Plant No: Pumping Unit For Luhais Degassing Station

Project : PE14038AR 00 PP5008 00

General Informations

LINE NO Service & Fluid code Piping Sheet No Pipe Material


Area Code Class

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0202-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 1-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 1-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0204-10-AC06-V 00 CO AC06 3-3 ASTM A106 GR B

00-CO0001-14-AC01-V 00 CO AC01 1-1 ASTM A106 GR B

00-CO0105-10-AC01-V 00 CO AC01 1-2 ASTM A106 GR B


(( QA/QC PIPING WELDING HIS

Welding

Joint Type Location Dia Thk Welding Date Welding Process WPS No
Number

49 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

50 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

51 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

52 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

53 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

54 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

55 BW F 0.75 5.56 11/3/2022 GTAW+SMAW 2

9 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

12 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

48 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

49 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

50 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

51 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

56 FW F 1 6.35 11/3/2022 GTAW+SMAW 2

57 BW F 1 6.35 11/3/2022 GTAW+SMAW 2

58 BW F 0.75 5.56 11/3/2022 GTAW+SMAW 2

29 BW F 10 6.35 11/3/2022 GTAW+SMAW 2

21 BW F 10 6.35 11/3/2022 GTAW+SMAW 2

`
WELDING HISTORY SHEET ))

Welding Visual inspection

Root Hot Fill 1 Fill 2 Fill 3 Cap Date RFI No Result

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C3 C3 C3 C3 C3 C3 11/4/2022 65 ACC

C3 C3 C3 C3 C3 C3 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C2 C2 C2 C2 C2 C2 11/4/2022 65 ACC

C5 C5 C5 C5 C5 C5 11/4/2022 65 ACC

C4 C4 C4 C4 C4 C4 11/4/2022 65 ACC
RT RT Repair PT Report

Date of RT RT Report Result Date Report No RESULT Date REQ REQ NO Date PT
No
PT Report

Report No Type RESULT PKG NO PKG AREA UNIT SERIAL


CODE NUMBER NUMBER
SUB- PROGRESS
SYSTEM NO. OF TP IVE TP P&ID SHEET NO DescriptioCat ( A/B/C )Action by Test Type Line Size
n
NO NO.
Hydrostatic test informations

Design FLUID Test Test Press


Press Medium PKG inch-dia
PKG Support
PKGIDTHREAD
Remain
ID RTReject RTRemain PT
DATE Status
Scop
PKG PKG
Submiss
ISSUED DATE
Remain
PL ARemain
Punch B Punch
SUBMIS acceptedW/D Notify
WalkDown
A Date
Punch Cleared SCOP Review
ion PKG
SION TO /commen
date
PEG ted Date
Painting Activiti
H/O to Hand SAND BLASTING &
Release Test
Hydro ReinstatementOver to 1ST LAYER PAINT DATE RESULT
to test Accept
Test Precom RFI
Painting Activities
2ND 3RD
PAINT DATE RESULT PAINT DATE RESULT
RFI RFI
Support
DWG. No. Line size Sheet Number Type L(mm) DIA

DW-1331-02 10 3-4 ST-06E-1 GP4-1790-609 NA NA


DW-1331-02 10 3-4 ST-07E-1 GP4-1790-609 NA NA
DW-1331-02 10 1-4 ST-04E-1 HAB-10-600-CS NA NA
DW-1331-02 10 1-4 ST-01E-1 DLH-12-400-CS-S40 NA NA
DW-1331-02 10 1-4 ST-01E-2 TP2-300-300-650 NA NA
DW-1331-02 10 3-4 ST-06D-1 GP4-1790-609 NA NA
DW-1331-02 10 3-4 ST-07D-1 GP4-1790-609 NA NA
DW-1331-02 10 1-4 ST-04D-1 HAB-10-600-CS NA NA
DW-1331-02 10 1-4 ST-01D-1 DLH-12-400-CS-S40 NA NA
DW-1331-02 10 1-4 ST-01D-2 TP2-300-300-650 NA NA
Welding Welding Report
Date Process WPS No Root Fill Cap Date No Result

11/01/2023 SMAW 3 C1 C1 C1 11/02/2023 62 ACC


11/01/2023 SMAW 3 C5 C5 C5 11/02/2023 62 ACC
11/01/2023 SMAW 3 C7 C7 C7 11/02/2023 62 ACC
11/01/2023 SMAW 3 C1 C1 C1 11/02/2023 62 ACC
11/01/2023 SMAW 3 C5 C5 C5 11/02/2023 62 ACC
11/01/2023 SMAW 3 C7 C7 C7 11/02/2023 62 ACC
11/01/2023 SMAW 3 C1 C1 C1 11/02/2023 62 ACC
11/01/2023 SMAW 3 C5 C5 C5 11/02/2023 62 ACC
11/01/2023 SMAW 3 C7 C7 C7 11/02/2023 62 ACC
11/01/2023 SMAW 3 C1 C1 C1 11/02/2023 62 ACC
Report
Date PT No Type RESULT DATE REPORT NO RESULT Remarks PKG NO