Road To Materials
Road To Materials
Road To Materials
PA-129
Improvement Of E11/E12 Intersection Between Al Falah & Al
Contract No:- (PD/CA/BPS/SY/R2167/P350- Project: Reef
2017-54480/19/115)
Material Description:- (Formation) Existing Material Sampling Date 2/07/2020
Material Source:- Road # 01 Testing Date 4/07/2020
Sample No. 2 Report Ref: FRM/RD#01/08
Location:- Road # 01 Test Method: AASHTO T-88-13
Initial Dry Wt. 1926.0 grms After wash weight gms. Part :- A
Specification
Sieve Size Sieve Size Retained Wt. Retained Wt. Retained Passing JMF LIMIT
Limit
(inch") (mm)
Individual Cum. % % From ~ To
2" 50.8 Nil Nil Nil 100 100 100
100
80
60
40
Passing %
20
-20
-40
-60
-80
-100
No.200 No.40 No.10 No.4 3/8" 3/4" 1" 1 1/2" 2"
Sieve Sizes
Remarks and Comments
CONTRACTOR CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Material Engineer
Particle Size Analysis of Soil
PA-129
Improvement Of E11/E12 Intersection Between Al Falah & Al
Contract No:- (PD/CA/BPS/SY/R2167/P350- Project: Reef
2017-54480/19/115)
Material Description:- (Formation) Existing Material Sampling Date 2/07/2020
Material Source:- Road # 01 Testing Date 4/07/2020
Sample No. 2 Report Ref: FRM/RD#01/08
Location:- Road # 01 Test Method: AASHTO T-88-13
Initial Dry Wt. 5418.0 grms After wash weight gms. Part :- B
Specification
Sieve Size Sieve Size Retained Wt. Retained Wt. Retained Passing JMF LIMIT
Limit
(inch") (mm)
Individual Cum. % % From ~ To
2" 50.8 Nil Nil Nil 100 100 100
100
80
60
Passing %
40
20
-20
-40
No.200 No.40 No.10 No.4 3/8" 3/4" 1" 1 1/2" 2"
Sieve Sizes
Remarks and Comments
CONTRACTOR CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Material Engineer
MOISTURE - DENSITY RELATION OF SOIL
AASHTO-T 180-10
PA-129 (PD/CA/BPS/SY/R2167/P350- Improvement Of E11/E12 Intersection Between Al Falah & Al
Contract No:- Project: Reef
2017-54480/19/115)
Material Description (Formation) Existing Material Sampling Date: 2/07/2020
Material Source Road # 01 Date Tested: 4/07/2020
Location Road # 01 Report Ref: FRM/RD#01/08
No of layers:- 5 No of Blows:- 56
1 2 3 4 5 6
Weight of Wet Soil + Mould gr. 10458 10655 10856 11034 11040
Wet Density
Weight of Dry Soil + Can gr. 635.1 597.1 658.4 620.8 537.0
Weight of Water gr. 30.1 42.0 58.9 60.9 47.4
Weight of Can gr. 116.5 67.4 63.8 113.6 197.0
Weight of Dry Soil gr. 518.6 529.7 594.6 507.2 340.0
Water Content % 5.8 7.9 9.9 12.0 13.9
Dry Density g/cc 1.691 1.744 1.799 1.840 1.812
M.D.D. 1.840 g/cc
O.M.C 12.0 %
1.860
1.850
1.840
1.830
Dry Density
1.820
1.810
1.800
1.790
1.780
1.770
1.760
1.750
1.740
1.730
1.720
1.710
1.700
1.690
1.680 Moisture
1.670
1.660
1.650
4 5 6 7 8 9 10 11 12 13 14 15
CLIENT : MUSANADA
PROJECT : Improvement Of E11/E12 Intersection Between Al Falah & Al Reef
TEST No. 1 2 3
SAND EQUIVALENT % 25 24 26
REMARKS
28.0
Liquid limil 24
Plactic limit 16
Plactic index 5
23.0
18.0
15 17 19 21 23 25 27 29 31 33 35
CONTRACTOR CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Materials Engineer
Improvement Of E11/E12 Intersection Between Al Falah & Al Reef
No. of Blows 10
Wt. Of Soil+Mould (gm) 10756
Corresponding Pen. (mm) 0.64 1.27 2.54 3.81 5.08 6.36 ~
Wt. Of Empty Mould (gm) 25.0
6824
Wt. Of Compacted Soil (gm) 3932 22.1 Load (KN) 0.7 1.5 2.7 3.5 4.0 4.2 ~
Volume of Mould (cc) 21.1
2126 20.0
Wet Density (gm/cc) 1.849 18.4
Load Kg/cm2 3.7 7.9 14.2 18.4 21.1 22.1 ~
Container No. 15
Load in kg/cm²
Contractor CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Materials Engineer
Improvement Of E11/E12 Intersection Between Al Falah & Al Reef
No. of Blows 30
Wt. Of Soil+Mould (gm) 10554
Corresponding Pen. (mm) 0.64 1.27 2.54 3.81 5.08 6.36 ~
Wt. Of Empty Mould (gm) 40
6358
Wt. Of Compacted Soil (gm) 4196 35 34.3 Load (KN) 1.1 2.2 3.8 5.2 6.0 6.5 ~
Volume of Mould (cc) 2131
31.6
Wet Density (gm/cc) 1.969 30
Load Kg/cm2 5.8 11.6 20.0 27.4 31.6 34.3 ~
Container No. 17
27.4
Load in kg/cm²
25
Wt. of Wet Soil + Con. (gm) 434.5
Standard Load ~ ~ 70 ~ 105 ~ ~
Wt. of Dry Soil + Con. (gm) 398.4 20 20.0
Wt. of Container (gm) 96.6
C.B.R % ~ ~ 28.6 ~ 30.1 ~ ~
Wt. of Water (gm) 15
36.1
Wt. of Dry Soil (gm) 301.8 11.6
10 Corrected C.B.R. ~ ~ ~ ~ ~ ~ ~
Water Content (%) 12.0
Dry Density (gm/cc) 5 5.8 Moisture After Soaking
1.759
Compaction (%) 95.6 Container No. 20 ~ ~
0 0.0
Wt. Of Wet Soil + Cont. (gm) 574.5 ~ ~
0 1.27 2.54 3.81 5.08 6.35
Soaking Time (Hrs) 96 Wt. Of Dry Soil + Cont. (gm) 512.4 ~ ~
Penetration in mm
Swelling Initial Reading 0.00 Wt. of Container (gm) 67.4 ~ ~
Test Final Reading 0.00 Wt. of Water (gm) 62.1 ~ ~
Swelling (%) Wt. of Dry Soil (gm) 445.0 ~ ~
Water Content (%) 14.0 ~ ~
Remarks and Comments:-
Contractor CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Materials Engineer
Improvement Of E11/E12 Intersection Between Al Falah & Al Reef
No. of Blows 65
45
Wt. Of Soil+Mould (gm) 11169
Corresponding Pen. (mm) 0.64 1.27 2.54 3.81 5.08 6.36 ~
Wt. Of Empty Mould (gm) 41.1
6812 40
39.0
Wt. Of Compacted Soil (gm) 4357
35 Load (KN) 1.9 3.1 4.8 6.3 7.4 7.8 ~
Volume of Mould (cc) 2132 33.2
Wet Density (gm/cc) 2.044 30 Load Kg/cm2 10.0 16.3 25.3 33.2 39.0 41.1 ~
Load in kg/cm²
Container No. 9
Wt. of Wet Soil + Con. (gm) 25 25.3
595.5
Standard Load ~ ~ 70 ~ 105 ~ ~
Wt. of Dry Soil + Con. (gm) 539.2
20
Wt. of Container (gm) 67.3
16.3 C.B.R % ~ ~ 36.1 ~ 37.1 ~ ~
Wt. of Water (gm) 56.3 15
Wt. of Dry Soil (gm) 471.9
10 10.0 Corrected C.B.R. ~ ~ ~ ~ ~ ~ ~
Water Content (%) 11.9
Dry Density (gm/cc) 1.826 Moisture After Soaking
5
Compaction (%) 99.2 Container No. 10 ~ ~
0 0 Wt. Of Wet Soil + Cont. (gm) 797.5 ~ ~
0.00 1.27 2.54 3.81 5.08 6.35
Soaking Time (Hrs) 96 Wt. Of Dry Soil + Cont. (gm) 709.6 ~ ~
Swelling Initial Reading 0.00 Penetration in mm Wt. of Container (gm) 69.4 ~ ~
Test Final Reading 0.00 Wt. of Water (gm) 87.9 ~ ~
Swelling (%) Wt. of Dry Soil (gm) 640.2 ~ ~
Water Content (%) 13.7 ~ ~
Remarks and Comments:-
Contractor CONSULTANT
Laboratory Technician Materials Engineer Materials Inspector Materials Engineer
Improvement Of E11/E12 Intersection Between Al Falah & Al Reef
Location: Road # 01
50
45
40
35
30
CBR %
25
20
15
10
5
0
87.0 88.0 89.0 90.0 91.0 92.0 93.0 94.0 95.0 96.0 97.0 98.0 99.0 100.0 101.0 102.0 103.0 104.0 105.0
Compaction %
Results Requirements
O.M.C.(%) 12 ~ ~
C B R AT 98% Compaction ~ ~ ~
C B R AT 95% Compaction 29 ~ ~
C B R AT 90% Compaction ~ ~ ~
L.L. ~ ~ ~
P.I. ~ ~ ~
Remarks & Comments:-
CONTRACTOR CONSULTANT
Laboratory Technician Materials Engineer Materials Inspactor Materials Engineer