Rukwa Project

IPC Target
Executed up to
Pipes Reached for Balance as on
S. No. Pipe Details Resource
IPC No.01 (m) 10.12.2022 10.12.2022 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 27-Dec 28-Dec 29-Dec 30-Dec Total

(i) Peritus Team with 2


Butt Fusion Machine (Per
1 HDPE OD 200mm PN 16 288.00 288.00 288.00 288.00
day per machine - 20
Joints)
2 HDPE DN 200 PN 10 3,692.00 1,697.00 1,995.00 480.00 480.00 480.00 480.00 75.00 1,995.00

3 HDPE OD 160mm PN 20 204.00 204.00 (i) Peritus Team with 2 204.00 204.00
Butt Fusion Machine (Per
day per machine - 25
Joints)
4 HDPE OD 160mm PN 16 804.00 804.00 400.00 404.00 804.00

(i) Scale Contractor with 2


Butt Fusion Machine (per
5 HDPE OD 160mm PN 10 10,428.00 1,797.00 8,631.00 day per Machine - 25 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 600.00 831.00 900.00 900.00 8,631.00
Joints Target)

15,416.00 3,494.00 11,922.00 - 600.00 600.00 600.00 600.00 1,080.00 1,080.00 1,080.00 1,080.00 963.00 1,204.00 1,235.00 900.00 900.00

(i) Scale Contractor -


800m
1 Earthwork 15,416.00 3,494.00 11,922.00 (ii) Peritus JCB - 300m (JCB 500.00 500.00 500.00 500.00 1,100.00 1,100.00 1,100.00 1,100.00 1,100.00 1,100.00 1,100.00 1,100.00 1,122.00 11,922.00
to be reached before
18.12.22)