PROSEDUR

PENYELIAAN KERJA BERKALA PAVEMEN

[JKR.PK(SJ).01.04.03]

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : i

KANDUNGAN Muka Surat

1.0 OBJEKTIF........................................................................................................ 1
2.0 SKOP ............................................................................................................... 1
3.0 RUJUKAN ........................................................................................................ 1
4.0 DEFINISI .......................................................................................................... 1
5.0 SINGKATAN .................................................................................................... 3
6.0 PROSES KERJA DAN TANGGUNGJAWAB .................................................. 5
6.1 Proses Kerja Berkala Pavemen ........................................................................ 5
7.0 REKOD KUALITI ............................................................................................. 6
8.0 LAMPIRAN ...................................................................................................... 6
(i) Borang Kajian Awalan dan Lawatan Tapak (Berkala Pavemen)
(ii) Senarai Semakan Kerja (Berkala Pavemen)
(iii) Borang Pemeriksaan Bersama
(iv) Anggaran Penyenggaraan Jalan (Borang APJ)
(v) Surat Laksana Kerja (SLK)
(vi) Arahan Kerja (AK)
(vii) Senarai Semakan Pelan Pengurusan Trafik TMP
(viii) Perakuan Siap Kerja
(ix) Sijil Siap Kerja (CoC)

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/7

1.0 OBJEKTIF

Prosedur ini adalah garis panduan pengurusan dan penyeliaan kerja berkala
pavemen dalam menzahirkan produk sebagaimana dasar dan objektif kualiti.

2.0 SKOP

Prosedur ini digunapakai oleh semua kakitangan dan pegawai yang


ditugaskan dalam menyelia kerja berkala pavemen di Jalan Persekutuan
Semenanjung Malaysia di bawah tanggungjawab JKR Malaysia dan JKR
Negeri serta memenuhi syarat-syarat yang ditetapkan dalam Dokumen
Perjanjian Penswastaan Penyenggaraan Jalan-Jalan Persekutuan di
Semenanjung Malaysia.

3.0 RUJUKAN

3.1 Dokumen Perjanjian Penswastaan Penyenggaraan Jalan-Jalan


Persekutuan di Semenanjung Malaysia bertarikh 22 Disember 2000.

3.2 Dokumen Perjanjian Tambahan Penswastaan Penyenggaraan Jalan-


Jalan Persekutuan di Semenanjung Malaysia yang berkuatkuasa dari
masa ke semasa.

4.0 DEFINISI

4.1 Dokumen Perjanjian Penswastaan


Dokumen Perjanjian Penswastaan merupakan dokumen perjanjian
antara Kerajaan Malaysia dengan syarikat konsesi yang mengandungi
surat perjanjian, skop kerja, syarat-syarat perjanjian, kadar harga dan /
atau maklumat yang berkaitan yang perlu.

4.2 Bahagian Senggara Fasiliti Jalan (Zon) (BSFJ (Zon))


BSFJ (Zon) adalah pejabat di CSFJ yang bertindak sebagai Pengurus
Program dan melaksanakan auditan dan pemantauan ke atas
Penyenggaraan Jalan Persekutuan di Semenanjung Malaysia

4.3 Bahagian Jalan, JKR Negeri


Bahagian Jalan, JKR Negeri adalah pejabat yang melaksanakan
pengurusan dan penyenggaraan Aset Persekutuan untuk
Penswastaan Penyenggaraan Jalan Persekutuan di Semenanjung
Malaysia.

4.4 Surat Laksana Kerja


Surat Laksana Kerja adalah satu surat yang menggariskan syarat
syarat laksana kerja yang dikeluarkan oleh pegawai yang diberi kuasa
kepada syarikat konsesi di bawah Perjanjian Penswastaan
Penyenggaraan Jalan-jalan Persekutuan Di Semenanjung Malaysia.

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 2/7

Surat ini dikeluarkan berdasarkan klausa 10.4 – Performance of The


Works (Dokumen Perjanjian Penswastaan).

4.5 Borang PJP01


Borang PJP01 adalah perakuan bayaran kerja penyenggaraan jalan
persekutuan.

4.6 Harta Pelanggan


Harta Pelanggan adalah harta/ komponen/ produk yang dibekalkan/
diserahkan oleh pelanggan kepada JKR bagi tujuan pelaksanaan
projek seperti tanah bagi Tapak Projek / Perabot / Peralatan
Mekanikal/ Peralatan Elektrikal.

4.7 Kalibrasi
Kalibrasi adalah merupakan ketentukuran bagi sesuatu peralatan
mengikut piawaian atau makmal yang diiktiraf mengikut tempoh sah
dan julat ketepatan yang dibenarkan.

4.9 Method Statement


Method Statement merupakan pernyataan tatacara/ kaedah kerja
pembinaan yang dicadangkan untuk dilaksanakan oleh pihak
kontraktor bagi sesuatu aktiviti pembinaan/ pemasangan produk yang
berkaitan.

4.10 Mock-up
Mock-up merupakan aktiviti pembinaan/ pemasangan yang
dilaksanakan oleh konsesi/ perunding untuk dijadikan sebagai penanda
aras yang dipersetujui oleh PTB sebelum pembinaan keseluruhan.

4.11 Lukisan Kerja dan Distress Mapping


Lukisan Kerja dan distress mapping merupakan cadangan lukisan
yang menunjukkan lokasi pembaikan yang hendak dijalankan.

4.13 Sijil Siap Kerja (CoC)


Sijil Siap Kerja adalah satu perakuan dari JKR Daerah yang diberi
kuasa untuk mengesahkan kerja siap dilaksanakan sepenuhnya/
sebahagian mengikut klausa 11.3 - Perakuan Siap Kerja (Dokumen
Perjanjian Penswastaan).

4.14 Syarikat Konsesi


Syarikat konsesi adalah syarikat yang dinamakan di dalam Dokumen
Perjanjian Penswastaan.

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 3/7

5.0 SINGKATAN

APJ - Anggaran Penyenggaraan Jalan.

BSFJ (Zon) - Bahagian Senggara Fasiliti Jalan (Utara, Tengah/Timur,


Selatan), Cawangan Senggara Fasiliti Jalan.

CSFJ - Cawangan Senggara Fasiliti Jalan, Ibu Pejabat JKR


Malaysia.

CMGD - Perakuan Siap Memperbaiki Kecacatan (Certificate of


Completion of Making Good Defects).

CoC - Sijil Siap Kerja (Certificate of Completion).

JD - Jurutera Daerah.

JS - Jurutera Senggara.

JF - Jurutera Fasiliti.

KKR - Kementerian Kerja Raya.

KPPK(Zon) - Ketua Penolong Pengarah Kanan, Bahagian Senggara


Fasiliti Jalan (Utara, Tengah/Timur, Selatan) di CSFJ.

KPPJ - Ketua Penolong Pengarah Jalan, Bahagian Jalan, JKR


Negeri.

NOD - Notis Kecacatan (Notification of Defects).

NCP - Produk Yang Tidak Mematuhi Spesifikasi (Non-


Comformance Product).

NCR - Laporan Ketidakpatuhan (Non-Conformance Report)

PTJ - Pusat Tanggungjawab.

PDI - Pre Delivery Inspection.

PWT - Performance Witness Testing.

PTB - Penyelia Tapak Bina.

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 4/7

PCSFJ - Pengarah Cawangan Senggara Fasiliti Jalan, Ibu Pejabat


JKR Malaysia.

PB - Pengarah Berkenaan yang terdiri dari Pengarah


Cawangan Ibu Pejabat JKR Malaysia, Pengarah JKR
Negeri/ Pengarah JKR Wilayah Persekutuan/Pengarah
JKR Pembangunan Persekutuan/Pengarah Unit Khas
JKR.

PTJ - Pusat Tanggungjawab.

SLK - Surat Laksana Kerja.

S.O.R - Schedule of Rates.

SST - Surat Setuju Terima.

SPSJ - Sistem Pengurusan Senggara Jalan.

WK - Wakil Kerajaan iaitu Ketua Pengarah Kerja Raya JKR


Malaysia.

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
No. Keluaran : 00
PROSEDUR No. Pindaan : 00
PENYELIAAN KERJA BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 5/7

6.0 PROSES KERJA DAN TANGGUNGJAWAB

6.1 Proses Kerja Berkala Pavemen

1. Semak & Lulus Pelan


Pengurusan Trafik (TMP) yang
disediakan oleh konsesi.
Rujuk Borang:
(i) Senarai Semakan Pelan
Pengurusan Trafik
JKR.PK(SJ).01.04.03-TMP
(ii) Arahan Teknik (Jalan) 2C/85
1. Keluar Surat (Manual on Traffic Control
1. Semakan senarai Laksana Kerja dan Arahan Devices: Temporary Sign and
kelulusan dan mengadakan Tiada Kerja (AK) Work Zone Control)
pindaan Rujuk Borang: 1. Pengesahan siap kerja
lawatan tapak
(i) Surat Laksana Kerja Rujuk Borang:
INPUT Rujuk Borang : 2. Pemeriksaan dan penyeliaan
JKR.PK(SJ).01.04.03-SLK tapak (i) Perakuan Siap Kerja
Kajian Awalan dan Lawatan
1. Senarai (ii) Arahan Kerja (AK) Rujuk Borang: JKR.PK(SJ).01.04.03-PSK
Tapak Kerja (Berkala
Kelulusan Kerja Terima dari JKR.PK(SJ).01.04.03-AK (i) Senarai Semakan Kerja (ii) Sijil Siap Kerja (CoC)
Pavemen)
Berkala Pavemen BSFJ (Zon) Berkala Pavemen JKR.PK(SJ).01.04.03-COC
JKR.PK(SJ).01.04.03-1
senarai 2. Daftar kerja dalam JKR.PK(SJ).01.04.03-2 (iii) Borang Pemeriksaan
sistem SPSJ (ii) Project Quality Plan (PQP) Bersama
2. Surat Kelulusan kelulusan 2. Pastikan projek mematuhi OUTPUT
kerja dan CSFJ JKR.PK(SJ).01.04.03-3
Peruntukan skop kerja dalam Perjanjian 1. Terima permohonan
daripada KKR peruntukan Penswastaan (Appendix II – Produk
pindaan daripada KPPJ. 2. Bayaran
Periodic Maintenance Work). 3. Untuk kerja pemulihan jalan akhir siap
Rujuk Borang: Rujuk:
(reconstruction)
Arahan Penyenggaraan Prosedur Kewangan
Rujuk SPB:
Jalan (Borang APJ) JKR.PK(SJ).01.04.01
KPPJ/ JD JKR.PK(O).04-SKC.JL.1 hingga 8
JKR.PK(SJ).01.04.01-APJ Proses Kerja 6.5 –
KPPJ JKR.PK(O).04-SKC.AM.2
Bayaran Siap Kerja
PTB Ada pindaan 2. Mohon kelulusan pindaan Proses Kerja 6.7 –
dari KKR Bayaran Wang Tahanan

3. Maklumkan kelulusan KPPJ/JD/PTB 3. Kemaskini sistem SPSJ


kepada KPPJ dan MySPATA (sekiranya
Keluar NCP (Jika ada) berkenaan)
Rujuk:
Prosedur Kawalan Produk Yang
KPPK
Tidak Memenuhi Spesifikasi
BSFJ(Zon)
JKR.PK(SJ).01.04.06
KPPJ/JD/PTB

KPPJ/JD/PTB

@ HAKCIPTA JKR MALAYSIA

DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 6 /7

7.0 REKOD KUALITI

BIL. JENIS REKOD LOKASI TEMPOH


PENYIMPANAN

1 Surat Laksana Kerja Fail JD 7 Tahun


(SLK)

2 Sijil Siap Praktikal Fail JD 7 Tahun

3 Sijil Siap Membaiki Fail JD 7 Tahun


Kecacatan (CMGD)

4 Borang Kalibrasi Fail JD 7 Tahun


Peralatan

5 Rekod/Borang/ Senarai Fail JD 7 Tahun


Semakan bagi
Pemeriksaan/ Pengujian

6 Minit Mesyuarat Pra Fail JD 7 Tahun


Pembinaan/ Tapak

8.0 LAMPIRAN

(i) Borang Kajian Awalan dan Lawatan Tapak (Berkala Pavemen)


[Borang JKR.PK(SJ).01.04.03-1]

(ii) Senarai Semakan Kerja (Berkala Pavemen)


[Borang JKR.PK(SJ).01.04.03-2]

(iii) Borang Pemeriksaan Bersama


[Borang JKR.PK(SJ).01.04.03-3]

(iv) Anggaran Penyenggaraan Jalan (Borang APJ)


[Borang JKR.PK(SJ).01.04.01-APJ]

(v) Surat Laksana Kerja (SLK)


[Borang JKR.PK(SJ).01.04.03-SLK]

(vi) Arahan Kerja (AK)


[Borang JKR.PK(SJ).01.04.03-AK]

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 7/7

(vii) Senarai Semakan Pelan Pengurusan Trafik TMP


[Borang JKR.PK(SJ).01.04.03-TMP]

(viii) Perakuan Siap Kerja


[Borang JKR.PK(SJ).01.04.03-PSK]

(ix) Sijil Siap Kerja (CoC)


[Borang JKR.PK(SJ).01.04.03-COC]

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-1
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

BORANG KAJIAN AWALAN & LAWATAN TAPAK


(BERKALA PAVEMEN)
1. LAWATAN TAPAK:
Tajuk Projek:
Bil Dokumen HDM4 NOD Aduan Permohonan Khas
Penerimaan Senarai
a.
Tanda ( √ ) di ruangan

BUTIRAN LOKASI

Negeri

b. Daerah

Nama jalan / laluan

Seksyen

c. Anggaran Kos

Kaedah Rawatan
d.
Jenis & Punca Kerosakan

PanjangJalan/Lebar
e.
(LHS/RHS)
Gambar-gambar
f. (seperti dilampirkan)
kerosakan di lokasi
Diperiksa bersama oleh JKR & Konsesi :

__________________ ___________________
Nama dan Jawatan : Nama dan Jawatan :
(PTB) (Konsesi)

Tarikh : Tarikh :
2. ULASAN
Komen dan Ulasan Keseluruhan :
i. Peruntukan iv. Lokasi
ii. Kaedah Rawatan v. Butiran
iii. Tempoh Kerja
…………………………………………………………………………………………………………………….
…………………………………………………………………………………………………………………….
…………………………………………………………………………………………………………………….
Disahkan oleh :

(JD)

Nama dan Jawatan :


Tarikh :

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-2
No. Keluaran : 00
PROSEDUR No. Pindaan : 00
PENYELIAAN KERJA BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/4

SENARAI SEMAKAN KERJA (BERKALA PAVEMEN)

Tarikh Pemeriksaan

Seksyen Seksyen
Negeri Daerah Laluan / FT
Mula Akhir
Lokasi Projek
Keterangan Projek

PROGRAM Tandakan
Inlay / Overlay
Reconstruction
Mill, Regulate & Pave
CIPR

AKTIVITI DI TAPAK
Pengukuran
Pengesahan
Bil. Aktiviti Kerja / Penilaian Komponen Kerja Catatan Rujukan
JKR
Konsesi
1 Kelulusan TMP Pengesahan & Perakuan ATJ 2C/85
Penentuan Laluan dan
Seksyen terlibat

Pengauditan & Pemeriksaan Setting Out & Marking


2
Tapak Survey data Jurukur
Tanah
Pengukuran di tapak

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-2
No. Keluaran : 00
PROSEDUR No. Pindaan : 00
PENYELIAAN KERJA BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 2/4

Pengukuran
Pengesahan
Bil. Aktiviti Kerja / Penilaian Komponen Kerja Catatan Rujukan
JKR
Konsesi
3 Penyediaan Tapak Pemeriksaan
Clause 4.2.4.3 b
▪ Peralatan Mesin Cukup
(JKR/SPJ)
Clause 4.2.4.3 b
▪ Kebersihan Permukaan Bersih
(JKR/SPJ)
Clause 4.2.4.3 b
▪ Semburan Tack Coat Rata
(JKR/SPJ)
Clause 4.2.4.3 b
▪ Cuaca Kering/ Basah
(JKR/SPJ)
4 Pembinaan
Pematuhan papantanda di
▪ TMP di tapak ATJ 2C/85
TMP
Pematuhan QC dan
▪ Quality Control Konsesi
Spesifikasi
Kelulusan bahan
Penyediaan Subbase & Clause 4.4-Table
▪ Ketebalan
Road base 4.13(JKR/SPJ)
Proposed 200
Pemadatan : MDD & FDT
m/test interval
o o Clause 4.2.4.5
▪ Suhu Asphalt 125 C ≤ suhu - ≤ 135 C
f.g.h. (JKR/SPJ)
Pengambilan sampel
▪ Sampel setiap 200 ton
Premix
o
Suhu antara ≤110 C -
o

125 C
Pemadatan
Jentera Pemadatan

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-2
No. Keluaran : 00
PROSEDUR No. Pindaan : 00
PENYELIAAN KERJA BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 3/4

Pengukuran
Pengesahan
Bil. Aktiviti Kerja / Penilaian Komponen Kerja Catatan Rujukan
JKR
Konsesi
ACWC ≤ 50 mm (as per
design) Prescribed as
▪ Ketebalan Premix
ACBC ≤ 60mm (as per treatment method
design)
Offset 100mm longitudinal Clause 4.2.4.5 h.
▪ Construction Joint
joints (JKR/SPJ)
Offset 500mm Tranverse Clause 4.2.4.5 h.
joints (JKR/SPJ)
Plate Test / Vernier
▪ Thermoplastic Rd. Marking
Caliper
Moisture Content: 3 test/
BS1377: Part 9
daily operation
Compaction: 3 test/ layer BS1377: Part 10
▪ CIPR Unconfined Compression
Strength test : every JKR/SPJ/1988
2000m2
Cutting Depth : 2 test
Draft Ream Spec.
/250m cut
Clause 4.2.3
Kelulusan bahan
▪ Bahu Jalan (JKR/SPJ)
Padat/ Rata / Chamber
Mesyuarat Kemajuan
Tapak
Marshall Test & Ketebalan Clause 4.2.4.5 i.j.
5 Semasa / Selepas Pembinaan Asphalt (JKR/SPJ)
Chamber Pavemen
Clause 4.4.3
Surface Regularities / IRI
(JKR/SPJ)

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-2
No. Keluaran : 00
PROSEDUR No. Pindaan : 00
PENYELIAAN KERJA BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 4/4

Pengukuran
Pengesahan
Bil. Aktiviti Kerja / Penilaian Komponen Kerja Catatan Rujukan
JKR
Konsesi
Pemeriksaan
Request for Inspection
6 Pemeriksaan PTB - Konsesi Bersama
Joint Measurement Sheet Proses Verifikasi

Nota: Rujukan berdasarkan Spesifikasi JKR : SPJ

Disediakan oleh : Disemak oleh: Ditentu sahkan oleh :

…………….............……….. …………………......….. …………………….............


Jurutera ( Syarikat Konsesi ) Syarikat Konsesi Penyelia Tapak Bina (JKR)

Tarikh : …………….. Tarikh : …………….. Tarikh : ……………..

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-3
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/2

BORANG PEMERIKSAAN BERSAMA


(BERKALA PAVEMEN/ BERKALA BUKAN PAVEMEN)

Kriteria Penerimaan
A Terima
B Terima Dengan Ulasan
C Tidak Diterima
D Belum Siap

PROJEK : KONSESI :
RUJUKAN :
(No projek, laluan dan seksyen, daerah / negeri)

TARIKH TERIMA NOTIS PERAKUAN SIAP KERJA :


TARIKH PEMERIKSAAN :
ITEM DESCRIPTION A B C D ULASAN

1 KERJA PAVEMEN
a. Permukaan jalan bersih dan sedia untuk
penerimaan.
b. Pemeriksaan Finished Surface Condition
meliputi antaranya kawasan retakan, ravelling,
bleeding, surface irregularity dan lain-lain yang
berkaitan (yang memungkinkan penerimaan
tidak dapat di buat)
c. Hamparan di buat mengikut dan mematuhi
garisan serta ukuran. (Nyatakan & periksa
secara rambang ukuran panjang dan lebar)
d. Lapisan pavemen mempunyai ketebalan purata
tidak kurang dari yang telah di tetapkan.
e. Lain - lain :

f. Outstanding Works (If any)

g. Kecacatan / kerosakan nyata yang di kesan


(Sila isikan di borang kerosakan / kecacatan).

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-3
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 2/2

ITEM DESCRIPTION A B C D ULASAN

GARISAN JALAN

a. Setting out & tanda di atas permukaan jalan


seperti di nyatakan.
b. Ketebalan & lebar hamparan tanda/garisan
jalan seperti dinyatakan/ditetapkan.
c. Hamparan & kawalan daripada kerosakan.

d. Pencapaian keperluan tahap pantulan.

e. Kecacatan / kerosakan nyata yang di kesan


(Sila isikan di borang kerosakan / kecacatan)
3 ROAD SHOULDER

a. Kelulusan bahan

b. Pemadatan dan kamber

4 ROAD FURNITURE

a. Mengikut spesifikasi JKR

b. Berfungsi

5 PEMERHATIAN-PEMERHATIAN LAIN

a.

b.

c.

6 KOMEN KESELURUHAN

Pemeriksaan Bersama & Disaksikan :

(PTB) (SYARIKAT
KONSESI)
Nota :

1. Tarikh CoC :

2. DLP ( Mula / Tamat ) :

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.01-APJ
No. Keluaran : 00
PROSEDUR
No. Pindaan : 00
PERANCANGAN DAN KAWALAN KEWANGAN
Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

BORANG ANGGARAN PENYENGGARAAN JALAN (BORANG APJ)

PROGRAM PENYENGGARAAN JALAN PERSEKUTUAN


TAHUN: _______ / TARIKH: _________
NEGERI:_____________________________
MAKLUMAT PROJEK / KERJA STATUS* CATATAN

SEKSYEN/ LOKASI
BAYARAN %
KOD * NAMA KM KERJA* KOS HARGA NAMA
BIL DAERAH NO. PANJANG / PERIHAL INTERIM/
AKTIVITI LALUAN ANGGARAN SEBENAR KONTRAKTOR P T C F
LALUAN BIL L/R/ KERJA MUKTAMAD
DARI KE L&R KEWANGAN FIZIKAL
/MEDIAN

1
2

Disediakan oleh (JD/ KPPJ/ KPPK ZON) : Diluluskan oleh (KPPK ZON/ PCSFJ) :

_______________________________ _______________________________
Nama : Nama :
Tarikh : Tarikh :

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-SLK
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA BERKALA No. Pindaan : 00
PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

SURAT LAKSANA KERJA


(BERKALA PAVEMEN/ BERKALA BUKAN PAVEMEN)

Ruj. Tuan :
Ruj. Kami :
Tarikh :
…………………………..
………………………….
.....................................
Tuan,
PENSWASTAAN PENYENGGARAAN JALAN –JALAN PERSEKUTUAN DI SEMENANJUNG MALAYSIA
- Surat Laksana Kerja Bagi Kerja Berkala Pavemen/ Berkala Bukan Pavemen Tahun…..
Dengan segala hormatnya, saya merujuk kepada perkara di atas.
Merujuk kepada perkara tersebut diatas, dengan hormatnya dimajukan rujukan Arahan Kerja berikut
untuk tindakan tuan selanjutnya:( Borang Arahan Kerja Disertakan )

Bil Rujukan Arahan Kerja Perihal Kerja Nilai Kerja (RM)

2. Berdasarkan klausa 10.4 syarat –syarat Perjanjian, sila laksanakan yang tertera di atas.
3. Kerja ini hendaklah dimulakan pada.......... ( dalam masa .......hari dari tarikh surat ini dan
disiapkan sepenuhnya pada ..................... (.......hari dari tarikh mula kerja). Sekiranya tuan gagal
memulakan atau menyiapkan kerja pada tarikh yang ditetapkan, pihak ketiga akan dilantik untuk
menyiapkan kerja tersebut berdasarkan klausa 17.6 dalam syarat-syarat Perjanjian.
4. Sekiranya terdapat perubahan kos tambahan ke atas nilai asal kos kerja seperti di Borang
Arahan Kerja, kelulusan ke atas perubahan ini perlu diperolehi terlebih dahulu dari pejabat ini
sebelum memulakan kerja yang melibatkan kos tambahan.
2. Sila kemukakan Pelan Kualiti Projek (Project Quality Plan) dalam tempoh empat belas (14) hari dari
tarikh surat ini yang mengandungi :
a. Carta Organisasi Dan Tanggungjawab Syarikat Konsesi;
b. Pelan Penyenggaraan Peralatan;
c. Program Kerja dan Method Statement;
d. Pelan Pemeriksaan dan Pengujian (Inspection and Testing Plan);
e. Lukisan Kerja dan Distress Mapping; dan
f. Pelan Pengurusan Trafik (Traffic Management Plan) dan pematuhan terhadap OSHA
( Occupational Safety Health Act) di tapak projek
Sekian, terima kasih.
* BERKHIDMAT UNTUK NEGARA *
Saya yang menurut perintah,

(Jurutera Daerah)
...................................................

s.k. BSFJ (Zon) ...........................

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-AK
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA BERKALA No. Pindaan : 00
PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

ARAHAN KERJA (AK)


(BERKALA PAVEMEN/ BERKALA BUKAN PAVEMEN)

Rujukan Arahan Kerja : Ruj.Kami :


Item : Tarikh :

Kepada :

1. Sila laksanakan kerja yang diperihalkan dalam jadual berikut:

Perihal Kerja Lokasi Nilai Kerja (RM)


Bil.
Laluan Dari Ke

Jumlah
Sila lihat lampiran untuk perihal kerja terperinci
Pegawai bertanggung jawab : Wakil Kerajaan :

...................................................... .........................................................
(PTB) (JD)
Tarikh : Tarikh :

3. Diterima oleh :
(Tandatangan dan Cop Syarikat
Tarikh :
Konsesi)
Nama : Masa :

Kami ………………………… (Syarikat Konsesi) mengakui telah menyiapkan kerja dengan sempurna pada
4.
……………………
dan memohon bayaran daripada pihak tuan. Kerja sebenar yang dilakukan adalah seperti di Lampiran. Sekian,
terima kasih.

(Tandatangan Syarikat Konsesi.) Tarikh :

5. Kerja diatas telah disiapkan dengan sempurna pada ............... dan disyorkan bayaran dilakukan
dalam Bayaran Kemajuan Bulan No. ……………… Jumlah yang disyorkan adalah RM.......................................
(Sila lihat Lampiran untuk perkiraan)
Pegawai bertanggung jawab : Wakil Kerajaan :

(Tandatangan & Cop JKR) (Tandatangan & Cop JKR)


Tarikh : Tarikh :

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-TMP
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/2

SENARAI SEMAKAN PELAN PENGURUSAN TRAFIK (TMP)


(BERKALA PAVEMEN/ BERKALA BUKAN PAVEMEN)

PROJEK:
RUJUKAN:
(No. Projek, Laluan , Seksyen dan Daerah/Negeri)
TARIKH MULA PROJEK:
TARIKH SIAP PROJEK:

Bil. Perihal Butiran Ada* Tiada* Catatan*


A. Sistem Pengurusan Trafik
2. Pasukan Pengurusan Trafik disediakan. merangkumi:
i) Carta Organisasi Pasukan Pengurusan
Trafik
ii) Pegawai Keselamatan Trafik (Traffic Safety Officer)
iii) Supervision/ foreman
iv) Traffic Controller
3. Lukisan Pelan Pengurusan Trafik (TMP) disediakan oleh
Traffic Safety Officer mengandungi:
i) TMP lokasi sebenar yang akan digunakan.
(Setiap TMP ada tarikh serta lokasi pelaksanaan
berdasarkan Program Kerja)
ii) Zon Kawalan Trafik yang mencukupi dalam setiap
lukisan termasuk Advance Warning, Transition
Area, Buffer Area, Termination Area.
iii) Susunatur permohonan tipikal.
iv) Mendapat kelulusan PTB.
B. Perabut Jalan Sementara Ada* Tiada* Catatan
1. New Jersey Barriers jenis konkrit seperti di dalam
Arahan Teknik Jalan.
2. Light Weight Moveable Barriers seperti di dalam Arahan
Teknik Jalan.
3. Light Weight Moveable Traffic Guidance Cones seperti
di dalam Arahan Teknik Jalan.
4. Blinkers seperti di dalam Arahan Teknik Jalan.
5. Beacon Light.
6. String Delineators.
7. Reflectors dipasang pada setiap penghadang.
8. Flashing Arrow.
9. Sand Bag.
10. Temporary Guardrails with reflectors.
11. Temporary Lighting or temporary flood light.
C. Papantanda Sementara
1. Pemasangan semua papantanda sementara jenis
fluorescent orange prismatic retro-reflective sheeting
termasuk tiang bercat seperti di dalam lukisan.

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-TMP
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 2/2

Bil. Perihal Butiran Ada* Tiada* Catatan*


D. Jalan Lencongan Sementara
1. Kerja Tanah
i) Membina laluan sementara.
ii) Membina longkang tanah di laluan sementara (jika
berkenaan).
iii) Penanaman rumput secara rapat (jika berkaitan).
2. Jalan Berturap
i) Membina jalan berturap sementara (jika
berkenaan).
3. Garisan Jalan
Menyediakan garisan jalan sementara, termasuk :
i) Garisan tepi (edges lines).
ii) Garisan tengah (centre lines).
iii) Memadam garisan jalan sedia ada (remove
existing road marking).
E. Laporan & Manual Penyenggaraan TMP
1. Pelan Pengurusan Kemalangan dan laporan (jika
berkenaan) merangkumi :
i) Carta Aliran Tindakan (Accident/ Incident Action
Flow Chart).
ii) Emergency Response Plan (ERP).
iii) Traffic Control Safety Manual (jika berkaitan).
2. Removeable of Temporary Road Diversion and
structures upon completion of project.
F. Lain-lain (jika diperlukan, seperti senarai di bawah) ;
1.
2.

Nota 1: * Sila tanda ( √ ) di ruangan ’Ada’ atau ’Tiada’ seperti berikut:


i) Diterima dan dipersetujui (accepted) - tanda ( √ ) di ruangan ’Ada’
ii) Diterima dengan ulasan (accepted with detail) - tanda ( √ ) di ruangan ’Tiada’ dan
nyatakan catatan jika perlu.
iii) Tidak Diterima (unaccepted) - tanda ( √ ) di ruangan ’Tiada’

Nota 2: Semakan Pelan Pengurusan Trafik ini digalakkan untuk dilaksanakan sebelum sesuatu projek Berkala
Pavemen/Berkala Bukan Pavemen dimulakan atau diluluskan pelaksanaannya di tapak.

ULASAN KESELURUHAN (SEKIRANYA ADA)

Diperiksa oleh: Disemak oleh:

________________ ________________
(PTB) (JD)
Nama dan Jawatan: Nama dan Jawatan:
Tarikh: Tarikh:

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-PSK
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

PERAKUAN SIAP KERJA


(BERKALA PAVEMEN/ BERKALA BUKAN PAVEMEN)

PROJEK :
NO. RUJUKAN SYARIKAT KONSESI :

Tarikh Mula Kerja Mengikut Program

Tarikh Siap Kerja Mengikut Program

Merujuk kepada klausa 10.4.2 syarat-syarat Perjanjian Penswastaan dan tertakluk


kepada perkara membaiki semula kecacatan, ketidaksempurnaan dan apa jua
kegagalan seperti yang dikehendaki di bawah klausa 10.7 yang akan timbul semasa
Tempoh Tanggungan Kecacatan, adalah dengan ini diperakukan bahawa kerja-kerja
pembinaan bagi projek yang tersebut di atas telah disiapkan sepenuhnya mengikut
rekabentuk, spesifikasi dan perjanjian.

Tandatangan Syarikat Konsesi Jawatan/ Cop Rasmi :

…………………….

Nama : Tarikh :

@ HAKCIPTA JKR MALAYSIA


DOKUMEN TERKAWAL
No. Ruj. Dokumen : JKR.PK(SJ).01.04.03-COC
PROSEDUR No. Keluaran : 00
PENYELIAAN KERJA No. Pindaan : 00
BERKALA PAVEMEN Tarikh : Jun 2016
JKR MALAYSIA Muka Surat : 1/1

KERAJAAN MALAYSIA
JABATAN KERJA RAYA

SIJIL SIAP KERJA


( CERTIFICATE OF COMPLETION )

Rujukan : ……………………………..

Pejabat :

Tarikh :
Kepada : ………………………………

TAJUK KERJA : PENSWASTAAN PENYENGGARAAN JALAN - JALAN PERSEKUTUAN


SEMENANJUNG MALAYSIA

JENIS KERJA : PENYENGGARAAN BERKALA PAVEMEN / BUKAN PAVEMEN *

No. Laluan / No Seksyen (Mula & Akhir) : FT…… / Seksyen dari ……. ke …….

Daerah / Negeri : …………..... / ……………….

Rujukan Arahan Kerja : ……………………………......

Tajuk Kerja : ……………………………......

Menurut Klausa 11.3 Syarat-syarat Perjanjian, dan tertakluk kepada penyiapan apa-apa kerja yang
belum disiapkan dan pembaikan apa-apa kecacatan, ketidaksempurnaan, kesusutan atau apa-apa
kerosakan lain apajuapun sebagaimana yang dikehendaki di bawah Klausa 10.7 Syarat-syarat
Perjanjian dan yang mungkin terzahir dalam Tempoh Tanggungan Kecacatan maka adalah dengan
ini diperakui bahawa seluruh Kerja-Kerja / Bahagian daripada Kerja-Kerja * seperti tersebut di atas
telah siap dengan memuaskan hati pada ____________ dan diambil milik pada ___________ dan
dengan itu Tempoh Tanggungan Kecacatan untuk Kerja-Kerja / Bahagian daripada Kerja-Kerja *
tersebut bermula pada ____________ dan akan berakhir pada _______________.

………..………………………………….
Jumlah Bayaran Pengawai Yang Diberikan Tanggungjawab
Nama :
Jumlah Wang Tahanan
Jawatan :
Nota:
(*) - Potong bahagian yang tidak berkenaan

@ HAKCIPTA JKR MALAYSIA