Professional Documents
Culture Documents
Opposition HLURB
Opposition HLURB
C E L I A E. L E U T E R I O,
Complainant-Appellee,
OPPOSITION
COMPLAINANT-APPELLEE CELIA E. LEUTERIO, represented by the
undersigned Law Offices, unto this Honorable Office, most respectfully submits the
contract.
-------------------------------------------------
1. The main argument in the Petition for Review dated 03 March 2004
parties as shown by the Reservation Agreement of 28 June 1995 which was allegedly not
signed by any of its representative. Accordingly, under the principle of relativity, the said
agreement could not be enforced upon respondent-appellant. Of course, the said argument
1
2. Well-settled is the rule that “[O]nce there is concurrence between the
offer and acceptance upon the subject matter, consideration, and terms of payment a
301 SCRA 572) As borne by the records, there is no doubt of the existence of a valid and
respondent-appellant signed for and on behalf of the latter beside the name of Val John E.
Perez, Vice-President for Finance of respondent, and on each and every page thereof.
dated 23 May 2002 (Cf: Annex “F” of Complainant’s Position Paper dated 24
one (1) condominium unit at AIC Empire Tower (Unit 1601) and two (2) parking slots
(Basement 06, Slot No. 52 & 53). It also shows that as early as 30 August 2000
consideration and mode of payment agreed upon in the contract. On the part of
complainant-appellee, she has fully complied with what was incumbent upon her.
6. Other than the two (2) documents mentioned, the subsequent documents
executed after the perfection of the said reservation agreement prove with certainty the
existence of the valid and binding contract. These documents are evidence of the
2
subsequent acts that should be taken into consideration in the determination of the
appellee wrote and sent to respondent-appellant the Letter dated 28 April 1999 and Letter
received on 28 February 2002 (Cf: Annexes “B” and “D” of Complainant’s Position
through Letter dated 16 August 2000, Letter dated 30 May 2002, and Letter of 10 July
2003 (Cf: Annexes “C, “E”” and “I” of Complainant’s Position Paper dated 24
November 2003).
of the contract.
-------------------------------------------------
virtually stands in an erroneous premise. On the contrary, there is a valid and enforceable contract that
complainant-appellee chose to rescind and claimed for reimbursement because of gross and substantial
3
"Section 23. Non-Forfeiture of Payments. - No
installment payment made by a buyer in a subdivision or
condominium project for the lot or unit he contracted to
buy shall be forfeited in favor of the owner or developer
when the buyer, after due notice to the owner or
developer, desists from further payment due to the failure
of the owner or developer to develop the subdivision or
condominium project according to the approved plans
and within the time limit for complying with the same.
Such buyer may, at his option, be reimbursed the total
amount paid including amortization interests but
excluding delinquency interest with interest thereon at the
legal rate."
11. The afore-quoted provision is clear and casts no doubt for ambiguous
interpretation. After due notice, the condominium unit buyer may desist from remitting
further payments to the owner or developer for failure of the latter to develop the
condominium project according to the approved plans and within the time limit for
complying with the same. The buyer, at his option, may ask for a reimbursement for all
reason to demand a return of all payments she made considering that she had already
paid, in full, the purchase price of the condominium unit and parking slots. Complainant-
appellee waited for more than eight (8) agonizing years for respondent-appellant to
deliver what was agreed upon. In fact, she made several requests for an update of the
status of the condominium project because she noticed that no major development had
been introduced therein since she signed the said reservation agreement. (Cf: Annexes
13. As held in the case of Casa Filipina Realty Corporation vs. Office of
the President (241 SCRA 165; February 7, 1995), "private respondents' refusal to
continue paying the amortization is thus based on two principal grounds: non-
development of the subdivision and encumbrance of the property subject of the sale
4
which became apparent to the buyer only after conducting his own investigation. As
such, the case falls squarely within the purview of both Secs. 23 and 24 of P. D. 957."
14. It is also clear form the words of Section 23 of P. D. No. 957, that the law
vests upon the buyer the option to demand reimbursement of the total amount paid or to
wait for further development of the subdivision or unit (Relucio vs. Brillante-Garfin,
15. The law explicitly provides that the reason why P. D. 957 was enacted is
precisely for the protection of the buyers from "fraudulent manipulations perpetrated by
unscrupulous subdivision and condominium sellers and operators…" (P. D. No. 957;
Casa Filipina Realty Corporation case, supra). Hence, without a doubt, complainant-
appellee is entitled to be protected under this law as her case falls squarely within the
-------------------------------------------------
16. An assiduous examination of the facts of the case will readily show that
its failure to construct, complete and deliver the condominium project. Thus,
complainant-appellee is not only entitled to a refund of all payments she made, but she is
17. The law expressly provides that "those who in the performance of their
obligation are guilty of fraud or delay and those who in any manner contravene the tenor
thereof, are liable for damages" (Article 1170 of the Civil Code; Barzaga vs. Court of
5
18. It is worth stressing that complainant-appellee was able to comply with
what was incumbent upon her, i. e., payment of the purchase price. Respondent-appellant,
on the other hand, has the concomitant obligation to start developing and constructing the
condominium project, and deliver the condominium unit agreed upon within the
stipulated period.
19. However, several years had passed and no progress can be seen on the
project site because the condominium project remained undeveloped. As held in the case
of Gutierez Hermanos vs. Oria Hermanos (30 Phil. 491), "if one party performs, and
the other does not, the latter would be in default." The act of the respondent-appellant in
obligation.
20. In reciprocal obligations, as in the instant case, default on the part of one
begins from the moment the other party fulfills with what is incumbent upon him
(Causing vs. Benser, 37 Phil. 417). Since the respondent-appellant failed to comply with
its obligation, complainant-appellee has every right to exercise her option to rescind her
appellee is likewise entitled to be indemnified for the damages she suffered in view of all
the unnecessary anxieties and inconveniences she has to go through as a result of the
unwarranted acts of the former. She parted away more than nine (9) million pesos of
22. Further, "a debtor who incurs delay or default is liable for damages plus
6
(Malayan Insurance Co., Inc. vs. Court of Appeals, G. R. No. 59919, November 25,
1986).
23. Attorney's fees may be granted based on the grounds enumerated under
"x x x x
x x x x"
24. In the instant case, complainant-appellee was forced to engage the services
of the undersigned Law Offices to seek redress and protect her interest. She has to go
through the tedious process of lodging a complaint just to enforce her rightful claims.
More so, it was quite clear that respondent-appellant acted in gross and evident bad faith
in its continued and unjustified refusal to satisfy complainant-appellee's valid, just and
demandable claims.
respondent-appellant for all legal and litigation expenses the former incurred in lodging
7
PRAYER
Honorable Board that respondent-appellant’s Petition for Review dated 03 March 2004 be
OTHER RELIEFS, just and equitable under the foregoing premises, are likewise
ALEXIS M. ESCOBEDO
Roll of Attorney No. 46807
PTR No.: 50460816: 13.01.04: Q.C.
IBP No.: 007082: 13.01.04: Sorsogon
Copy furnished:
EXPLANATION
Respondent’s counsel was furnished a copy of this Opposition via registered mail
due to lack of personnel to effectuate the preferred mode of service.
ALEXIS M. ESCOBEDO