve in leading to sludge pump alarm
downstream of CTSFT damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
pump sludge pump in case of low low level in 4 D Low
reactor
PIT-4201 available to trip (I-11) sludge
pump at low low suction pressure
18. Less Pressure 1. Tripping of FSA pump 1. Possible drop in reactor level LIT-3201/3202 available with low level
(FSA) (23A50-PMP-005/006) leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
4 C Medium
reactor agitators in case of low low level in
reactor
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
2. Spurious closure of FV- 1. Possible drop in reactor level LIT-3201/3202 available with low level
2202 leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
3. Inadvertent closure of 1. Possible drop in reactor level LIT-3201/3202 available with low level
manual isolation valve in leading to sludge pump alarm
FSA line damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
19. Less Pressure 1. Inadvertent closure of 1. Possible Sludge pump PIT-4202 available to trip (I-11) sludge
(Sludge) manual isolation valve in damage due to cavitation pump at low low suction pressure 4 C Medium
suction line of sludge pump
2. Empty Reactor (3600-REA- 1. Possible Sludge pump PIT-4202 available to trip (I-11) sludge
100/101) damage due to cavitation pump at low low suction pressure 4 C Medium
20. Less Pressure 1. Blockage of reactor vent 1. Possible reactor collapses Vent is adequately designed
(Reactor) leading to loss of containment Dike is provided 3 E Low
(LOC) causing possible injury
and environmental impact
21. High Temperature 1. No Safety concern
23. High Level (Sludge) 1. Tripping of sludge pump 1. High level in reactor leading LIT-3201 / 3202 available with high level
(3600-PMP-300) to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
2. Spurious closure of HV- 1. High level in reactor leading LIT-3201 / 3202 available with high level
7302 to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
3. Inadvertent closure of 1. High level in reactor leading LIT-3201 / 3202 available with high level
manual isolation valve in to overflow to sump. Minor alarm
suction line of sludge pump environmental damage LIT-3201 / 3202 available to trip all
4 C Medium
incoming streams in case of high high level
in reactor
Dike is provided
24. High Level (FSA) 1. Full opening of FV-2202 1. High level in reactor leading LIT-3201 / 3202 available with high level
to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
25 High Level 1. Full opening of FV-2201 1. High level in reactor leading LIT-3201 / 3202 available with high level
. (Decant Water) to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
26. High Level 1. Malfunction of pump VSD 1. High level in reactor leading LIT-3201 / 3202 available with high level
(CTSFT) to overflow to sump. Minor alarm
environmental damage LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
27 Less Level 1. Tripping of CTSFT pump 1. Possible drop in reactor level LIT-3201/3202 available with low level 1. Update P&ID MD-512-3600-EG-
. (CTSFT) (3600-PMP-200) leading to sludge pump alarm PR-PID-3002 to reflect tripping of
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) sludge pump at low low (LL)
sludge pump in case of low low level in suction pressure (PIT-4202)
reactor 4 D Low PMT
PIT-4202 available to trip (I-11) sludge
pump at low low suction pressure
2. Spurious closure of HV- 1. Possible drop in reactor level LIT-3201/3202 available with low level
7301 leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
sludge pump in case of low low level in
4 D Low
reactor
PIT-4202 available to trip (I-11) sludge
pump at low low suction pressure
3. Inadvertent closure of 1. Possible drop in reactor level LIT-3201/3202 available with low level
manual isolation valve in leading to sludge pump alarm
downstream of CTSFT damage due to cavitation LIT-3201/3202 available to trip (I9/I12)
pump sludge pump in case of low low level in
4 D Low
reactor
PIT-4201 available to trip (I-11) sludge
pump at low low suction pressure
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
2. Possible drop in reactor level LIT-3201/3202 available with low level
leading to reactor agitators alarm
damage (3600-AGI- LIT-3201/3202 available to trip (I9/I12)
100/101/102/103/104/105) 4 C Medium
reactor agitators in case of low low level in
reactor
28. Less Level (FSA) 1. Tripping of FSA pump 1. Possible drop in reactor level LIT-3201/3202 available with low level
(23A50-PMP-005/006) leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
2. Spurious closure of FV- 1. Possible drop in reactor level LIT-3201/3202 available with low level
2202 leading to sludge pump alarm
damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
3. Inadvertent closure of 1. Possible drop in reactor level LIT-3201/3202 available with low level
manual isolation valve in leading to sludge pump alarm
FSA line damage due to cavitation LIT-3201/3202 available to trip (I9/I12) 4 C Medium
reactor agitators in case of low low level in
reactor
29. Isolation 1. No Safety concern
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
2 Utilities 1. Instrument air failure 1. Inadvertent closure of 1. FV-2201/2202, HV- Refer to No Flow scenario in Node-1 (FSA
battery limit isolation valve 7301/7302 will move to fail Treatment Package)
safe position (closed) that will
lead to No Flow scenario of
Node-1 (FSA Treatment
Package)
2. Tripping of instrument air 1. FV-2201/2202, HV- Refer to No Flow scenario in Node-1 (FSA
system 7301/7302 will move to fail Treatment Package)
safe position (closed) that will
lead to No Flow scenario of
Node-1 (FSA Treatment
Package)
2. Seal water failure 1. Inadvertent closure of 1. Possible mechanical seal PIT-4203 available to trip sludge pump (I- 9. Consider providing interlock for
battery limit isolation valve damage of CTSFT pump 27) in case of low seal water pressure tripping of CTSFT pump (3600-
(3600-PMP-200), Sludge (3600-PMP-300) PMP-200) in case of low low seal PMT
pump (3600-PMP-300) and No safeguard available for CTSFT pump water pressure
Sump pump leading to loss of
containment (LOC) with
minor environmental impact 10.Update P&ID (MD-512-3600-
4 C Medium EG-PR-PID-3002) to reflect seal
water battery limit valve as
normally open (NO) and
isolation valve on CTSFT pump PMT
(3600-PMP-200) as normally
open (NO)
2. Tripping of seal water 1. Possible mechanical seal PIT-4203 available to trip sludge pump (I- 9. Consider providing interlock for
system damage of CTSFT pump 27) in case of low seal water pressure tripping of CTSFT pump (3600-
(3600-PMP-200), Sludge (3600-PMP-300) PMP-200) in case of low low seal
PMT
pump (3600-PMP-300) and No safeguard available for CTSFT pump water pressure
Sump pump leading to loss of
containment (LOC) with
minor environmental impact 10.Update P&ID (MD-512-3600-
4 C Medium EG-PR-PID-3002) to reflect seal
water battery limit valve as
normally open (NO) and
isolation valve on CTSFT pump PMT
(3600-PMP-200) as normally
open (NO)
3. Power Failure 1. Primary power source 1. Shutdown of all electrical None 11.Ensure operator/working
failure equipment’s (Pumps, personnel carry portable gas
Blowers, Fan and Agitators) detectors (O2 and CO2) all the
with potential CO2 release time and evacuate area in case
from reactor vent 3 C Medium of oxygen deficiency and update Operation
ERP accordingly. Also ensure
area if free of CO2 before
startup of FSA treatment facility
Risk
No. Node Deviation Cause Consequences Safeguards Severi Likelihood HAZOP Recommendations By
Ranking
2. Local power failure from 1. Shutdown of all electrical None 11.Ensure operator/working
PAP Sub-Station equipment’s (Pumps, personnel carry portable gas
Blowers, Fan and Agitators) detectors (O2 and CO2) all the
except CTSFT pump (3600- time and evacuate area in case
PMP-200) 3 C Medium of oxygen deficiency and update Operation
ERP accordingly. Also ensure
area if free of CO2 before
startup of FSA treatment facility
2. High level in reactor leading LIT-3201 / 3202 available with high level
to overflow to sump. Minor alarm
environmental damage
LIT-3201 / 3202 available to trip all
incoming streams in case of high high level 4 C Medium
in reactor
Dike is provided
APPENDIX C – CARF
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 1
Problem Statement
Consequence: Possible drop in reactor level leading to sludge pump damage due to cavitation
Update P&ID MD-512-3600-EG-PR-PID-3002 to reflect tripping of sludge pump at low low (LL) suction
pressure (PIT-4202)
Risk Ranking L
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 2
Problem Statement
Consider providing tripping of sludge pump (3600-PMP-300) in case of high high discharge pressure
to avoid sludge pump damage (3600-PMP-300) due to block discharge
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 3
Problem Statement
Cause: Inadvertent closure of manual isolation valve in sparging Air Line at blower
discharge or reactor inlet when one reactor is in service
Consequence: Possible blowers (3600-BLW- 100/101) damage due to blocked discharge
Consider providing high discharge pressure protection for air blowers (3600-BLW-100/101)
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 4
Problem Statement
Consequence: Possible release of CO2 into the reactor surrounding area which will lead to lack of
oxygen effecting people in the surrounding area
Consider stopping of reaction feed and sparging blower (3600-BLW-00/101) when exhaust fan
damper is in closed position through interlock
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 5
Problem Statement
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 6
Problem Statement
Consequence: Possible release of CO2 into the reactor surrounding area which will lead to lack of
oxygen effecting people in the surrounding area
Consider stopping of reaction feed and sparging blower (3600-BLW-00/101) when exhaust fan
(3600-FAN-100) is tripped through interlock.
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 6
Problem Statement
Consequence: Possible release of CO2 into the reactor surrounding area which will lead to lack of
oxygen effecting people in the surrounding area
Consider stopping of reaction feed and sparging blower (3600-BLW-00/101) when exhaust fan
(3600-FAN-100) is tripped through interlock.
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 7
Problem Statement
Consequence: Possible release of CO2 into the reactor surrounding area which will lead to lack of
oxygen effecting people in the surrounding area
Consider stopping of reaction feed and sparging blower (3600-BLW-00/101) when exhaust fan
(3600-FAN-100) is tripped through interlock.
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 8
Problem Statement
Consider providing interlock for closing HV-7302 in case of sludge pump (3600-PMP-300)
tripping/stoppage to avoid damage of sludge pump (3600- PMP-300) due to reverse flow
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 9
Problem Statement
Node 2: Utilities
Consequence: Possible mechanical seal damage of CTSFT pump (3600-PMP-200), Sludge pump
(3600-PMP-300) and Sump pump leading to loss of containment (LOC) with minor
environmental impact
Consider providing interlock for tripping of CTSFT pump (3600-PMP-200) in case of low low seal
water pressure
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 10
Problem Statement
Node 2: Utilities
Consequence: Possible mechanical seal damage of CTSFT pump (3600-PMP-200), Sludge pump
(3600-PMP-300) and Sump pump leading to loss of containment (LOC) with minor
environmental impact
Update P&ID (MD-512-3600- EG-PR-PID-3002) to reflect seal water battery limit valve as normally
open (NO) and isolation valve on CTSFT pump (3600-PMP-200) as normally open (NO)
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 11
Problem Statement
Node 2: Utilities
Consequence: Shutdown of all electrical equipment’s (Pumps, Blowers, Fan and Agitators)
with potential CO2 release from reactor vent
Ensure operator/working personnel carry portable gas detectors (O2 and CO2) all the time an
evacuate area in case of oxygen deficiency and update ERP accordingly. Also ensure area if free of
CO2 before startup of FSA treatment facility
Risk Ranking M
Resolution
By: By:
Date: Date:
HAZOP Study
Correction Action & Recommendation Form
Location Turaif
Recommendation / Action # 12
Problem Statement
Consequence: Possible release of CO2 into the reactor surrounding area which will lead to lack of
oxygen effecting people in the surrounding area
It is recommended to conduct LOPA workshop for assessing the SIL level of all proposed interlocks
and already implemented interlocks in the
DCS
Risk Ranking M
Resolution
By: By:
Date: Date:
POWER : KW SIZE : H 5000 MM X ID 12000 MM DESIGN MAX. FLOWRATE : 8000 NM3/H DESIGN MAX. FLOWRATE : 60 M3/H
A A
VOLUME : 557 M3 POWER DRIVE RATED :250 KW POWER DRIVE RATED : 4 KW ( NOTE 1 )
3600-ABAFBA-0007
I26B LEVEL
I15 I23 SHEET 2, HIGH HIGH
I21 SHEET 2 LEVEL
HH
HH
LIC H
DN 25
FQI FQI LIC H
NC
2202 2201 3201 I26A
3202 L
L
LL LL
B CTSFT 100-3600-CTSFT-AR09-004-NI B
100-3600-CTSFT-AR09-002-NI
002 MD-521-3600-EG-PR-PID-3002
3600-ABAFBA-0002
PG
3600-ABAFBA-0026
3600-ABAFBA-0014
FROM CTSFT PUMPS I6
FQIT FY 4101 I12
LOW LOW
2202 I16 2202 LEVEL
DN 25
FE FV
NC
TI NC
+
NO
+
2202 2202
3001 DN 25
FSA DN 50
100-3600 -FSA-AR09-003-NI
009 MD-512-3A50-EG-PR-PID-2004 M
100-3600 -FSA-AR09-001-NI
100-3600 -FSA-AR09-002-NI
NO NOTE 9 100X80 80X100 NO
FROM 200-23A50-FSA-AR09-0023-NI FSA LINE 3600-ABAFBA-0001 3600-ABAFBA-0003 3600-ABAFBA-0017 3600-ABAFBA-0006
DN 50 3600-ABAFBA-0004 DN 50 NC
DECANT WATER 3600-ABAFBA-0025 NC NC
MD-512-3600-EG-PR-PID-3002 014 200-3600-WPR-AG40-007-NI C03
100-3600-CTSFT-AR09-003-NI
TO 3600-PMP-300 SUCTION LINE NC
NC I18
NOTE 5
DN 25 NOTE 11 I9 NOTE 10
1,2,3 H
3600-ABAFBA-0037
DN 50 PG LIA
200-3600-WPR-AG40-006-NI
C C03 C
4102 3203
3600-ABAFBA-0013
C03
3600-ABAFBA-0019
C03 L
DECANT WATER LIT I17 LIT
MD-512-3600-EG-PR-PID-3004 029 200-3600-WPR-AG40-009-NI FQIT FY
3600-ABAFBA-0008
DN 25
2201 2201 3201 1,2,3 3202
NC
TO 3600-SKR-100 200X150 150X200 NC FE FV
3600-FL-100 DN 25 I14
NO
+ +
TI 2201 2201 3600-ABAFBA-0005 HIGH
3600-AKGFBA-0007
3002 NO LEVEL
DECANT WATER 250-3600-WPR-AG40-001-NI 250-3600-WPR-AG40-003-NI 250-3600-WPR-AG40-005-NI DN 50 I13
012 MD-512-07ZZ-EG-PR-PID-3001 M LOW
3600-AKGFBA-0004
FROM EXISTING DECANT POND WATER NO
NC
250X150 150X250 LEVEL
3600-ABAFBA-0027
3600-AKGFBA-0002 NOTE 9 3600-AKGFBA-0005
RETURN PUMPS HEADER NC 3600-ABAFBA-0022 DN 50
3600-ABAFBA-0023
NO
100-3600-WPR-AG40-022-NI
NOTE 11
DN 25
NO
250-3600-WPR-AG40-004-NI
NC NC 100-3600-SLG-AG16-008-NI
DN 25 DN 50
TI 3600-ABAFBA-0009 NC
C03 VSD NOTE 10
3003 C03 VSD VSD VSD VSD VSD CO2+AIR
DECANT WATER 1200-3600-SGO-GRPDUCT-001-NI
250-3600-WPR-AG40-002-NI 031 MD-512-3600-EG-PR-PID-3004
D 013 MD-512-07ZZ-EG-PR-PID-2001 D
3600-ABAFBA-0036
FROM EXISTING DECANT POND WATER NC M M M NC M M M TO EXHAUST FAN 3600-FAN-100
3600-ABAFBA-0018
3600-AKGFBA-0003 DN 20
RETURN PUMPS STANDBY HEADER 300-3600-ATA-AA03-005-PP
DN 25
NC
3600-ABAFBA-0035
3600-ABAFBA-0021 CO2+AIR
NC DN 25 1200-3600-SGO-GRPDUCT-002.-NI
NC 030 MD-512-3600-EG-PR-PID-3004
400-3600-ATA-AA03-003-PP DN 20
3600-AKGFBA-0006
3600-ADVFXA-001
3600-ABFFBA-0004
TO EXHAUST FAN 3600-FAN-100
3600-AKGFBA-0009
3600-ADVFXA-002
100-3600-WPR-AG40-021-NI
300-3600-ATA-AA03-004-PP DN 2500
DN 2500 DN 200 N 11 N 11
400 X 300 N9 TO I21,I23 DN 200 N9
NC I5
NOTE 8
NO
N 10 SHEET 2 LIT
NC
NO N 10 N8
NC NOTE 10 N8 HIGH PH
NO
NOTE 8
NOTE 11 TO I21,I23 DN 20 3600-AGARBA-011 N 13 3203
N 13
100-3600-WPR-AG40-008-NI
DN 20 SHEET 2 3600-ABAFBA-0024 N 12
N7 H
N 17 AI N 17 N7
3600-ABAFBA-0034 I4 N 16 1202
HIGH PH N 16
N1
C03 N1
300-3600-ATA-AA03-002-PP
E E
300-3600-ATA-AA03-001-PP
H
AI N4 100-3600-SLG-AG16-009-NI
1201 NC N4
3600-AKGFBA-0015 NC SLUDGE
3600-AKGFBA-0037 NC
3600-AKGFBA-0016 026 MD-520-3600-EG-PR-PID-3002
N3 N3
400-3600-SLG-AG16-004-NI TO SLUDGE PUMPS 3600-PMP-300/301
NO
3600-AGARBA-010
3600-AGARBA-009
3600-AKGFBA-0010
020-3600-WSW-AQ15-004-NI
AIT
3600-ACKFBA-0002
I 28
400-3600-SLG-AG16-012-NI
400-3600-SLG-AG16-011-NI
C03
C03 PH
PG PG AE
CO
PH CO
NOTE 9
1201 AE
100-3600-SLG-AG16-007-NI
4103 4104
F DN20 DN20 1202 I19 I 20 F
3600-ABAFBA-0020 3600-ABAFBA-0010 3600-AGI-100/101/102 3600-AGI-103/104/105
N 14 N 14
NO 3600-AGARBA-0037
TO I25 DN 50 DN 50
SHEET 4 NOTE 4
3600-BLW-100 3600-BLW-101
3600-AKGFBA-0036
I24 NOTE 4
300-3600-SLG-AG16-002-NI
3600-AKGFBA-0011 3600-REA-100 3600-REA-101
1,2
NO
N5 NOTE 5 NOTE 5 N5
200-3600-SLG-AG16-005-NI 200-3600-SLG-AG16-006-NI
80 X 100
NO NO
NC N2 N2 3600-AKGFBA-0014 M
NC NC
3600-AKGFBA-0035 M
3600-AKGFBA-0012 3600-AKGFBA-0013
300-3600-SLG-AG16-001-NI
G G
NOTES :
1- TO BE COMPLETED BY SUPPLIERS
2- THE RETENTION DYKE IS DESIGNED FOR 110% ONE REACTOR CAPACITY NOTE 2
3600-AGI-106 3600-PMP-400
MD-512-3600-EG-SR-DGA-3001
3- OVER FLOW LINE IS TO BE PROVIDED WITH GOOSE NECK OR AN OPEN TROUGH IN CASE OF FOAM GENERATION
4- WEIR IS PROVIDED TO AVOID BYPASS FROM THE INLET TO THE OUTLET WHICH WOULD LIMIT THE RESIDENCE TIME OF THE PRODUCT AND TO REMOVE THE SOLID PARTICLES WHICH TEND TO BE PRESENT AT THE BOTTOM OF THE REACTOR NO
5- AIR SPARGERS ARE REMOVABLE AND EQUIPPED WITH FLANGES FOR EASY OPERATION AND MAINTENANCE 3600-AKGFBA-0038
6- ALL INSTRUMENTS TAGS SHALL BE PREFIXED BY FACILITY BREAKDOWN CODE 3600.
7- FOUR (04) OPERATING MODES ARE PROVIDED FOR OPERATOR SELECTION VIA THE SELECTOR SWITCH 3600-YI-0500 LOCATED ON REACTORS PANEL. FOR DETAILS OF OPERATING MODES, REFER TO OPERATING AND CONTROL PHILOSOPHY (DOC NO. MD-512-3600-EG-PR-RPT-3004)
8-DAMPER VALVES TO BE LOCKED OPEN TYPE
Node 01 FSA
9- ISOLATING SPOOL
10- PIPE TO FLOOR DRAIN
11- PIPE TO DRAINAGE COLLECTOR
Treatment Package ISSUED FOR CONSTRUCTION
CONTRACTOR: DRAWN KCH 19/07/18
C03 19.07.18 ISSUED FOR CONSTRUCTION GHH KCH JI
PROPRIETARY & CONFIDENTIAL NESMA & PARTNERS UMM WU'AL PHOSPHATE PROJECT
CONTRACTING CO. CHECKED 19/07/18 FSA TREATMENT PACKAGE 6.25
C02 11.05.18 ISSUED FOR CONSTRUCTION GHH KCH JI GHH
This document and the information contained P.O. Box 1498, Al-khobar 31952 PIPING & INSTRUMENTATION DIAGRAMS
H C01 21.03.18 ISSUED FOR CONSTRUCTION GHH KCH JI herein is Ma'aden proprietary know-how. Kingdom Of Saudi Arabia ENGINEER KCH 19/07/18 SHEET 1 H
This document or any part thereof should not Telephone: +966 (13) 897 1050
A06 12.03.18 ISSUED FOR 30 % REVIEW GHH KCH JI
16:00
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8
C03 MD-512-3600-EG-PR-PID-3002
REV DRAWING NUMBER
Interlock Description
3600-PMP-200 3600-PMP-300
High High level in reactor 1 close FV-2201
CTSFT CHARGING PUMP ( WITH VFD ) SLUDGE PUMP (WITH VFD)
High High level in reactor 1 close FV-2202
A
I1 A
DESIGN MAX. FLOWRATE : 51 M3/H DESIGN MAX. FLOWRATE : 435 M3/H High High level in reactor 1 close HV-7301
POWER DRIVE RATED : 20 KW ( NOTE 4 ) POWER DRIVE RATED : 152.5 KW ( NOTE 4 )
High Highlevel in reactor 1 stop pump 3600-PMP-200
I2 Flow control in DECANT WATER feed line
HEAD : 55.2 M HEAD : 96.8 M I3 Flow control in FSA inlet line
I4 High PH in REACTOR 1
I5 High PH in REACTOR 2
I8 I1 I6 I4 I5 I2 I3 High High level in reactor 2 close FV-2201
High High level in reactor 2 close FV-2202
I6
High High level in reactor 2 close HV-7301
LL LEVEL FROM LIT-1401 I 10 I21 I7 High High level in reactor 2 stop pump 3600-PMP-200
I7 Flow control in CTSFT feed line
PIA (OPEN) (CLOSED) I8 Suction low pressure stop pump 3600-PMP-200
B B
4201 ZLO ZLC FQI Low Low Level in reactor 1 stop pump 3600-PMP-300 and Agitator
L I4 I5 I2 I3 I1 I9
7301 7301 2203 3600-AGI-100/101/102
VSD
I10 low low level in CTSFT tank 21A61-TNK-010 stop pump 3600-PMP-200
PG
3600-ABAFBA-0011
PIT I11 Section low pressure stop pump 3600-PMP-300 to stop
3600-ABAFBA-0016
4105 I6 I 23 ZSO ZSL FQIT
4201 Low Low Level in reactor 2 stop pump 3600-PMP-300 and Agitator
M 7301 7301 2203 I12
3600-AGI-103/104/105
NO
FE
NO
HV +
I13 Low level stop sump pump 3600-PMP-400 and agitator 3600-AGI-106
+
C C
NC
3600-AGARBA-0014
I18-3 Agitator 3600-AGI-105 interlock
3600-ABAFBA-0030
PIT 3600-AKGFBA-0028
NOTE 5 ZSO ZSL
3600-ABAFBA-0015
3600-ABAFBA-0036 DN 20
NO
NOTE 1 HV TI
NO
350-3600-SLG-AT21-010-NI
SLUDGE DN50 HOLD
E 300-3600-SLG-AG16-003-NI E
021 MD-512-1A61-EG-PR-PID-0001 150 X 300 TO THE TOP OF THE GYPSUM STACK
NOTE 2 300X200 DN100
NO DN100 PIT PIA
FROM FIRST OR SECOND REACTORS PIT PIA NC I28 TO I20
NC 3600-AKGFBA-0025
3600-AKGFBA-0022 NC 3600-AKGFBA-0041 4204 4204 SHEET 1 Node 01 FSA
3600-AGARBA-0011
4203 4203
3600-AGARBA-0012
DN100 3600-PMP-300
3600-AGARBA-0010
DN 50
NO
C03
NO
F
NO
CONTRACTOR:
NOTE 1
3600-AGARBA-0032 ISSUED
KCH
FOR CONSTRUCTION F
C03 17/07/18 ISSUED FOR 60 % REVIEW GHH KCH JI DRAWN 17/07/18
NESMA & PARTNERS UMM WU'AL PHOSPHATE PROJECT
CONTRACTING CO. CHECKED GHH 17/07/18 FSA TREATMENT PACKAGE 6.25
C02 11.05.18 ISSUED FOR CONSTRUCTION GHH KCH JI P.O. Box 1498, Al-khobar 31952
Kingdom Of Saudi Arabia ENGINEER KCH 17/07/18 PIPING & INSTRUMENTATION DIAGRAMS
Telephone: +966 (13) 897 1050
C01 21.03.18 ISSUED FOR 60 % REVIEW GHH KCH JI JI SHEET 2
SUB-CONTRACTOR: APPROVED 17/07/18
ENGINEERING PROCUREMENT &
A06 16.08.17 ISSUED FOR 60 % REVIEW GHH KCH JI PROJECT MANAGEMENT S.A EMPLOYER
DRAWING NUMBER REV
Silver Street, Fatma Building. Lake gardens MD-512-3600-EG-PR-PID-3002
SCALE A2
DOCUMENT NUMBER REFERENCE DOCUMENTS REV DATE REVISION DESCRIPTION DRN CHK ENG APP EMP 1053 Tunis-TUNISIA - P: (+216) 71 16 81 00 / F : (+216) 71 19 09 18 C03
1 2 3 4 5 6 7 8
This document and the information contained herein is Ma'aden proprietary know-how. This document or any part thereof should not be reproduced, stored in a retrieval system or transmitted by any means, electronic or otherwise, or divulged without prior written permission of Ma'aden.
1 2 3 4 5 6 7 8
MD-512-3600-EG-PR-PID-3003 C03
MD-512-3600-EG-PR-PID-3002
TO FLOW CONTROL VALVE FV-2201
MD-512-3600-EG-PR-PID-3001
TO FLOW CONTROL VALVE FV-2202
MD-512-3600-EG-PR-PID-3001
REV DRAWING NUMBER
INSTRUMENT AIR
INSTRUMENT AIR
INSTRUMENT AIR
3600-ABARRA-002
3600-ABARRA-012
3600-ABARRA-003
3600-ABARRA-005
DN 25
DN 25
NC
DN25
NO
NO
NO
DN 20
050-3600-IAS-AP10-001-NI
INSTRUMENT AIR
80-23C20-IAS-AP10-0006-NI 3600-ABARRA-001
B MD-512-39AA-EG-PR-PID-2055 DN 20 B
FROM EXISTING INSTRUMENT AIR SYSTEM 3600-ABARRA-013 NC
TI
3010 NOTE 1
INSTRUMENT AIR
TUBING
MD-512-3600-EG-PR-PID-3002
TO ON-OFF VALVE HV-7301
TI
3012
C C
3600-ABARRA-009
NC
DN 20
PLANT AIR
040-3600-PRA-AZ02-001-NI
HOLD
PLANT AIR 3600-ABARRA-006 3600-ABARRA-007 TO UTILITIES STATION
50-23C20-PAS-AZ02-0233-NI
MD-512-39AB-EG-PR-PID-2035 3600-ABARRA-014 NC
DN 20
FROM EXISTING AIR SYSTEM 3600-ABARRA-011 Node 02 Utilities
TI NC
3009 DN 50 NOTE 1
SERVICE WATER
050-3600-WRS-AG13-001-NI
HOLD
SERVICE WATER 3600-ABARRA-008 C03 3600-ABARRA-0017
80-23C20-WRS-AG13-0233-NI
D MD-512-3C80-EG-PR-PID-2005 TO UTILITIES STATION D
3600-ABARRA-010 NC POTABLE WATER
FROM EXISTING SERVICE WATER SYSTEM DN 50 040-3600-WPD-AP12-002-IC
HOLD
TI 3600-AGARBA-0001 TO EYE WASH 3600-LEB-100 AND SAFETY SHOWER
3008 3600-AGARBA-0008 NOTE 1 POTABLE WATER
040-3600-WPD-AP12-003-IC
NC HOLD
DN 20
3600-AGARBA-0002 TO EYE WASH 3600-LEB-101 AND SAFETY SHOWER
050-3600-WPD-AP12-001-IC
POTABLE WATER 3600-AGARBA-0006 C03 POTABLE WATER
080-239MA-WPD-AP12-0010-IC 3600-AGARBA-0007 NC 040-3600-WPD-AP12-004-IC
MD-512-39WG-EG-PR-PID-2015 HOLD
DN 20
FROM EXISTING POTABLE WATER SYSTEM 3600-AGARBA-0003 TO EYE WASH 3600-LEB-102 AND SAFETY SHOWER
POTABLE WATER
E TI NOTE 1 040-3600-WPD-AP12-005-IC E
3007 HOLD
3600-AGARBA-0004 TO EYE WASH 3600-LEB-103 AND SAFETY SHOWER
POTABLE WATER
040-3600-WPD-AP12-006-IC
HOLD
C03 3600-AGARBA-0005 TO EYE WASH 3600-LEB-104 AND SAFETY SHOWER
POTABLE WATER 3600-AGARBA-0018 POTABLE WATER
80-21A61-WPD-AG14-522-IC
HOLD 040-3600-WPD-AP12-007-IC
HOLD
FROM EXISTING POTABLE WATER SYSTEM
TO EYE WASH 3600-LEB-105 AND SAFETY SHOWER
TI
NOTE:
1- TO DRAINAGE COLLECTOR
3011
ISSUED FOR CONSTRUCTION
F CONTRACTOR: DRAWN KCH 19/07/18 F
C03 19.07.18 ISSUED FOR CONSTRUCTION NESMA & PARTNERS UMM WU'AL PHOSPHATE PROJECT
CONTRACTING CO. CHECKED GHH 19/07/18 FSA TREATMENT PACKAGE 6.25
C02 11.05.18 ISSUED FOR CONSTRUCTION GHH KCH JI P.O. Box 1498, Al-khobar 31952
Kingdom Of Saudi Arabia ENGINEER KCH 19/07/18 PIPING & INSTRUMENTATION DIAGRAMS
Telephone: +966 (13) 897 1050
C01 21.03.18 ISSUED FOR CONSTRUCTION GHH KCH JI SUB-CONTRACTOR: APPROVED JI 19/07/18 SHEET 3
ENGINEERING PROCUREMENT &
A04 13.03.18 ISSUED FOR 60 % REVIEW GHH KCH JI PROJECT MANAGEMENT S.A EMPLOYER
DRAWING NUMBER REV
Silver Street, Fatma Building. Lake gardens SCALE A2 MD-512-3600-EG-PR-PID-3003 C03
DOCUMENT NUMBER REFERENCE DOCUMENTS REV DATE REVISION DESCRIPTION DRN CHK ENG APP EMP 1053 Tunis-TUNISIA - P: (+216) 71 16 81 00 / F : (+216) 71 19 09 18
1 2 3 4 5 6 7 8
This document and the information contained herein is Ma'aden proprietary know-how. This document or any part thereof should not be reproduced, stored in a retrieval system or transmitted by any means, electronic or otherwise, or divulged without prior written permission of Ma'aden.
1 2 3 4 5 6 7 8
C01 MD-512-3600-EG-PR-PID-3004
REV DRAWING NUMBER
3600-FAN-100 3600-SKR-100
A A
EXHAUST FAN STACK
40-3600-WPR-AG40-014-NI
NOTE 2
NOTE 1
40-3600-WPR-AG40-016-NI
40-3600-WPR-AG40-017-NI
40-3600-WPR-AG40-015-NI
40-3600-WPR-AG40-013-NI
20X40
B B
CO2+ AIR
1200-3600-SGO-GRPDUCT-001-NI
MD-512-3600-EG-PR-PID-3001
FROM REACTOR 1 3600-REA-100 NOTE 1
NOTE 1
40-3600-WPR-AG40-012-NI
NOTE 1
20X40
NOTE 1
Node 01 FSA
CO2 + AIR
Treatment Package
80-3600-WPR-AG40-011-NI
1200-3600-SGO-GRPDUCT-002-NI
MD-512-3600-EG-PR-PID-3001
NOTE 1
FROM REACTOR 2 3600-REA-101
C C
1200-3600-SGO-GRPDUCT-003.-NI
100-3600-WPR-AG40-010-NI
100-3600-WPR-AG40-018-NI
3600-AKGFBA-0030
D I 25 D
C01
200-3600-WPR-AG40-009-NI DECANT WATER
1200-3600-SGO-GRPDUCT-004-NI MD-512-3600-EG-PR-PID-3001 29
3600-AKGFBA-0034
100-3600-WPR-AG40-020-NI
DN 100 3600-ADVFXA-003 3600-AKGFBA-0029
NC DN 100
3600-FAN-100 NC
100-3600-WPR-AG40-019-NI 3600-SKR-100
E E
NOTE 4
SEAL POT
NOTE 5 NOTE 4
NOTE 4
NOTE :
1- SPRAY NOZZLES
2- OPENING ORIENTATION TO THE WEST
3- TO BE CONFIRMED / COMPLETED BY SUPPLIER
4- PIPE ROUTED TO FLOOR DRAIN
F CONTRACTOR: KCH F
C01 11.05.18 ISSUED FOR CONSTRUCTION NESMA & PARTNERS
DRAWN 11/05/18
CONTRACTING CO. GHH UMM WU'AL PHOSPHATE PROJECT
P.O. Box 1498, Al-khobar 31952
CHECKED 11/05/18 FSA TREATMENT PACKAGE 6.25
A03 13.03.18 ISSUED FOR 60 % REVIEW GHH KCH JI Kingdom Of Saudi Arabia KCH
Telephone: +966 (13) 897 1050
ENGINEER 11/05/18 PIPING & INSTRUMENTATION DIAGRAMS
A02 13.10.17 ISSUED FOR 60 % REVIEW GHH KCH JI SUB-CONTRACTOR: APPROVED JI 11/05/18 SHEET 4
ENGINEERING PROCUREMENT &
A01 16.08.17 ISSUED FOR 60 % REVIEW GHH KCH JI PROJECT MANAGEMENT S.A EMPLOYER
DRAWING NUMBER REV
Silver Street, Fatma Building. Lake gardens SCALE
DOCUMENT NUMBER REFERENCE DOCUMENTS REV DATE REVISION DESCRIPTION DRN CHK ENG APP EMP 1053 Tunis-TUNISIA - P: (+216) 71 16 81 00 / F : (+216) 71 19 09 18 A2 MD-512-3600-EG-PR-PID-3004 C01
1 2 3 4 5 6 7 8
This document and the information contained herein is Ma'aden proprietary know-how. This document or any part thereof should not be reproduced, stored in a retrieval system or transmitted by any means, electronic or otherwise, or divulged without prior written permission of Ma'aden.