Professional Documents
Culture Documents
Qs 004 Module 3 Compilation
Qs 004 Module 3 Compilation
0 Intended Learning Outcomes (ILO's) : QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
Proprietary Clause
CLICK NEXT.
https://tip.instructure.com/courses/38256/pages/3-dot-0-intended-learning-outcomes-ilos?module_item_id=3653030 1/2
12/4/22, 8:21 PM 3.0 Intended Learning Outcomes (ILO's) : QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
https://tip.instructure.com/courses/38256/pages/3-dot-0-intended-learning-outcomes-ilos?module_item_id=3653030 2/2
12/4/22, 8:21 PM 3.1 Contract Administration: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
c
Contract Administration
Introduction to the Topic:
Contract Administration
Design Stage
Tender Stage
Construction stage
Handover and Final Account stage
https://tip.instructure.com/courses/38256/pages/3-dot-1-contract-administration?module_item_id=3605104 1/5
12/4/22, 8:21 PM 3.1 Contract Administration: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
In this stage, the employer is with his conceptual plan in mind. In most of the projects,
a project manager will be appointed at this stage. Contract Administration duties
during this stage include monitoring and controlling both cost and time under the pre-
determined terms with the Employer.
Procurement is an important stage for any project and this is the stage where more
contract administration work involves. It is necessary to determine the tender
procedure and prepare the tender documents. In most construction projects, tender
documents will be part of the contract documents. Therefore it is important to check
the tender documents thoroughly before calling for bids.
In this stage, it is necessary to understand the contract document and the obligations
to each party. During the construction stage, more risk is involved in terms of both time
and money. At the same time, it is also necessary to get the work done with the
required quality and as mentioned in the specifications.
Contract Administration during the maintenance, completion and Final account stage
is mostly similar in different forms of contract. In this stage, it is necessary to monitor
the defects, warranties if necessary, and any other liabilities. Once all the obligations
are fulfilled, it is necessary to prepare the Final Account Certificate. Adjustments to the
contract document in terms of variations, liquidated damages or penalties should
indicate in Final Account. In this stage, the release of retention money is included too.
https://tip.instructure.com/courses/38256/pages/3-dot-1-contract-administration?module_item_id=3605104 2/5
12/4/22, 8:21 PM 3.1 Contract Administration: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
The first step to ensuring a successful contracting process is to clearly lay out
expectations, including the scope and deliverables. Scope creep is a common issue
that can derail any contract, so including in writing exactly what the contract does and
does not cover will help keep the contract on track.
It may sound like a given, but contract administration plans should include a detailed
timeline accounting for every important milestone throughout the life of the contract,
including project start and end dates, deadlines for deliverables, and progress
updates.
To avoid contract disputes and maintain positive relationships between both parties,
everyone involved in the contract administration process should know the financial
terms of the agreement, including the value of the contract, payment intervals, and the
process to address the need for any additional expenses (depending on the type of
contract).
To ensure transparency and accountability, the plan should include details about how
the contract deliverables will be executed, including the people who will be working on
each part of the agreement (including both internal and third-party personnel, if
applicable).
Every contract comes with risk, but putting plans in place to account for those risks
can prevent the contract from failing. Outline the most likely risks for each agreement
and the steps that should be taken in the event those events actually happen.
Variations
Powers and responsibility of the engineer
Delays, Time extension and Liquidated Damage
Payment
Price Adjustment
Default of employer and contractor
Suspension
Termination
Claims and Disputes
End of Discussion.
Reference:
Uniform General Conditions of Contract for Private Construction – CIAP DOC 102
TIP Library
(https://www.tip.edu.ph/library.html)
Proprietary Clause
https://tip.instructure.com/courses/38256/pages/3-dot-1-contract-administration?module_item_id=3605104 4/5
12/4/22, 8:21 PM 3.1 Contract Administration: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
CLICK NEXT.
https://tip.instructure.com/courses/38256/pages/3-dot-1-contract-administration?module_item_id=3605104 5/5
12/4/22, 8:21 PM 3.2 Delays and Damages: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
c
Delays and Damages
Introduction to the Topic:
Construction delays are among the most common disputes that arise on projects.
However, the process of establishing and proving a delay claim can get complicated
quickly. That’s why having a comprehensive understanding of the necessary elements
to justify a delay claim can be a priceless advantage.
A delay damages construction contract contains a clause that provides for damages
due in the event of delays. The term “delay” may be broadly defined, however, so the
amount of damages can vary widely.
A critical delay is one that will affect the project completion date (or some other
important milestone date on a project). Critical delays can’t really be made up – they
just tack on extra time.
https://tip.instructure.com/courses/38256/pages/3-dot-2-delays-and-damages?module_item_id=3605105 1/5
12/4/22, 8:21 PM 3.2 Delays and Damages: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
Non-critical delays will affect the completion of specific activities, but not the
completion date or the date of some important milestone. The determining factor is
whether the delay extends the Critical Path of the project.
Inexcusable delays are those where the contractor was entirely responsible for
extending the project’s duration. If this is the case, then the contractor will be liable for
any costs or damages caused by the delay.
All excusable delays are compensable. This means that any time a delay is
considered “excusable,” the contractor will generally have a claim for a time extension,
compensation, or both! If the contractor is solely at fault, the delay will very likely be
non-compensable. Non-compensable delays can fall under any of the other
categories, depending on the situation and contract terms.
Damages
For owner-caused delays (or those caused by another contractor), a contractor may
have a claim for:
https://tip.instructure.com/courses/38256/pages/3-dot-2-delays-and-damages?module_item_id=3605105 2/5
12/4/22, 8:21 PM 3.2 Delays and Damages: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
When a contractor is at fault for a delay, an owner may have a claim for:
Supervision costs
Extended general conditions
Jobsite trailer rental
Temporary facilities/utilities
Liability insurance
Equipment rental & maintenance costs
Field labor
Increased materials cost
Lost productivity
Hourly labor rate increases
De-mobilization/re-mobilization
Types of Damages
2. Unliquidated Damages
https://tip.instructure.com/courses/38256/pages/3-dot-2-delays-and-damages?module_item_id=3605105 3/5
12/4/22, 8:21 PM 3.2 Delays and Damages: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
1. Concurrent Delay
A concurrent delay occurs when multiple activities affect the project’s timeline, but the
delays don’t precisely stack on top of each other. That doesn’t necessarily mean the
delays have to happen at the exact same time to be considered concurrent.
Contract clause stating that delays are not compensable. Enforceability may be limited
by statute.
A contractor failed to notify the owner of the delay in the time required by the contract.
A “time is of the essence” clause means that the contract will hold everyone
responsible for completing the agreed upon work by the agreed upon time.
Force majeure generally covers any occurrences that were (a) not reasonably
foreseeable at the time of contracting, (b) beyond the control of the parties, and (c) not
caused or compounded by negligence. Consequently, when one of these events
occur, performance will either be suspended or excused depending on the contract
terms and the duration of the disruption
End of Discussion.
https://tip.instructure.com/courses/38256/pages/3-dot-2-delays-and-damages?module_item_id=3605105 4/5
12/4/22, 8:21 PM 3.2 Delays and Damages: QS 004-CE41S1C - Contract Practice and Administration including Cost Reporting
Reference:
Uniform General Conditions of Contract for Private Construction – CIAP DOC 102
TIP Library
(https://www.tip.edu.ph/library.html)
Proprietary Clause
CLICK NEXT.
https://tip.instructure.com/courses/38256/pages/3-dot-2-delays-and-damages?module_item_id=3605105 5/5
osneey)
Module 3
: aeet as
aI a ES and Damages
lis nie Types of Damages
s Contract Administration involves all necessary activities for a
construction project performance from the initial stage to its final
stage. These activities include monitoring of the project
performance with the agreed contractual obligations between the
parties to the contract.
Typically, a construction project undergoes few different stages.
* Design Stage
« Tender Stage _
« Construction stage
¢ Handover and
Final Account stage
— :
k
* Design Stage Procurement is an important stage for any
project and this is the stage where more
¢ Tender Stage contract administration work involves. It is
, necessary to determine the tender procedure
I and prepare the tender documents. In most
¢« Handover and Slag projects, teed caged “Hi
1 ccount stage be part of the contract documents. Therefore
ee 8 it is important to check the tender documents
thoroughly before calling for bids.
ie
All excusable delays are compensable. This means that any time a
delay is considered “excusable,” the contractor will generally
have a claim for a time extension, compensation, or both! If the
contractor is solely at fault, the delay will very likely be non-
compensable. Non-compensable delays can fall under any of the
other categories, depending on the situation and contract terms.
Damages claimed by a contractor
For owner-caused delays (or those caused by another
contractor}, a contractor may have a claim for:
¢ Improper Notice
¢ Time is of the Essence
* Force Majeure Events
¢ Concurrent Delay
* No Damages for Delay Clause