Professional Documents
Culture Documents
Complete Set - NBS - Minor Works Version - JCT
Complete Set - NBS - Minor Works Version - JCT
Complete Set - NBS - Minor Works Version - JCT
CONTENTS
C20 Demolition
C45 Damp proof course renewal/ Insertion
C46 Cavity wall tie renewal/ insertion
C52 Fungus/ Beetle eradication
1
C20 DEMOLITION
05 SURVEY: Before starting work, carry out a survey and submit a report and method
statement covering all relevant matters listed below and in Health and Safety
Executive Guidance Note GS29/1 paragraph 32:
- Condition and demolition methods of the structure(s).
- Removal methods of any hazardous materials.
- Type and location of adjoining or surrounding premises which may be adversely
affected by the Works.
- Identification and location of services.
15 BENCH MARKS: Report any bench marks and other survey information found. Do
not remove or destroy unless instructed.
35 DRAINS IN USE: Protect drains and fittings still in use and keep free of debris at all
times. Make good any damage arising from demolition work and leave clean and in
working order at completion.
50 WORKMANSHIP GENERALLY:
- Demolish structure(s) in accordance with BS 6187 and Health and Safety Executive
Guidance Notes GS29/1, 3 and 4.
- Operatives must be appropriately skilled and experienced for the type of work and
hold or be training to obtain relevant CITB Certificates of Competence.
- Site staff responsible for supervision and control of the work are to be experienced in
the assessment of the risks involved and in the methods of demolition to be used.
55 SITE HAZARDS:
- Prevent fire or explosion caused by gas or vapour.
- Reduce dust by periodically spraying with water.
- Take adequate precautions to protect site operatives and the general public from
vibration, dangerous fumes and dust arising during the course of the Works.
- Cordon off site to prevent ingress from non site operatives
60 ADJOINING PROPERTY:
- Provide adequate temporary support and protection to adjoining property at each
stage.
- Prevent damage to adjoining property and leave no unnecessary or unstable
projections.
- Do not disturb support to foundations of adjoining property.
- Report any defects exposed or becoming apparent in adjoining property.
- Promptly repair any damage caused to adjoining property.
- Prior to works commencement and during the works ensure that the Party Wall Act
has been complied with (employer to arrange)
65 STRUCTURE(S) TO BE RETAINED:
- Adequately protect parts of existing structure(s) that are to be kept in place.
- Cut away and strip out the minimum necessary.
- Prevent debris from overloading any part of the structure which is not to be
demolished.
86 COMPLETION: Clear away all debris and leave the site tidy on completion. Grade
the site to follow the levels of adjacent areas.
90 OWNERSHIP: Components and materials arising from the demolition work are to
become the property of the Contractor except where otherwise provided. Remove
from site as work proceeds.
12 REMEDIAL WORK
- Carry out remedial work as shown to be necessary by the survey
50 GUARANTEE
- Type: Insurance backed. Administered by an independent insurance protection
company.
- Guarantee period (minimum): 20 years from Practical Completion.
- Documentation: Provide certificates/ guarantees at Practical Completion.
C46 CAVITY WALL TIE RENEWAL/INSERTION
15 DRYING OUT: Ensure that effective measures to ventilate and dry out damp building
fabric are commenced as soon as possible. Agree methods with the CA.
20 DRY ROT:
- Do not disturb fruiting bodies. Spray with fungicide, remove carefully and clean
down.
- Agree the extent of removal of infected timber, plaster and other finishes with the CA.
- Remove infected materials immediately in bags or as necessary to ensure that no other
parts of the building become contaminated. Dispose of materials safely at a tip
approved by a Waste Regulation Authority.
25 WET ROT: Cut out all rotten material until sound timber is reached, having first
agreed with the CA that this will not adversely affect the building fabric.
35 CLEANING: Thoroughly clean down all surfaces in affected areas. Remove all loose
material, dust and debris and remove from site without delay.
04 SITE INVESTIGATION
- Report: a report is to be prepared prior to any excavation works commencing on site.
10 PREPARATORY WORK
- Trees, shrubs and hedges to be removed: Cut down, grub up main roots and fill voids.
- Clear site of rubbish and vegetation. Grub up large roots.
- Arisings: Remove from site.
20 STRIPPING TOPSOIL
- General: Excavate from required areas to full depth of top soil and keep separate
ready for re-use.
25 INSPECTING FORMATIONS
- Notice: Make advance arrangements for inspection of formations for work sections as
previously agreed with CA.
27 ADJACENT EXCAVATIONS
- Timing of excavations in close proximity: Complete deepest excavation first.
30 OBSTRUCTIONS
- Recorded foundations, beds, drains, etc: Break out and seal off drain ends. Remove
contaminated earth.
- Unrecorded foundations, beds, basements, filling, tanks, service pipes, drains, etc:
Give notice.
35 EXCESS EXCAVATIONS
- Excavation taken wider than required: Backfill as instructed by CA.
- Excavation taken deeper than required: Backfill with well graded granular material or
with lean mix concrete as instructed by CA.
53 WATER
- Generally: Keep excavations free from water until foundations and below ground
constructions are completed.
60 BACKFILLING TO FOUNDATIONS
- Under oversite concrete and pavings: Hardcore as clause 65.
- Under grassed or landscaped areas: Material excavated from the trench, laid and
compacted in 300 mm layers.
62 FROST SUSCEPTIBILITY
- General: Except as allowed below, fill must be non frost-susceptible as defined in
Transport Research Laboratory Report SR 829 'Specification for the TRRL frost-
heave test'.
- Frost-susceptible fill: Use only within the external walls of buildings below spaces
that will be heated. Protect from frost during construction.
65 HARDCORE
- Fill: Granular material, free from harmful matter and excessive dust or clay, well
graded, passing a 75 mm BS sieve and one of the following:
- Crushed hard rock or quarry waste.
- Crushed concrete, brick or tile, free from plaster.
- Gravel or hoggin.
- Filling: Spread and level both backfilling and general filling in layers not exceeding
150 mm. Thoroughly compact each layer.
75 BLINDING TO HARDCORE
- Surfaces to receive sheet overlays or concrete: Blind with:
- Concrete where shown on drawings; or
- Sand, fine gravel, or other approved fine material applied to provide a close
smooth surface.
- Permissible deviation on surface level: +0 -25 mm.
10 WORK BELOW GROUND: Vertical faces of strip footings, bases and slabs may be
cast against faces of excavation, provided the faces are sufficiently accurate and stable
and adequate measures are taken to prevent contamination of concrete.
40 FORMWORK:
- Construct accurately and robustly to produce finished concrete to the required
dimensions. Formed surfaces must be free from twist and bow, all intersections, lines
and angles being square, plumb and true.
- Construct (including joints between forms and completed work), to prevent loss of
grout, using seals when necessary. Secure tight against adjacent concrete to prevent
formation of steps.
- Fix inserts or box out as required in correct positions before placing concrete. Form
all holes and chases. Do not cut hardened concrete without approval.
E30 REINFORCEMENT FOR IN SITU CONCRETE
70 FIXING REINFORCEMENT:
- Where ground bearing slabs are reinforced with a single layer of fabric in the upper
part of the slab, the fabric may be placed in position on top of the first compacted
layer of concrete, followed by the top layer of concrete, placed within two hours of
the first layer.
- In all other cases fix reinforcement before the concrete is placed, providing suitable
spacers at not more than 1 m centres or closer spacing as necessary to support in
position and maintain the specified cover.
- Fix adequately, using tying wire, which must not intrude into the concrete cover.
E41 WORKED FINISHES TO IN SITU CONCRETE
10 FINISHING GENERALLY
- Timing: Carry out finishing operations at optimum times in relation to the setting and
hardening of the concrete.
- Prohibited treatments to surfaces: Wetting to assist working and sprinkling cement.
30 TROWELLED FINISH
- Floating: Float to an even surface with no ridges or steps, then immediately
commence curing as section E10.
- Trowelling: When suitably stiff, trowel to a uniform, smooth but not polished surface,
free from trowel marks and other blemishes, and suitable to receive specified flooring
material. Resume curing without delay.
60 PRECAST UNITS:
- Lift units at designed lifting points only.
- Set on level bearings ensuring not less than the minimum seating recommended by
manufacturer.
- Form openings, sinkings and junctions with walls in accordance with manufacturer's
recommendations, unless detailed otherwise.
- Do not cut units except as recommended by manufacturer.
70 CONCRETE INFILL:
- Thoroughly clean and wet surfaces of precast units.
- Place concrete, avoiding segregation, and compact thoroughly to eliminate voids.
80 LATERAL RESTRAINT:
- Ensure that floors/roof decks tightly abut walls.
- Straps:
Position at centres as required to secure floors/roof decks to abutting external cavity
walls.
20 RECONSTRUCTED STONEWORK
- Walling type: to match existing
Finish/colour: to match existing
Special shapes: do not use without approval or as per design drawings
- Mortar: As section Z21.
- Joints: to match existing
40 ENGINEERING BRICKWORK
- Bricks: to BS 3921, Engineering Class A
- Mortar: As section Z21, mix: as specified.
- Bond: English
- Joints: Flush.
51 BASIC WORKMANSHIP:
- Store bricks/blocks in stable stacks clear of the ground. Protect from inclement
weather and keep clean and dry.
- Build walls in stretching half lap bond when not specified otherwise.
- Lay bricks/blocks on a full bed of mortar; do not furrow. Fill all cross joints and collar
joints; do not tip and tail.
- Rack back when raising quoins and other advance work. Do not use toothing.
- Bring both leaves of cavity walls to the same level at
– Every course containing rigid ties.
– Every third tie course for double triangle/butterfly stainless steel ties.
– Courses in which lintels are to be bedded.
- Do not carry up any one leaf more than 1.5 m in one day unless permitted by the CA.
55 FACEWORK:
- Facework to start not less than 150 mm below finished level of external paving or soil.
- Select bricks/blocks with unchipped arrises. Cut with a masonry saw where cut edges
will be exposed to view.
- Keep courses evenly spaced using gauge rods. Set out carefully to ensure satisfactory
junctions and joints with adjoining or built-in elements and components.
- Protect against damage and disfigurement, particularly arrises of openings and
corners.
60 ALTERATIONS/EXTENSIONS:
- Arrange brick courses to line up with existing work.
- Unless otherwise specified or agreed block bond new walls to existing by cutting
pockets not less than 100 mm deep, the full thickness of the new wall, and:
Brick to brick: 4 courses high at 8 course centres.
Brick to block, block to brick or block to block: Every alternate block course.
Bond new walling into pockets with all voids filled solid.
- Except where a straight vertical joint is specified, new and existing facework in the
same plane to be tooth bonded together at every course to give a continuous
appearance.
- Where new lintels or walling are to support existing structure, completely fill top joint
with semidry mortar, hard packed and well rammed to ensure full load transfer after
removal of temporary supports.
- Wall starter to be fixed to wall to bond new wall to existing wall
65 FIRE STOPPING: Fill joints around joist ends built into cavity walls with mortar to
seal cavities from interior of building.
66 FIRE STOPPING: Ensure a tight fit between brickwork and cavity barriers to prevent
fire and smoke penetration.
20 WORKMANSHIP GENERALLY:
- Cutting, dressing, laying and jointing of stone to be carried out by skilled masons.
Provide evidence of previous experience and details of work previously carried out.
- Store stone clear of the ground, protect from adverse weather and keep dry.
- Dampen stones to control suction as necessary and lay on their natural bed on a full
even bed of mortar with all joints filled and between 12–18 mm wide. Evenly
distribute different shapes, sizes and colours throughout the face of the wall to give a
consistent overall appearance and good bond with no long continuous vertical joints.
- Accurately plumb all wall faces, angles and features. Set out carefully to ensure
satisfactory junctions and joints with adjoining or built-in elements and components.
- Prevent damage to stonework and keep clean during construction and until Practical
Completion. Ensure that no mortar encroaches on face when laying. Turn back
scaffolding boards at night and during heavy rain.
25 GROUND LEVEL: Facing stonework to start not less than 150 mm below finished
level of external paving or soil except where shown otherwise.
30 CAVITY WALLS: Dress stones to give consistent thickness of leaf and ensure that
specified cavity width is maintained.
35 BONDERS: In walls which are faced both sides build in bonding stones of a length
two thirds the thickness of the wall, one to every square metre of each side of the wall
and staggered.
40 JOINTING: Finish exposed joints neatly and consistently as the work proceeds. After
the initial set has taken place, stipple joints with a stiff brush to remove laitance and
give a coarse texture.
45 ADVERSE WEATHER:
- Do not use frozen materials and do not lay on frozen surfaces.
- Do not lay stones:
- In cement gauged mortars when the air temperature is at or below 3°C.
- In hydraulic lime:sand mortars when the air temperature is at or below 5°C.
- Maintain temperature of the work above freezing until mortar has fully set.
- Protect newly erected walling against rain and snow by covering when precipitation
occurs and at all times when work is not proceeding.
- Rake out and replace mortar damaged by frost and where instructed, rebuild damaged
work.
F30 ACCESSORIES/SUNDRY ITEMS FOR BRICK/BLOCK/STONE WALLING
05 CAVITIES:
- Fill cavities with concrete up to adjoining external ground level maintaining a
minimum of 150 mm between top of fill and general ground level dpc. Concrete mix
to BS 5328, Designated mix GEN1 or Standard mix ST2, high workability.
- Clean off surplus mortar from joints on cavity faces as the work proceeds. Keep
cavities, ties and dpcs free from mortar and debris with laths or other suitable means.
08 WEEP HOLES:
- Form with plastics perpend at not greater than 1000 mm centres immediately above
base of cavity, external openings and stepped dpcs. Provide not less than two weep
holes over openings.
15 AIR BRICKS:
To BS 493, Class 1, built in as the work proceeds.
Material/Colour/Design: clay
Work size(s): to suit surrounding wall material.
17 VENTILATION DUCTS:
- Manufacturer and reference: as approved
- Install across cavity, sloping away from inner leaf, bedding fully in mortar to seal
cavity.
39 WALL STARTERS/CONNECTORS:
- Manufacturer and reference: as specified and/or approved
Material and finish: stainless steel
Size(s): as specified.
- Sealant to external vertical joint: as specified.
Colour: as specified.
Prepare joint and apply sealant as section Z22.
42 JOINT REINFORCEMENT
Width: 40–50 mm less in width than wall or leaf.
- Lay on an even bed of mortar in a continuous strip with 225 mm laps at joints and full
laps at angles. Keep back 20 mm from face of external work, 12 mm back from face
of internal work and finish mortar joint to normal thickness.
86 TILE SILLS:
- Plain clay tiles to BS EN 1304.
- Lay two courses as detailed, to break joint, fully bedded in 1:¼:3 cement:lime:sand
mortar as section Z21, with all joints filled and neatly finished flush.
94 FIREPLACE COMPONENTS:
To BS 1251.
96 CHIMNEY POTS:
- Manufacturer and reference: as specified and/or approved
- Bed solid in mortar specified for chimney stack.
F31 PRECAST CONCRETE SILLS/LINTELS/COPINGS/FEATURES
25 REINFORCEMENT:
- Type of reinforcement, unless otherwise specified: To BS 4449 and/or BS 4483, cut
and bent to BS 4466.
- Fix accurately and securely. Tying wire must not encroach into the concrete cover.
Cover spacers must not be used to concrete faces which will be exposed in the
finished work.
40 LAYING:
- Unless specified otherwise, lay components on a full bed of mortar used for adjacent
work.
- Leave bed joints to one piece sills/thresholds open except under end bearings. On
completion point with mortar to match adjacent work.
- Faces which will be exposed to view in the finished work to be kept clean with no
mortar encroachment.
10 FABRICATION OF MEMBERS:
- Steel sections: To BS 4-1, BS EN 10055, BS EN 10056 or BS EN 10210, as
appropriate.
- Steel: To BS EN 10025, grade S275.
- Surface condition: Free from heavy pitting and rust, burrs, sharp edges and flame
cutting dross.
- Cuts and holes: Form neatly and accurately.
- Welding: Metal arc method to BS EN 1011-2.
- Welded joints: Fully fused, with mechanical properties not less than those of the
parent metal.
- Site welding: Not allowed without permission.
20 SHOP PRIMING
- Preparation: Remove loose scale and rust, burrs, fins, sharp edges and weld spatter.
Clean out crevices. Thoroughly degrease and rinse with clean water. Allow to dry.
- Primer: Zinc phosphate modified alkyd.
- Application: Apply one full coat within 8 hours of cleaning surfaces, free from
runs and sags.
40 INSTALLATION
- Accuracy: Position members true to line and level. If necessary, use steel packs of
sufficient area to allow full transfer of loads to bearing surfaces.
- Fixing: Use washers under bolt heads and nuts.
- Tapered washers: Provide under bolt heads and nuts bearing on sloping surfaces.
Match taper to slope angle and align correctly.
G20 CARPENTRY/TIMBER FRAMING/FIRST FIXING
20 TRUSSED RAFTERS
- Standard: Design and fabricate to BS 5268-3 and BS EN 1059.
- Manufacturer: A firm currently registered under a third party quality assurance
scheme.
- Truss system: Agrément certified
- Types/weights of roofing/insulation/ceiling materials: as specified.
- Ancillary components to be supplied by fabricator: as specified.
- Trussed rafter treatment: as specified.
- Handling and storage: Keep trussed rafters vertical.
40 MOISTURE CONTENT
- Moisture content of timber and wood based products at time of installation: Not more
than:
- Covered in generally unheated spaces: 24%.
- Covered in generally heated spaces: 20%.
- Internal in continuously heated spaces: 20%.
45 FRAMING ANCHORS
- Fasteners: Nails not less than 30 x 3.75 mm galvanized or sherardized square twist.
- Fixing: Fix anchors securely using not less than the number of nails recommended by
anchor manufacturer.
50 ADDITIONAL SUPPORTS
- Provision: Where not shown on drawings, position and fix additional studs, noggings
or battens for appliances, fixtures, edges of sheets, etc.
- Material properties: Additional studs, noggings and battens to be of adequate size and
have the same treatment, if any, as adjacent timber supports.
65 JOIST HANGERS
- Material/finish: galvanised steel sheet.
- Size: To suit joist, design load and crushing strength of supporting construction.
70 TRIMMING OPENINGS
- Trimmers and trimming joists: Not less than 25 mm wider than general joists.
75 TRUSSED RAFTERS
- Inspection: Carefully inspect each truss before erection to ensure compliance with
shop drawings and specification.
- Erection: To BS 5268-3, clause 9.3 and TRA site installation guide.
- Trusses generally: Do not modify without approval.
- Damaged trusses: Do not use.
- Fixing: Fix securely with galvanized or stainless steel truss clips ensuring that bottom
chords of standard trusses and rafters of raised tie trusses bear fully on wall plates.
Use 32 x 3.5 mm galvanized or sherardized square twisted nails in every hole.
- Bottom chords of standard trusses: Do not fix to internal walls until roofing is
complete and cisterns are installed and filled.
95 STRUTTING:
- Type: One of the following:
- Herringbone strutting: At least 38 x 38 mm softwood.
- Solid strutting: At least 38 mm thick softwood and at least three quarters of joist
depth.
- Proprietary metal strutting.
- Fixing: Fix strutting between joists as follows:
- Joist spans of 2.5 to 4.5 m: One row at centre span.
- Joist spans over 4.5 m: Two rows equally spaced.
- Strutting must not project beyond top and bottom edges of joists.
- Outer joists: Block solidly to perimeter walls.
30 TIMBER BATTENS:
- Dry regularized softwood free from decay and insect attack (except ambrosia beetle
damage).
- Preservative treatment: CCA as section Z12 and British Wood Preserving and Damp-
proofing Association Commodity Specification C8.
50 FIXING SHEETS:
- Set out sheets with joints accurately aligned, of constant width and parallel to
perimeter edges.
- Securely fix sheets to supports without distortion and true to line and level.
- Fasteners to be evenly spaced in straight lines, in pairs across joints and sufficient
distance from edge of sheet to prevent damage.
- Exposed fasteners to be sealed with plastic washers and caps to match sheet or in
accordance with sheet manufacturer’s recommendations.
- Protect sheets from dirt, stains and damage until Practical Completion.
60 COVER STRIPS:
- Form straight runs in single lengths wherever possible. Location and method of
forming running joints to be submitted to the CA where not detailed.
H30 FIBRE CEMENT PROFILED SHEET CLADDING
70 FIXING GENERALLY:
- Cut sheets to give clean true lines.
- Lay sheets with exposed joints of side laps away from prevailing wind unless shown
otherwise on drawings. Lay verge sheets terminating with a crown.
- Ensure that ends of sheets and end laps are fully supported, with fixings at top of lap.
Ensure that raking cut edges at hips and valleys are fully supported.
- Drill all holes. Position at regular intervals in straight lines, centred on support
bearings. Locate fasteners centrally within holes that are oversized.
- Remove dust, etc. before fixing sheets into position.
- Check fastenings on completion and adjust as necessary to ensure that they are
watertight and sheeting is secure.
90 WARNING NOTICES:
- To BS 5378:Part 3 and as follows, fixed at points indicated on drawings.
- Warning sign reference A.2.4 with supplementary text sign, 'DANGER Fragile roof'.
- Mandatory sign reference A.3.1 with supplementary text sign. 'Use crawling boards'.
H60 PLAIN ROOF TILING
10 VERTICAL TILING
- Underlay: breathable polyethylene or polyester underfelt.
- Horizontal lap (minimum): 100 mm.
- Battens: As clause 30. Allow sufficient fixings to carry tiling
- Tiles: to match existing
- Fixing: As clause 35, two nails per tile in every course.
25 UNDERLAY
- Laying: Maintain consistent tautness.
- Vertical laps (minimum): 100 mm wide, coinciding with supports.
- Fixing: Galvanized steel, copper or aluminium 20 x 3.35 mm extra large head nails.
- Eaves: Where exposed, underlay must be BS 747, type 5U, or equivalent UV durable
type.
- Penetrations: Use proprietary underlay seals or cut underlay neatly.
30 BATTENS/COUNTERBATTENS
- Timber: Sawn softwood.
- Standard: BS 5534-1.
- Moisture content at time of covering (maximum): 22%.
- Preservative treatment: CCA or OS as section Z12 and BWPDA Commodity
Specification C8.
32 BATTEN FIXING
- Batten length (minimum): 1800 mm.
- Joints in length: Butt centrally on supports. Joints must not occur more than once in
any group of four battens on one support.
- Additional battens: Provide where unsupported laps in underlay occur between
battens.
35 TILE FIXING
- General: Fix tiling and accessories to make the whole sound and weathertight at the
earliest opportunity.
- Exposed fittings and accessories: To match tile colour and finish.
- Setting out: To true lines and regular appearance. Lay tiles to a half lap bond with
joints slightly open. Align tails.
- Cut tiles: Cut only where necessary, to give straight, clean edges.
- Ends of courses: Use tile and a half tiles to maintain bond and to ensure that cut tiles
are as large as possible.
- Top and bottom courses: Use eaves/tops tiles to maintain gauge.
- Perimeter tiles: Twice nail end tile in every course. Twice nail or clip two courses of
tiles at eaves and top edges.
- Fixings: As recommended by tile manufacturer.
47 EAVES
- Ventilation components: continuous abutment ventilation system.
- Underlay support:
- Continuous to prevent water retaining troughs.
- Gutter: Dress underlay or underlay support tray to form drip into gutter.
- Undercourse and first course tiles: Fix with tails projecting 50 mm over gutter or to
centre of gutter.
58 ARRIS HIPS
- Underlay: Lay courses over hip. Overlap (minimum) 150 mm.
- Arris hip tiles:
- Bedding: In mortar as clause 40. Course in with roof tiling.
- Fixing: Secure with nails.
59 BONNET HIPS
- Underlay: Lay courses over hip. Overlap (minimum) 150 mm.
- Bonnet hip tiles:
- Bedding: In mortar as clause 40, neatly struck back about 13 mm. Course in with
roof tiling. Fill ends of bottom hip tiles with mortar and tile slips finished flush.
- Fixing: Secure with nails.
70 SIDE ABUTMENTS
- Underlay: Turn up not less than 100 mm at abutments.
- Abutment tiles: Cut as necessary. Fix close to abutments.
- Soakers: Interleave and turn down over head of abutment tiles.
86 VENTILATOR TILES
- Ventilator tiles:
- Positions: as specified and required by design.
25 UNDERLAY
- Laying: Maintain consistent tautness.
- Vertical laps (minimum): 100 mm wide, coinciding with supports.
- Fixing: Galvanized steel, copper or aluminium felt nails.
- Eaves: Where exposed, underlay must be BS 747, type 5U, or equivalent UV durable
type.
- Penetrations: Use proprietary underlay seals or cut underlay neatly.
30 BATTENS/ COUNTERBATTENS
- Timber: Sawn softwood.
- Standard: BS 5534-1.
- Moisture content at time of covering (maximum): 22%.
- Preservative treatment: CCA or OS as section Z12 and BWPDA Commodity
Specification C8.
32 BATTEN FIXING
- Batten length (minimum): 1200 mm.
- Joints in length: Butt centrally on supports. Joints must not occur more than once in
any group of four battens on one support.
- Additional battens: Provide where unsupported laps in underlay occur between
battens.
35 TILE FIXING
- General: Fix tiling and accessories to make the whole sound and weathertight at the
earliest opportunity.
- Setting out: To true lines and regular appearance. Align tails.
- Ends of courses: Use special tiles to maintain bond and to ensure that cut tiles are as
large as possible.
- Perimeter tiles: Fix tiles in eaves and top courses, and at verges, abutments and each
side of valleys and hips.
- Fixings: As recommended by tile manufacturer.
47 EAVES
- Underlay support: as specified.
- Continuous to prevent water retaining troughs.
- Gutter: Dress underlay or underlay support tray to form drip into gutter.
- Eaves filler units for profiled tiles: Fix to close underside of first course tiles.
- First course tiles: Fix with tails projecting 50 mm over gutter or to centre of gutter.
50 DRY VERGES
- Underlay: Carry over full width of verge.
- Tiling battens: Carry over underlay and project as recommended by dry verge
Manufacturer.
55 DRY HIPS
- Underlay: Lay courses over hip. Overlaps (minimum) 150 mm.
- Roof tiles: Cut and fix closely at hip.
56 MITRED HIPS
- Underlay: Lay courses over hip. Overlap (minimum) 150 mm.
- Mitred tiles: Cut double and tile and a half tiles and fix to a neat mitre through
weathering unit supplied by tile manufacturer.
67 TROUGH VALLEYS
- Underlay: Lay strips not less than 600 mm wide centred on valleys. Overlap with
general roof underlay.
- Valley battens: Fix to raise tiling battens and lift roof tiles clear of trough tiles.
- Valley trough tiles:
- Roof tiles: Cut adjacent tiles to fit neatly.
- Bedding: On mortar as clause 40 on fibre cement undercloaks laid loose each side
of valleys. Keep trough tile interlocks and channels free of mortar.
70 SIDE ABUTMENTS
- Underlay: Turn up not less than 100 mm at abutments.
- Abutment tiles: Cut as necessary. Fix close to abutments.
76 DRY RIDGES
- Underlay: Lay courses over ridge. Overlap (minimum) 150 mm.
81 DRY MONO-RIDGES
- Underlay: Lay not less than 150 mm over mono-ridge.
86 VENTILATOR TILES
- Ventilator tiles:
- Positions: as specified and required by design.
H71 LEAD SHEET COVERINGS/FLASHINGS
10 GUTTER LININGS:
- Underlay: Waterproof building paper to BS 1521, class A.
- Lead: Code 4
- Cross Joints: in accordance with Lead Sheet Association recommendations.
- Spacing: in accordance with Lead Sheet Association recommendations.
- Outlets: to design.
20 MISCELLANEOUS WEATHERINGS
- Underlay: Waterproof building paper to BS 1521, class A.
- Lead: Code 4
- Fixing: in accordance with Lead Sheet Association recommendations
30 APRON FLASHINGS
- Lead: Code 4 in lengths not exceeding 1500 mm.
- End to end joints: Laps of not less than 100 mm.
- Upstand not less than 75 mm.
- Cover to abutment: in accordance with Lead Sheet Association recommendations
- Fixing: Lead wedges into bed joint and lead clips to bottom edge at laps and 300 mm
centres.
35 COVER FLASHINGS:
- Lead: Code 4 in lengths not exceeding 1500 mm.
- End to end joints: Laps of not less than 100 mm.
- Cover: Overlap to upstand of not less than 75 mm.
- Fixing: Lead wedges into bed joint and lead clips to bottom edge at laps and 300 mm
centres.
52 CHIMNEY FLASHINGS:
- Front apron: Lead code 4.
Length: Width of chimney plus not less than 150 mm underlap to each side flashing.
Upstand: Not less than 75 mm.
Cover to roof: in accordance with Lead Sheet Association recommendations
Fixing: Lead wedges into bed joint.
- Back gutter: Lead code 4.
Length: Width of chimney plus not less than 100 mm overlap to each side flashing.
Upstand: Not less than 100 mm.
Gutter Sole: Not less than 150 mm.
Cover up roof: Not less than 225 mm.
- Back gutter cover flashing: Lead code 4.
Length: Width of chimney plus not less than 100 mm overlap to each side flashing.
Cover: Overlap to back gutter upstand of not less than 75 mm.
Fixing: Lead wedges into bed joint.
76 UNDERLAY:
- Handle carefully to prevent tears and punctures.
- Lay on dry base in strips across fall of roof, lapped and fixed in position with copper
or stainless steel staples or clout nails.
- Do not lay over roof edges but do turn up at abutments.
- Wood core rolls, where used, must be fitted over the underlay.
- Keep underlay dry and cover with lead at the earliest opportunity.
80 CLIPS:
- Generally 50 mm wide where not specified to be continuous, length to suit detail.
- Lead: Cut from sheets of the same code as the sheet being secured, or
- Copper: Cut from 0.7 mm thick sheet to BS EN 1172, temper R220 (soft) or R240
(half hard) depending on position, dipped in solder if exposed to view, or
- Stainless steel: Cut from 0.38 mm sheet to BS EN 10088, grade 1.4301(304), terne
coated if exposed to view.
- Fix with two fastenings not more than 50 mm from edge of lead sheet. Clips welted
around edges of sheets to be turned over 25 mm.
25 ROOFING GENERALLY
- Lay roof covering to provide a secure, free draining and completely weathertight roof.
- Ancillary products and accessories, where not specified, to be types recommended for
the purpose by the asphalt manufacturer.
- Provide temporary covers and drainage as required to keep unfinished areas of the
roof dry.
- Protect edges of phased roofing with temporary asphalt kerbs, fully sealed to base.
- Protect daywork joints in warm deck roofs with a lapped and fully bonded strip of BS
747, Type 5B felt or equivalent.
55 JOINTS IN RIGID SHEET BASES: Lay at 150 mm wide strip of felt, BS 747 type
5U, centrally over joints and adhere to base with bonding compound along edges
only.
60 LAYING THE VAPOUR CONTROL LAYER: Lay sheets with fully bonded 50 mm
side and 75 mm end laps. Carry up vertically at upstands and trim level wtih first layer
of asphalt or turn back over insulation and seal down before separating membrane is
laid. Fully seal at penetrations by bonding or taping.
65 BONDING OF VAPOUR CONTROL LAYER: Lay sheets other than torch on type
on a continuous even coating of hot bonding compound by the pour and roll method.
Other methods will be permitted only where this is not practicable. Ensure that there
is a full bond over the whole surface, with no air pockets.
75 SEPARATING LAYER: Black sheathing felt to BS 747, type 4A. Loose lay with 75
mm laps immediately prior to laying asphalt.
80 APPLICATION OF ASPHALT:
- Unless specified otherwise, lay roof covering in accordance with BS 8218 to provide a
secure, free draining and completely weathertight roof.
- Remelt in mechanically agitated mixers and do not heat to more that 230 degC.
- Apply each coat to even thickness free from imperfections and crazing. Apply
successive coats without delay and within the same working period. Maintain full
thickness at angles.
- Ensure complete fusion of asphalt at all joints to give a continuous watertight
membrane. Clean and heat edges by poulticing. Discard poultices and cut away edges
before jointing. Do not use torching.
- Stagger junctions of bays in successive coats by not less than 150 mm.
- Pierce any blows and make good affected areas while asphalt is still at working
temperature.
- Form 45 deg solid fillets in two layers at all internal angles, fully fused to asphalt
coating and not less than 40 mm wide.
- Turn asphalt into splayed chase at top edge of skirtings and vertical work. Splay top
surface to shed water.
- Form watertight joints around penetrations.
- Finish asphalt to a smooth flat surface, free from lipping, pitting and other
imperfections. Rub horizontal surfaces while still warm with clean, coarse sand from
natural deposits, passing to 600 micron sieve and retained on a 210 micron sieve.
90 PAVING TILES:
Tiles: to match existing.
- Where required by tile manufacturer prime contact surfaces and allow to dry.
- Apply sufficient bitumen bonding compound to fully bed tiles but avoid excess
compound being squeezed over face of tiles.
- Lay tiles with 3 mm joints and expansion gaps at 3 m intervals. Do not foul expansion
or drainage gaps with bonding compound.
- Stop tiles 75 mm short of angle fillets at upstands.
95 CHIPPINGS:
- Pea gravel or crushed rock not less than 10 mm nominal size graded as 'Single sized
aggregate for asphalt roofing', light coloured to approval.
- Ensure that gravel guards are fitted to all outlets.
- Evenly pour a hot or cold application dressing compound to BS 3690:Part 1 at 1.5
kg/sq m and scatter chippings at approximately 16 kg/sq m.
- On completion remove loose chippings without exposing the asphalt.
J30 LIQUID APPLIED DAMP PROOF MEMBRANES
50 WORKMANSHIP GENERALLY:
- Apply all damp proofing systems in accordance with manufacturer’s instructions.
- Ensure that all holes, cracks, defective joints and other defects in surfaces to be coated
have been made good. Remove dirt, laitance, grease, rust and loose material.
- Primer, if specified, to be brushed well in, ensuring complete coverage. Allow to dry
thoroughly before applying coating.
- Apply coatings to clean, dry surfaces, to give a uniform, continuous film. Do not
allow to pool in hollows.
- Coatings must adhere firmly and be free from defects likely to permit the passage of
water.
- Prevent damage and apply final covering as soon as possible after coating has
hardened.
70 BLIND coatings as specified whilst still tacky. Brush away surplus material when
coatings are completely dry.
J40 FLEXIBLE SHEET DAMP PROOFING
15 VENTING HARDCORE BEDS: Blind with stiff weak mix concrete to BS 5328,
Designated mix GEN 1 or Standard mix ST2, 50 mm thick. Finish with a wood float
to give a smooth surface.
WORKMANSHIP
50 WORKMANSHIP GENERALLY:
- Ensure that surfaces to be covered are clean, dry, smooth and free from voids, sharp
protrusions and frost.
- Apply materials carefully to provide a completely impervious, continuous membrane.
- Where pipes, ducts, cables, etc. pass through sheeting, make junctions completely
impervious by forming collars fully bonded/sealed to both pipes and sheeting.
- Protect finished sheeting adequately to prevent puncturing.
- Immediately prior to covering with permanent overlying construction check for
damage and repair as necessary.
15 ROOFING GENERALLY:
- Lay the full roof covering in accordance with BS 8217 to provide a secure, free
draining and completely weathertight roof.
- Ancillary products and accessories, where not specified, to be types recommended for
the purpose by the felt manufacturer.
- Store felt indoors in reasonably warm conditions until immediately before use.
- Provide temporary covers and drainage as required to keep unfinished areas of the
roof dry.
- Protect daywork joints in warm deck roofs with a lapped and fully bonded strip of top
layer felt.
55 NAILING: Fix felt to timber base with galvanized extra large head felt or clout nails
to BS 1202, 20 mm long:
- at 50 mm centres to perimeter of roof area(s) and along centres of laps
- at 150 mm staggered centres over area of sheets.
60 PARTIAL BONDING: Loose lay the specified venting base layer to roof surfaces, but
do not carry up angle fillets and vertical surfaces or through details.
75 WELTED DRIPS:
- Form using maximum length strips.
- Nail tail of welt to face of drip batten, fold neatly and bond welt together. Carry not
less than 100 mm onto roof and overlap with top layer.
K10 PLASTERBOARD DRY LININGS/ PARTITIONS/ CEILINGS
70 ADDITIONAL SUPPORTS
- Framing: Accurately position and securely fix to fully support:
- Partition heads running parallel with, but offset from main structural supports.
- Fixtures, fittings and services.
- Board edges and lining perimeters.
90 SEAMLESS JOINTING
- Filling and taping: Fill joints, gaps and internal angles with jointing compound and cover with
continuous lengths of tape, fully bedded.
- Finishing: Apply jointing compound feathered out to give a flush, smooth, seamless surface.
- Nail/ screw depressions and minor indents: Fill to give a flush surface.
K20 TIMBER BOARD FLOORING/ SARKING/ LININGS/ CASINGS
50 FIXING BOARDS
- Protection during and after installation: Keep boards dry, clean and undamaged.
- Boards to be used internally: Do not install until building is weathertight.
- Moisture content of timber supports: Not more than 18% at time of fixing boards.
- Fixing: Fix boards securely to each support to give flat, true surface free from undulations,
lipping, splits and protruding fasteners.
- Timber movement: Position boards and fixings to prevent cupping. springing, excessive
opening of joints and other defects.
- Heading joints: Tightly butted, central over supports and at least two boards widths apart on
any one support.
- Edges: Plane off proud edges.
60 TREATED TIMBER
- Surfaces exposed by minor cutting and/ or drilling: Treat with two flood coats of a solution
recommended for the purpose by main treatment solution manufacturer.
L10 WINDOWS/ROOFLIGHTS/SCREENS
15 WOOD WINDOWS
- Standard: To BS 644-1 and Brutish Woodworking Federation (BWF) accredited.
- Manufacturer: A firm currently registered under a third party quality assurance
scheme.
- Timber generally: To BS EN 942.
- Wood species: European Redwood.
- Appearance class: J10 for glazing beads, drip mouldings and the like. J40 or better
for all other members.
- Moisture content on delivery: 12 – 19%.
- Preservative treatment: guaranteed for a minimum life of 30 years.
- Finish as delivered: factory painted or stained.
- Glazing details: factory glazed with hermetically sealed double glazed units to
BS6262, with low emissivity glazing. Minimum 24mm composite thickness. All
frame units to be manufactured and approved under the British Standard Kitemark
scheme and marked accordingly.
- Fixing: in accordance with manufacturer’s recommendations.
- Fastener spacing: When not predrilled or specified otherwise, position fasteners
not more than 150 mm from ends of each jamb, adjacent to each hanging point of
opening lights, and at maximum 450 mm centres.
30 COMPLIANCE STANDARDS
Contractor shall ensure that the design, manufacture and installation complies with all current and
relevant British Standards, Codes of Practice, Building Regulations and manufacturers’
current printed instructions, including, but not limited to, the following standards:
MATERIALS
70 mm wide, white, high impact PVCu multi chamber sections with a minimum of 3
mm external wall thickness.
External glazing beads (inconjunction with glazing tape) to be in white, high impact
PVCu with three point locking system.
Friction hinges to be heavy gauge stainless steel with head moulding to ensure a close
weather-tight fit. The type and size to be all in accordance with the table prepared by
LB Plastics Ltd. Top hung sashes over 500 mm deep window bays shall be from the
Defender range supplied by Security Ltd.
The casement fasteners to be Sonata locking handles, with polyester powder paint
finish and striking plates. 1 No. to be fixed centrally on casements not exceeding 600
mm long and 2 No. fixed equidistant from the centre on casements 600 mm long or
above, (both side and top hung). All keys to be the same differ.
Fastenings, fixings, screws, rivets, nuts and bolts to be of stainless steel, bright zinc
plated steel or dichromate zinc plated steel.
Existing window board and internal tiled cills are to be covered using 10 mm thick
PVCu board supplied by BCE Cellular Extrusions, Billet Lane, Lysaghts Enterprise
Park, Normanby Road, Scunthorpe, DN15 9YH.
GLAZING
All windows shall have hermetically sealed double glazed units Units to be
minimum 24mm thick (4-16-4) and comprise 4mm float glass, 16 mm air space
and 4mm clear low emissivity glass The windows as a whole to have a maximum U
value of 2.0 W/Ms
degree K.
FABRICATION
The windows are to meet the full requirements of the BSI Registered Firms Scheme
for plastic windows, reference QAS/M/4834/18 and QS/M/4834/19.
The windows shall reach the following performance specification of BS 6375 Part 1
“Performance of Windows when tested”, in accordance with BS 5368 Parts 1, 2 ad
3:
The windows are to be outward opening with top and side hung casements and to be
outward glazed.
The fabrication of all framing and opening lights is to be heat welding of the
sections using approved techniques and equipment, the corner welds being mitred,
with a grooved finish, and with profiles reinforced with aluminium sections.
Exposed drainage slots shall be cloaked with a neat white PVCu cap, permanently
glued to the face of the frame.
All screws used to attach ironmongery shall penetrate the reinforcement or at least
two separate walls of the PVCU profile. The ironmongery shall be capable of being
adjusted or replaced without removing the outer frame from the structure.
GUARANTEES
The complete windows, including the double glazing units, shall be guaranteed for a
minimum of five years against any defect.
SURVEYING
The window sizes given in the “Schedule of Rates” are approximate and the
Contractor is responsible for all measuring to obtain the exact dimensions of each
window on site and for making an allowance of 5 mm on each side, top and bottom,
for expansion, (i.e. a total of 10 mm on each dimension), all in accordance with the
“Sheerframe” installation instructions.
The vertical dimensions are to be taken to the top of any existing tiled external cill.
The use of “make up” sections to overcome shortfalls in the overall size of
manufactured windows will not be permitted.
INSTALLATION
The Contractor is to carefully take out the existing windows and remove from the site,
care is to be taken to minimise any damage to finishings and decorations.
The windows shall be fixed with plastic sheathed fixing bolts, all in accordance with
“Sheerframe” installation instructions and with flexible foam strip, SW 7091 where
recommended, and sealed all round externally with white silicone sealant, compatible
with the window.
The new windows shall, as far as is practicable, be fitted up to the existing plaster
line. Where this is not possible the Contractor shall make good to the plaster reveal
between the existing plaster and new window in plaster or, where less than 12 mm,
with a neat PVCu bead or quadrant.
MAKING GOOD
Prices for window installation shall include for all making good to any decorations,
external renderings, brickwork and claddings.
45 ROOFLIGHTS:
Type: to suit location
Glazing details: factory glazed with hermetically sealed double glazed units with low
emissivity glazing. Minimum 24mm composite thickness.
Kerb: to suit roofing type and location
Other requirements: opening device where necessary
75 SEALANT JOINTS:
- Sealant manufacturer and reference:, low modulus gun grade polyurethane based
elastomeric sealant to BS5889, Type A as recommended by window manufacturer.
Colour: clear
- Prepare joints and apply sealant as section Z22. Finish triangular fillets with a flat or
slightly convex profile.
- Back-up Rods:
Provide closed cell polyethylene foam back-up rods as required prior to applying
sealant.
65 GARAGE DOORS:
- Type: up and over door.
- Material: galvanised steel door primed for painting.
- Frame: treated softwood timber frame painted to full gloss
- Ironmongery: as specified.
80 SEALANT JOINTS:
- Sealant manufacturer and reference: as appropriate
Colour: as specified.
- Prepare joints and apply sealant as section Z22.
50 EXTERNAL BALUSTRADES
- Component material, grade and finish as delivered:
- Guarding: tubular galvanized steel
- Handrails: tubular galvanized steel
- Workmanship:
Metalwork: As section Z11.
70 HANDRAILS IN DWELLINGS
- Component material and finish as delivered:
- Handrails: softwood
- Other requirements: paint or stain finish
80 FIXING GENERALLY
- Fasteners and methods of fixing: To Section Z20.
- Structural members: Do not modify, cut, notch or make holes in structural members,
except as indicated on drawings.
- Temporary support: Do not use stairs, walkways or balustrades as temporary support
or strutting for other work.
L40 GENERAL GLAZING
10 WORKMANSHIP GENERALLY:
- Glazing generally: to BS 6262.
- The glazing must be wind/watertight under all conditions. Make full allowance for
deflections and other movements.
- Glass generally to BS 952 and the relevant part(s) of:
BS EN 572 for basic sodium lime silicate glass
BS EN 12150 for thermally toughened soda lime silicate glass
BS EN ISO 12543 for laminated glass and laminated safety glass
BS EN 1096 for coated glass
- Sagety glazing shall be used in accordance with BS6206 where required to comply
with Approved Document N of the Building Regulations.
- Glass generally to be free from scratches, bubbles and other defects.
- Panes/sheets to be accurately sized.
- Ensure that glass/plastics, surround materials, sealers primers and paints/clear finishes
are compatible. Comply with glazing/sealant manufacturers’ recommendations.
50 MIXING
- Water content: Minimum necessary to achieve full compaction.
- Mixing: Mix materials thoroughly to uniform consistence in a suitable forced action
mechanical mixer.
52 COMPACTION
- General: Compact thoroughly over entire area.
- Screeds over 50 mm thick: Lay in two layers of equal thickness. Roughen surface of
compacted lower layer then immediately lay upper layer.
90 CURING
- Curing period: As soon as screed has set sufficiently, closely cover with polyethylene
sheeting for not less than 7 days.
- Drying after curing: Allow screeds to dry gradually.
M20 PLASTERED/RENDERED/ROUGHCAST COATINGS
10 CEMENT:LIME:SAND RENDER:
- Undercoat(s) (cement:lime:sand):
Lime:sand mix: Ready-mixed to BS 4721 using sand to BS 1199, type A.
Thickness (excluding dubbing out): to design.
- Final coat (cement:lime:sand):
Lime:sand mix: Ready-mixed to BS 4721 using sand to BS 1199, type A.
Thickness: to design
- Finish: as specified
20 WATERPROOF RENDER:
- Preparation: Cut out cracks and all defective areas, then make good as manufacturer's
recommendations. Form and seal all holes for fastenings. Do not make any holes after
coatings are applied.
- Application: Thoroughly soak backgrounds. Joints in successive coats, if necessary,
must be staggered by at least 100 mm and must not occur at angles.
Patch all pinholes, breaks and thin areas before applying next coat. Do not scratch to
form a key.
- Internal angles: After first coat form fillets of waterproof coating mix. After final coat
form smooth round coves.
- Finish with a wood float without drawing excessive laitance to the surface.
61 CEMENT: All cements must comply with the appropriate British Standard and be
licensed under the BSI Kitemark scheme for cement. Where Portland cement,
Portland blastfurnace cement, Portland pulverised-fuel ash cement or Sulfate-resisting
Portland cement is specified use class 42.5 or 52.5 material.
63 MIXING:
- Measure materials accurately by volume using gauge boxes. Proportions of specified
mixes are for damp sand. Adjust proportions if sand is dry.
- Do not allow contamination of one type of material with another, or by any set
material.
- Do not use admixtures unless specified or approved.
- Mix materials thoroughly.
67 ADVERSE WEATHER
- Take precautions to prevent damage to internal work when air temperature is below
3°C.
- Do not carry out external work when air temperature is below 3°C and falling or
below 1°C and rising.
- Adequately protect newly applied external coatings against frost and rain for the first
48 hours using polyethylene sheet hung clear of the face, or other approved method.
80 PLASTERBOARD BACKINGS:
- Plasterboard: To BS 1230:Part 1.
Fixings: Galvanized plasterboard nails of length not less than 3 times the thickness of
board being fixed.
- Ensure that noggings, bearers, etc. to support fixtures, fittings and services are
accurately and securely fixed.
- Ensure that perimeter and unbound or cut edges of boards are supported by additional
noggings in accordance with board manufacturer's recommendations.
- Stagger end joints between rows. Gap between boards to be not more than 3 mm. Do
not use damaged boards.
- Fill and tape (scrim) all joints and angles between boards to walls and ceilings and to
wall/ceiling joint (except where coincident with a metal bead) using tape
recommended by board manufacturer.
87 APPLICATION GENERALLY:
- All coatings to be firmly bonded, of even and consistent appearance, free from
rippling, hollows, ridges, cracks and crazing.
- Finish surfaces to a true plane with all angles and corners to a right angle unless
specified otherwise, and with walls and reveals plumb and square.
- Prevent excessively rapid or localised drying out.
93 DRYING OF RENDER:
- Keep each undercoat and final coat damp for the first 3-4 days by covering with
polyethylene sheet and/or spraying with water.
- Allow each coat to dry out thoroughly to ensure shrinkage is complete before
applying next coat.
97 FINAL COAT OF RENDER - SCRAPED FINISH: After coating has set sufficiently,
expose aggregate by scraping surface to an even texture with a saw blade.
99 FINAL COAT OF RENDER - PLAIN FLOATED FINISH: Finish with wood float to
an even, open texture. Do not apply water while working up or draw excessive
laitance to surface (either by overworking or by use of steel trowel).
M21 INSULATION WITH RENDERED FINISH
30 GENERAL REQUIREMENTS:
- Complete the design of the system and associated features to meet the requirements of
this specification.
- The installation must be weathertight under all anticipated conditions and capable of
resisting likely impact and wind loads.
- Warranty: provide a 25 year insurance backed warranty for the installation on
completion.
- Installation to be carried out by the system manufacturer or by a contractor approved
by the system manufacturer.
- Carefully protect all existing work. Clean off any droppings from finished work
immediately.
- Form construction/movement joints where shown on drawings. If modifications are
necessary on site, agree revisions with CA before proceeding.
- Refix all removed items onto suitable grounds at completion of work
35 EXISTING OPENINGS
- Fix PVCu edging beads to all reveals to windows, doors etc. to enable windows,
doors, etc. to be removed at a later date without causing damage to render
40 ADVERSE WEATHER:
- Do not apply adhesive, mortar or render when the air temperature is at or below 5°C
on a falling thermometer
- Protect newly rendered surfaces against rain and snow by covering when precipitation
occurs.
- Replace coatings damaged by rain or frost.
50 BACKGROUNDS:
- To be structurally sound, dry, unpainted, and free from contamination by dirt, dust,
efflorescence or other deleterious substances.
- Remove efflorescence, dust and other loose material by thoroughly dry brushing.
Remove all traces of paint, dirt and other substances incompatible with adhesive by
scrubbing with water containing detergent and washing off with clean water. Allow to
dry before applying coatings.
60 PULL OUT TEST(S) ON FIXING PINS to be carried out on site to prove the
suitability of the structural background and determine the size and number of fixings
required. Notify CA to enable testing to be witnessed.
70 CURING:
- Allow primer coats and undercoats to dry out thoroughly before applying subsequent
coats.
- Take all necessary precautions to prevent newly rendered surfaces from drying out too
rapidly.
80 FIRE BARRIERS:
- Noncombustible material to BS 476:Part 4, minimum size 100 mm x total thickness of
external wall insulation.
- Install barriers in accordance with manufacturer’s recommendations
- Mechanically fix back to structural background with closely butted joints, leaving no
gaps. Incorporate any intumescent materials recommended by system manufacturer.
85 SEALANT JOINTS:
- Sealant: Type recommended by system manufacturer.
- Form in accordance with system manufacturer's recommendations using any
necessary joint fillers, backing strips, etc.
15 NEW BACKGROUNDS/BASES
- Background drying times (minimum):
- Brick/block walls: 6 weeks.
- Rendering: 2 weeks.
- Gypsum plaster: 4 weeks.
- Base drying times (minimum):
- Concrete slabs: 6 weeks.
- Cement:sand screeds: 3 weeks.
25 NEW PLASTER
- Plaster primer: Apply if recommended by adhesive manufacturer.
30 FIXING GENERALLY
- Colour/shade: Avoid unintended variations within tiles for use in each area/room.
- Adhesive: Compatible with background/base.
- Cut tiles: Neat and accurate.
- Fixing: Provide adhesion over entire background/base and tile backs.
- Final appearance: Before bedding material sets, make adjustments necessary to give
true, regular appearance to tiles and joints.
- Deviation of surface: Variations in gap under a 2 m straightedge (with feet) placed
anywhere on the surface to be not more than 3 mm.
- Surplus bedding material: Clean from joints and face of tiles.
35 SETTING OUT
- Joints: True to line, continuous and without steps.
- Joints on walls: Horizontal, vertical and aligned round corners.
- Joints in floors: Parallel to main axis of space or specified features.
- Cut tiles: Minimise number, maximise size and locate unobtrusively.
- Joints in adjoining floors and walls: Align.
- Joints in adjoining floors and skirtings: Align.
70 GROUTING
- Sequence: Grout when bed/adhesive has set sufficient to prevent disturbance of tiles.
- Joints: 6 mm deep (or depth of tile if less). Free from dust and debris.
- Grouting: Fill joints completely, tool to profile, clean off surface. Leave free from
blemishes.
- Polishing: When grout is hard, polish tiling with dry cloth.
40 DAMPNESS: Where coverings are to be laid on new wet-laid bases, ensure that
drying aids have been turned off for not less than 4 days, then test for moisture
content in accordance with BS 8203, Annexe A. Do not lay coverings until all
readings show 75% relative humidity or less.
50 HARDBOARD UNDERLAY:
- To BS EN 622:Part 2.
Sheet size: 1200 x 1200 mm.
- Ensure that existing floor boards are securely fixed and acceptably level. Remove or
fill any gross irregularities. Punch in any protruding fastenings.
- Condition sheets by sponging the mesh side with approximately 0.5 litre of water per
1200 x 1200 mm sheet, then stack spaced horizontally for 24-48 hours before fixing.
- Lay sheets butt jointed with smooth side uppermost, cross joints staggered such that
no joint within the base and underlay is coincident.
- Fix with 25 mm ring shanked or twisted shank nails or divergent staples, commencing
at the centre of one side of each sheet, at 150 mm grid centres over the area and 100
mm centres along perimeter, set in 12 mm from edge.
- Ensure that fasteners do not project above sheet surface or through underside of base.
- Do not lay coverings until conditioned hardboard is dry.
55 PLYWOOD UNDERLAY:
- To an approved national standard.
Bonding quality to BS EN 314:Part 2:Class 3
Appearance class to BS EN 635
Finish: sanded
Sheet size: 1200 x 1200 mm.
- Ensure that existing floorboards are securely fixed and acceptably level. Remove or
fill any gross irregularities. Punch in any protruding fastenings.
- Lay sheets with cross joints staggered such that no joint within the base and underlay
is coincident and with a 0.5-1 mm gap between sheets.
- Fix with 25 mm annular ring shanked or twisted shank nails or divergent staples,
commencing at the centre of one side of each sheet, at 150 mm grid centres over the
area and 100 mm centres along perimeter, set in 12 mm from edge.
- Ensure that fastenings are driven well in, with heads set flush with surface and do not
project through underside of base.
60 SET OUT TILES from centre of space/room unless specified otherwise, so that
wherever possible:
- Tiles along opposite edges are of equal size, and
- Edge tiles are more than 50% of full tile width.
65 LAYING COVERINGS:
- Bases must be rigid, dry, smooth and free from grease, dirt and other contaminants
before coverings are applied.
- Use a primer where recommended by adhesive manufacturer. Allow to dry thoroughly
.
- Adhesive, when not specified otherwise, to be as recommended by covering
manufacturer or, in the absence of such recommendation, to be approved.
- Before laying commences thoroughly condition materials as recommended by
manufacturer.
- Before, during and after laying, provide adequate ventilation and maintain
temperature and humidity approximately at levels which will prevail after the building
is occupied.
- Finished coverings must be accurately fitted, tightly jointed, securely bonded, smooth
and free from air bubbles, rippling, adhesive marks, stains, trowel ridges and high
spots.
70 EDGINGS/COVER STRIPS:
- Manufacturer and reference(s): as recommended by floor covering manufacturer.
- Fix securely (using matching fastenings where exposed to view) ensuring that edge of
covering is firmly gripped.
85 WASTE: Retain spare covering material suitable for patching. On completion hand
over to Employer pieces selected by CA.
M60 PAINTING/CLEAR FINISHING
14 Intumescent Varnish.
- Surfaces: Timber surfaces in internal communal areas.
- Preparation: rub down with fine grade sandpaper before applying stain rub down
between coats
- Initial coats: as recommended by manufacturer.
- Finishing coats: as recommended by manufacturer.
20 COATING MATERIALS
- Selected manufacturer: Submit name before commencement of any coating work.
30 PREPARATION GENERALLY
- To BS 6150, Section 4.
- Preparation materials: Types recommended by their manufacturers and the coating
manufacturer for the situation and surfaces being prepared.
- Substrates: Sufficiently dry in depth to suit coating.
- Efflorescence salts, dirt, grease and oil: Remove.
- Organic growths and infected coatings: Remove with assistance of biocidal solution.
Apply residual effect biocidal solution to inhibit regrowth.
- Joints, cracks, holes and other depressions: Fill with stoppers/fillers. Abrade to a
smooth finish.
- Surface irregularities: Abrade to a smooth finish.
- Dust, particles and residues from abrasion: Remove.
- Doors, opening windows and other moving parts: Ease before coating. Prime resulting
bare areas.
37 TIMBER PREPARATION
- General: Abrade to a smooth, even finish with lightly rounded arrises.
- Degraded or weathered surface timber: Abrade to remove.
- Degraded substrate timber: Repair with sound timber of same species.
- Heads of fasteners: Countersink sufficient to hold stoppers/fillers.
- Resinous areas and knots: Apply two coats of knotting.
- Defective primer: Abrade back to bare timber.
- Rub down with fine grade sandpaper before applying gloss/stain rub down between
coats
39 STEEL PREPARATION
- Corrosion and loose scale: Abrade back to bare metal.
- Residual rust: Treat with a proprietary removal solution.
- Primer: Apply as soon as possible.
41 MASONRY/RENDERING PREPARATION
- Loose and flaking material: Remove.
43 PLASTER PREPARATION
- Nibs, trowel marks and plaster splashes: Scrape off.
- Overtrowelled ‘polished’ areas: Abrade lightly.
55 EXISTING GUTTERS
- Dirt and debris: Clean from inside of gutters.
- Defective joints: Clean and seal with suitable jointing material.
61 COATING GENERALLY
- Application: To BS 6150, Section 5.
- Conditions: Maintain suitable temperature, humidity and air quality.
- Surfaces: Clean and dry at time of application.
- Thinning and intermixing: Not permitted unless recommended by manufacturer.
- Priming coats: Apply as soon as possible on same day as preparation is completed.
- Finish: Even, smooth and of uniform colour. Free from brush marks, sags, runs and
other defects. Cut in neatly.
68 STAINING TIMBER
- Primer: Apply if recommended by stain manufacturer.
- Stain: Apply in flowing coats. Brush out excess stain before set. Produce uniform
depth of colour.
70 EXTERNAL DOORS
- Bottom edges: paint to full gloss or stain before hanging doors.
- New external doors and new ply panels to bottom of door to be painted to white gloss
internally.
80 PUTTY GLAZING
- Setting: Allow putty to set for seven days.
- Sealing: Within a further 14 days, seal with an oil based primer. Fully protect putty
with coating system as soon as it is sufficiently hard. Extend finishing coats on to
glass up to sight line.
N10 FIXTURES/FURNISHINGS/EQUIPMENT
20 KITCHEN UNITS:
- To BS 6222 and BS EN 1153.
Structural performance grade: H
Surface finishes performance to BS 6222:Part 3.
Doors/drawer finish/colour: melamine faced moisture resistant particle board. Colour
and finish choice from specified range.
Side panel/plinth/shelves finish/colour: white melamine faced moisture resistant
particle board
Worktop classification to BS 6222:Part 3 Type: 2
Worktop finish/pattern/colour: post formed plastics laminate board, colour from
specified range.
- Fixing: in accordance with manufacturer’s instructions.
25 KITCHEN SINK:
- Type: stainless steel inset 1½ bowl with draining board.
- Taps: ½” chrome plated deck sink mixer with twin flow cast swivel spout and chrome
plated metal handles.
- Waste: 40 mm chrome plated brass plug waste to BS 3380 with black plastic plug and
chrome plated chain and stay.
- Trap: 40 mm plastics trap
30 WASH BASIN:
- Type: vitreous china basin
- Taps: ½” hot and cold washbasin pillar taps with chrome plated handles.
- Waste: 40 mm chrome plated brass plug waste to BS 3380 with black plastic plug and
chrome plated chain and stay.
- Trap: 40 mm plastics trap
35 BATH:
- Type: 1700 x 700 mm enamelled steel bath with slip resistant base to BS 1390.
Colour: white
- Taps: For balanced supplies: ¾” deck mounted bath and shower mixer with flexible
hose, handspray and cradle bracket, chrome plated handles. Where no balanced
supply is available: ½” hot and cold bath pillar taps with chrome plated handles.
- Waste: 40 mm chrome plated brass plug waste to BS 3380 with black plastic plug and
chrome plated chain and stay.
- Trap: 40 mm plastics trap
- Other accessories: chrome plated grab handles, and WBP plywood side/end panels
with mouldings as required.
70 INSTALLATION GENERALLY:
- Fix appliances securely to structure, without taking support from pipelines, level and
plumb and so that surfaces designed to fall drain as intended.
- Unless specified otherwise, use jointing and bedding compounds recommended by the
manufacturers of appliances, accessories and pipes to form watertight joints between
appliances and backgrounds (except cisterns) and between appliances and discharge
pipes.
75 CISTERNS:
- Obtain cistern operating components from cistern manufacturer. Ensure that ballvalve
matches pressure of water supply.
- Ensure that overflow pipe is fixed to falls, and located to give visible warning of
discharge. Agree position with CA.
80 SEALANT POINTING:
- Sealant: low modulus silicone based to BS 5889, Type B with fungicide.
Colour: white.
- Application: As section Z22.
10 LOFT INSULATION:
- Insulating material: To BS 5803.
Type: flexible non-combustible mineral fibre rolls laid between and across joists.
Depth: 250mm minimum
- Installation: To BS 5803-5, a copy of which must be kept on site.
65 BREATHER MEMBRANE:
- Set out with continuity to form a barrier to prevent water, snow and wind blown dust
reaching the substrate.
- Lap joints not less than 100 mm horizontally and 150 mm vertically.
- Fix with galvanized, sherardized or stainless steel large head nails or stainless steel
staples.
- Seal at penetrations.
- Lap bottom edges over flashings, sills, etc. to allow free drainage to the exterior.
80 FIRE STOPPING: Ensure that any imperfections of fit between building elements
which are required to have fire resistance and/or resist the passage of smoke, are
completely sealed. Where not specified otherwise, tightly pack gaps with mineral
wool.
P11 FOAMED/FIBRE/BEAD CAVITY WALL INSULATION
20 REMEDIAL WORK: Include in the tender for remedial work shown to be necessary
by the survey.
50 CAVITY FILL:
- Granulated blown mineral fibre full fill cavity wall insulation of a type currently
certified by the British Board of Agrément (BBA) as suitable for the purpose and
exposure situation.
- Installed by an approved firm in accordance with the BBA Surveillance Scheme.
70 GAPS/OPENINGS:
- Seal openings into cavity where necessary to prevent loss of fill, using mineral wool
packed tightly.
- Remove air bricks/grilles of untrunked vents. Seal openings into cavity with mineral
wool or insert an approved sleeve to keep opening permanently clear.
80 MAKING GOOD: Remove any blockages from vents and refix or replace any air
bricks. Fill injection holes, replacing existing materials where possible to ensure a
close match of colour and texture with existing surface. Obtain approval of finished
appearance of first few holes before completing the remainder.
85 FLUES WITH NO APPLIANCE: Check for and remove any blockages. Carry out a
smoke test if a full inspection cannot be made. Inform CA before inspecting and
testing.
10 SOFTWOOD SKIRTINGS
- Quality of timber and fixing: To BS 1186-3.
- Moisture content at time of fixing: 9 to 13 %.
- Profile: Bull nosed
- Finished size: 100mm minimum x 25 mm or to match existing.
- Finish as delivered: wrot.
10 SOFTWOOD ARCHITRAVES
- Quality of timber and fixing: To BS 1186-3.
- Moisture content at time of fixing: 9 to 13 %.
- Profile: Bull nosed
- Finished size: 75mm minimum x 25 mm or to match existing.
- Finish as delivered: wrot.
50 INSTALLATION GENERALLY:
- Joinery workmanship: As section Z10.
- Methods of fixing and fastenings: As section Z20.
- Straight runs: Form in single lengths wherever possible.
- Running joints: Location and method of forming to be agreed where not detailed.
- Joints at angles: Mitre unless shown otherwise.
- Moisture content of timber and wood based boards: Maintain within the range
specified for the component during storage and installation.
P30 TRENCHES/PIPEWAYS/PITS FOR BURIED ENGINEERING SERVICES
20 TRENCHES
- Width: As small as practicable.
- Trench sides: Vertical.
- Trench bottoms: Remove mud, rock projections, boulders and hard spots. Trim level.
- Give notice: To inspect trench for each section of the work.
30 PIPEDUCTS
- Types and sizes: As recommended by the service undertaker.
- General: Lay pipes straight to line, true to gradient or level on an even, continuous
bed.
- Bedding thickness: 100 mm minimum
- Clearance between pipe ducts where they cross (minimum): 50 mm.
- Drawlines: During laying, thread through pipeducts.
- Material, strength and length: As specified by service undertaker.
- Protection: Protect from ingress of debris. During construction, temporarily seal all
exposed ends.
- Inspection: Before backfilling, allow service undertakers to inspect installation.
- Surround material: Lay and compact to a level not less than 150 mm above pipeduct
crown.
50 BACKFILLING
- Backfill from top of pipeduct surround: Material excavated from the trench.
- Backfilling: Lay and compact in 300 mm maximum layers. Do not use heavy
compactors before backfill is 600 mm deep.
P31 HOLES/CHASES/COVERS/SUPPORTS FOR SERVICES
30 PIPE SLEEVES
- Sleeves: Extend through full thickness of wall or floor. Position accurately.
- Clearance around service (maximum): 20 mm or diameter of service, whichever is
the lesser.
- Installation: Bed solid.
40 LAYING GENERALLY
- Cutting: Neatly, and accurately and without spalling. Form neat junctions.
- Bedding units on foundation: Allow mortar bedding to set and secure with a
continuous haunching of concrete.
- Concrete for foundations and haunching: To BS 5328, Designated mix GEN0 or
Standard mix ST1 or better, low workability.
- Mortar bedding: 1:3 cement:sand as section Z21.
- Bed thickness: 10-40 mm.
45 ACCURACY
- Deviations (maximum):
- Level: ± 6 mm.
- Horizontal and vertical alignment: 3 mm in 3 m.
10 THICKNESSES OF SUB-BASES
- Thicknesses: As specified in the relevant paving section.
30 COMPACTION OF SUBGRADE
- Final excavation to formation level: Carry out immediately before compaction of
subgrade.
- Soft spots: Give notice.
- Wet conditions: Do not excavate or compact when the subgrade may be damaged or
destabilised.
- Thorough compaction:
- Use a mechanical rammer where use of a roller is not practical.
- Provide additional compaction where local excavation and backfilling has taken
place.
- Immediately before placing sub-base thoroughly compact subgrade with a roller
weighing not less than 2.5 tonnes or equivalent other plant.
- Apply weedkiller to ground before laying sub-stone
40 SUB-BASE
- Granular material: Free from ice, harmful matter and excessive dust or clay, well
graded, all pieces less than 75 mm in any direction, and selected from one of the
following:
- Crushed rock (other than argillaceous rock) or quarry waste.
- Crushed concrete, crushed brick or tile, free from plaster, timber and metal.
- Gravel or hoggin.
- Crushed nonexpansive slag.
- Well burned nonplastic colliery shale.
- Natural sand or gravel.
50 ACCURACY
- Permissible deviation (maximum) from required levels, falls and cambers:
Subgrade ± 20 mm
Sub-base ± 12 mm
60 BLINDING
- Locations: Surfaces to receive sand bedded interlocking brick or block paving to
section Q24 and Q25.
- Material: Sand, fine gravel, PFA or other approved.
- Finish: Vibrated to provide a close, smooth surface.
70 PROTECTION:
- Sub-bases: As soon as practicable, cover with subsequent layers, specified elsewhere.
- Subgrades and sub-bases: Prevent damage from construction traffic, construction
operations and inclement weather.
Q22 COATED MACADAM PAVINGS
30 LAYING GENERALLY
- Preparation: Remove all loose material, rubbish and standing water.
- Adjacent work: Form neat junctions. Do not damage.
- Channels, kerbs, inspection covers etc: Keep clean.
- Permissible deviation from the required levels, falls and cambers (maximum):
- Finished surface: ±6 mm.
- Adjacent to gullies and manholes: +6 – 0 mm.
- New paving:
- Keep traffic free until it has cooled to prevailing atmospheric temperature.
- Do not allow rollers to stand at any time.
- Prevent damage.
- Lines and levels: With regular falls to prevent ponding.
- Overall texture: Smooth, even and free from dragging, tearing or segregation.
- State on completion: Clean.
Q28 TOPSOILING
20 IMPORTED TOPSOIL
- Quantity: Provide as necessary to make up any deficiency existing on site and to
complete the work.
- Grade: General purpose to BS 3882.
- Grading: Reasonably free of stones and with maximum size of 50 mm in any
dimension.
- Purity: Free of weed seeds, roots of perennial weeds, sticks, subsoil and foreign
matter.
30 SPREADING TOPSOIL
- Temporary roads or surfacing: Remove before spreading topsoil.
- Spreading: Spread when reasonably dry, maintaining crumb structure. Do not
compact.
- Layers:
- Depth (maximum): 150 mm.
- Gently firm each layer before spreading the next.
80 TIMBER RAILS: Each rail must span not less than two bays with joints in adjacent
rails staggered. Nail each length of rail to each post with two 100 mm galvanized wire
nails. Rails with split ends must be replaced.
15 ALUMINIUM GUTTERS:
- Gutters and fittings: To BS 2997.
Profile: 100mm minimum diamter ogee section.
Type/Grade: seamless aluminium
Colour: black or brown.
- Fixing: in accordance with manufacturer’s recommendations
20 PLASTICS PIPEWORK
- Pipes, fittings and accessories: PVC-U.
- Sections/ Nominal sizes: half round, 65mm minimum diameter.
- Colour: black or brown.
- Fixing: in accordance with manufacturer’s recommendations
40 RAINWATER OUTLETS:
Outlet: Type and direction to suit pipework with adaptors and connections
recommended for the purpose by outlet manufacturer.
50 INSTALLATION GENERALLY:
- Install to ensure the complete discharge of rainwater from the building without
leaking.
- Obtain all components for each type of pipework/guttering from the same
manufacturer unless specified otherwise.
- Provide access fittings and rodding eyes as necessary in convenient locations to
permit adequate cleaning and testing of pipework.
- Provide for thermal and building movement when fixing and jointing, and ensure that
clearances are not reduced as fixing proceeds.
- Where not specified otherwise use plated, sherardized, galvanized or nonferrous
fastenings, suitable for the purpose and background, and compatible with the material
being fixed or fixed to.
60 GUTTERS:
- Set out to a true line to ensure no ponding or backfall. Position high points of gutters
as close as practical to the roof and low points not more than 50 mm below the roof.
- Overlap joints in direction of fall and seal as specified to make watertight.
- Ensure that roofing underlay is dressed into gutter.
70 PIPEWORK:
- Fix securely at specified centres plumb and/or true to line with additional supports as
necessary to support pipe collars, particularly at changes in direction.
- Make changes in direction of pipe runs only where shown on drawings unless
otherwise approved.
- Cut ends of pipes to be clean and square with burrs and swarf removed.
50 INSTALLATION GENERALLY
- Standard:
- BS EN 2056-1, clauses 3-6.
- BS EN 2056-2, clauses 3-6, National Annex NA-NG, System III.
- BS EN 2056-5, clauses 4-6, 8, 9 and 11.
- Drainage from appliances: Quick, quiet and complete, without blockage, crossflow,
backfall, leakage, odours, noise nuisance or risk to health.
- Components: From same manufacturer for each type of pipework.
- Access: Provide access fittings in convenient locations to permit cleaning and testing
of pipework.
- Thermal and building movement: Provide and maintain clearance as fixing and
jointing proceeds.
- Fixings: To allow the pipe to slide.
- Finish: Plated, sherardized, galvanized or other nonferrous.
- Compatibility: Suitable for the purpose, material being fixed and background.
60 PIPEWORK
- Fixing: Securely at specified centres plumb and/or true to line. Fix every length of
discharge stack pipe at or close below socket collar or coupling.
- Additional supports: Provide as necessary at junctions and changes in direction.
- Cut ends of pipes: Clean and square with burrs and swarf removed.
70 PIPEWORK TEST
- Preparation: Temporarily seal open ends of pipework with plugs.
- Testing: Connect a ‘U’ tube water gauge and pump air into pipework until gauge
registers 38 mm.
- Required performance: Allow a period for temperature stabilisation, after which the
pressure of 38 mm is to be maintained without loss for not less than three minutes.
R12 DRAINAGE BELOW GROUND
02 EXISTING DRAINS: Before starting work, check levels and positions of existing
drains, inspection chambers and manholes against drawings and report any
discrepancies.
14 PLASTICS PIPELINES
- Pipes, bends and junctions: PVC-U to BS EN 1401-1, class SN4, Kitemark certified.
- Bedding class: as required by location.
- Warning marker tape: as required by location.
21 BEDDING/JOINTING GENERALLY:
- Lay pipes to true line and regular gradient on an even bed for the full length of the
barrel with sockets (if any) facing up the gradient.
- Joint using recommended lubricants, leaving recommended gaps at ends of spigots to
allow for movement.
- Comply with local authority requirements in respect of arrangement, flexible jointing,
bedding and surround of pipes at junctions with manholes, foundation walls and other
points where differential settlement may occur.
58 INSTALLATION OF FITTINGS:
- Set fittings square with and tightly jointed to adjacent construction as appropriate.
- Bed and surround fittings, traps, etc. in concrete, 150 mm thick, mix as clause 04.
- Permissible deviation in level of gullies to be +0 to -10mm.
84 TESTING/INSPECTION GENERALLY:
- Check that all sections of installation are free from obstruction and debris before
testing.
- Provide water, assistance and apparatus as required.
- All lengths of drain, manholes and inspection chambers must pass the tests specified.
If permitted test loss or infiltration is exceeded, remedy defect(s) before retesting after
an appropriate period.
97 CLEANING: Flush out the whole installation and remove all silt and debris
immediately before handing over.
06 INSTALLATION GENERALLY:
- Complete the design and install the systems to comply with BS 6700 and be free from
leaks and water hammer.
- All installation work to be carried out by qualified operatives.
- Electrical work in connection with the installation must be in accordance with BS
7671 (The IEE Wiring Regulations).
- Comply with restrictions on the cutting of holes, chases, notches, etc. specified in
section P31.
- In locations where moisture is present or may occur, use corrosion resistant
fittings/fixings and avoid contact between dissimilar metals by use of suitable
washers, etc.
- All equipment, pipework, components, valves, etc. to be fully accessible for
maintenance, repair or replacement.
- Installation to be fitted with vents at high points and draining taps at low points to
facilitate purging and draining.
36 CISTERN(S):
- Moulded plastics to BS 4213, Kitemark certified, and complying with the additional
requirements of BS 7181 unless specified otherwise. Size: 250 litres.
- Valve: Float operated diaphragm type to BS 1212 with plastics float to BS 2456, size
to suit water pressure.
- Outlet pipe to be at least 30 mm above bottom of cistern.
40 VALVES:
- Types approved for the purpose by the local water undertaker and of the appropriate
pressure/temperature ratings. Kitemark certified.
- Provide in convenient locations for isolation and regulation of all equipment and
subcircuits.
- Fit with handwheels where appropriate for isolation by the building user.
50 COPPER PIPELINES:
- Tube: To BS EN 1057, Kitemark certified.
- Joint fittings: To BS EN 1254, Kitemark certified. Capillary fittings to be lead-free.
- Supports: plastic with pipe clip.
- Do not use formed bends on exposed pipework except for small offsets. Form changes
of direction with radius fittings.
- Use purpose designed adaptors for connecting dissimilar materials: do not improvise.
- Protect background and plastics pipes and fittings from heat damage when forming
soldered joints. Clean off all flux residue. Do not use ‘self-cleaning’ fluxes.
55 WATER PIPELINE SIZES: Calculate sizes to suit the probable simultaneous demand
for the building and to ensure:
- A water velocity of not more than 1.3 m/s for hot water and 2.0 m/s for cold water.
- Suitable discharge rates at draw off points.
- A filling time for the cold water storage cistern of not more than one hour.
60 FIXING PIPELINES:
- Runs to be straight and parallel or perpendicular to walls, floors, ceilings, etc. as
appropriate. Obtain approval of routes before commencing work.
- Where reasonably possible conceal pipe runs within floor, ceiling or roof voids.
- Run hot pipes above cold where routed together horizontally. Do not run pipes
through electrical enclosures or above switch gear, distribution boards or the like.
- Fix at adequate centres with minimum of bends and offsets.
- Allow for thermal movement and isolate from structure where necessary to prevent
noise or abrasion caused by movement. Pipes passing through walls to be sleeved as
specified in section P31.
- Prevent ingress of dirt during installation.
- Completed pipelines to be of consistent bore, clean and free from external scratching,
toolmarks, distortion, cracks and other defects.
66 INSULATION TO PIPELINES:
- Fit to all hot and cold water pipelines, including those which are concealed from view,
but not to short lengths in prominent positions adjacent to appliances.
- Material: Preformed flexible closed cell or mineral fibre preformed split tube with
thermal performance to BS 5422.
- Fit insulation after completion of testing, ensuring continuity over fittings and at
supports, leaving no gaps and with the split on ‘blind’ side of pipeline.
75 WARNING PIPE:
- Material: PVC-U to BS 5255, solvent welded joints. Outside diameter to be greater
than that of inlet pipe but not less than 22 mm.
- Difference between normal water level and overflow level to be not less than bore of
warning pipe.
- Fall to be not less than 1 in 10 with supports to prevent sagging, with turned down
end, discharging in approved prominent position.
- Turn down end within the cistern, terminating 50 mm below normal water level.
- Fit with insulation where the pipe is in an uninsulated space.
80 VENT PIPE to be not less than 20 mm diameter with no restrictions or valves and to
discharge over cistern.
85 DISCHARGE PIPE from unvented hot water storage system to be sized to suit the
outlet on the safety device, laid to a fall not less than 1 in 80 and to discharge via an
air break and tundish to drain.
02 THE INSTALLATION:
- Heat source: gas fired boiler
- Heat emitters: steel panel round top radiators
- Circulation: pumped
- Other requirements: 7-day time clock, hot water storage, thermostatic controls.
10 SYSTEM CAPACITY:
- Output of heating surface area in any space to be near to, but not less than, the design
heat loss for that space, making appropriate additional allowances for anticipated
pattern of use, thermal capacity of the construction and any special exposure
conditions.
- Boiler output to be not less than the total calculated heat loss, including emission from
the system pipelines.
- Boiler output must, at the same time, be capable of meeting the hot water supply
requirements specified in section S12.
12 SYSTEM CONTROL:
- Provide fully automatic and independent temperature and time control of the system.
Ensure that all controls are compatible with each other and with the central heating
boiler. Controls are to include:
3-port control valve
Room thermostat
Cylinder thermostat
7-day digital timeclock with 2 on/offs per day
Control junction box
- Gravity circulation must not occur in the heating circuit. Design the system
accordingly or fit an antigravity valve.
- Bypass and pump overrun to be fitted if recommended by the boiler manufacturer.
16 INSTALLATION GENERALLY:
- Complete the design, install and balance the system so that it complies with the water
supply byelaws/regulations, and is safe, efficient, free from leaks, excessive noise and
vibration.
- All installation work to be carried out by qualified operatives.
- Electrical work in connection with the installation must be in accordance with BS
7671 (The IEE Wiring Regulations).
- Comply with restrictions on the cutting of holes, chases, notches, etc. specified in
section P31.
- In locations where moisture is present or may occur, use corrosion resistant
fittings/fixings and avoid contact between dissimilar metals by use of suitable
washers, etc.
- All equipment, pipework, components, valves, etc. to be fully accessible for
maintenance, repair or replacement.
- Installation to be fitted with vents at high points and draining taps at low points to
facilitate purging and draining.
- Each time system is refilled provide a liquid corrosion inhibitor (percentage to
manufacturers design/recommendations). Provide a certificate confirming the
percentage corrosion inhibitor, with date. Apply a self adhesive label repeating this
information to the casing of the boiler, fixed in a prominent location.
28 GAS FIRE:
To BS 5258 and BS 6332-2, installed to BS 5871.
30 EXISTING CHIMNEY: Thoroughly clean. Carry out a smoke test. If any obstructions
or leaks are revealed, submit proposals for making good and obtain approval.
32 FLUE LINER:
- Flexible, spirally wound, austenitic stainless steel tube, size to suit boiler, with all
necessary fittings.
- Ensure that flue is unobstructed and clean. Install liner in one piece, fixing securely at
top of stack and to boiler with clamps supplied for the purpose by liner manufacturer.
- Seal joint at boiler with recommended jointing material, to give a gas tight
installation.
34 FLUE PIPE:
- Size to suit appliance, with all fittings necessary to provide a complete installation.
Finish/Colour: white
- Install with sockets uppermost, fully supported and with joints filled with approved
jointing material to give a gas tight installation. Keep bends to a minimum and slopes
at not more than 30° from vertical. Do not locate joints within the depth of floors.
- Ensure that flue pipe is not less than the required minimum distance from combustible
materials and can adequately accommodate thermal movement.
- Roof terminal: ridge terminal, wherever possible. Other locations only with express
permission.
52 CIRCULATING PUMP(S):
- To BS 1394-2 or BS EN 1151 and BS EN 60335-2-51. Kitemark certified.
- Adjustable to give the required temperature differential between flow and return and
with a facility for venting.
56 RADIATORS:
To BS EN 442.
Material: steel round top
Finish: white enamel.
64 VALVES GENERALLY:
- Types approved for the purpose by the local water supply undertaker and of the
appropriate pressure/temperature ratings. Kitemark certified.
- Provide in convenient locations for isolation and regulation of all equipment, heat
emitters and subcircuits.
- Fit with handwheels where appropriate for isolation by the building user.
72 COPPER PIPELINES:
- Tube: To BS EN 1057, Kitemark certified.
- Joint fittings: To BS EN 1254, Kitemark certified. Capillary fittings to be lead-free.
- Supports: plastic two piece with pipe clip.
- Do not use formed bends on exposed pipework except for small offsets. Form changes
of direction with radius fittings.
- Use purpose designed adaptors for connecting dissimilar materials: do not improvise.
- Protect background and plastics pipes and fittings from heat damage when forming
soldered joints. Clean off all flux residue. Do not use 'self cleaning' fluxes.
76 FIXING PIPELINES:
- Runs to be straight and parallel or perpendicular to walls, floors, ceilings, etc. as
appropriate. Obtain approval of routes before commencing work.
- Where reasonably possible, conceal pipe runs within floor, ceiling or roof voids.
- Run hot pipes above cold where routed together horizontally.
- Do not run pipes through electrical enclosures or above switch gear, distribution
boards or the like.
- Fix at adequate centres with minimum of bends and offsets.
- Allow for thermal movement and isolate from structure where necessary to prevent
noise or abrasion caused by movement. Pipes passing through walls to be sleeved as
specified in section P31.
- Prevent ingress of dirt during installation.
- Completed pipelines to be of consistent bore, clean and free from external scratching,
toolmarks, distortion, cracks and other defects.
81 INSULATION TO PIPELINES:
- Fit to all pipelines, but not to short lengths in prominent positions adjacent to emitters.
- Material: Preformed flexible closed cell or mineral fibre preformed split tube with
thermal performance to BS 5422.
- Fit insulation after completion of testing, ensuring continuity over fittings and at
supports, leaving no gaps and with the split on the 'blind' side of the pipeline.
84 WARNING PIPE:
- Material: PVC-U to BS 5255, solvent welded joints. Outside diameter to be greater
than that of inlet pipe but not less than 22 mm.
- Difference between normal water level and overflow level to be not less than bore of
warning pipe.
- Fall to be not less than 1 in 10 with supports to prevent sagging, with turned down
end, discharging in an approved prominent position.
- Turn down end within the cistern, terminating 50 mm below normal water level.
- Fit with insulation where the pipe is in an uninsulated space.
86 VENT PIPE to be not less than 20 mm diameter with no restrictions or valves and to
discharge over feed and expansion cistern.
05 VENTILATION GENERALLY:
- All units to be BEAB approved and Kitemark certified.
- Comply with BS 3535 for water ingress protection for all units located in wet areas
(i.e. bathrooms and kitchens).
30 RIGID DUCTING:
- Type/size(s): PVCu 200mm x 60mm.
Complete with all necessary fixings, jointing, bends, junctions, reducers, connectors,
adaptors, etc.
32 FLEXIBLE DUCTING:
- Type/size(s): 50mm or 100mm PVC coated glass fibre fabric on PVC coated steel
wire helix.
Complete with all necessary jointing, junctions, reducers, connectors, adaptors, etc.
36 SUPPLY/EXTRACT AIR TERMINAL:
- Type/Size: PVCu to match fan/duct
- Colour/Finish: plastic to match brickwork externally, white internally.
38 EXTERNAL GRILLE:
- Type/Size: PVCu to match fan/duct
- Colour/Finish: plastic to match brickwork.
60 DUCTWORK GENERALLY:
- Seal joints to provide a robust airtight installation.
- Support ductwork correctly without distortion or reduction in cross-sectional area and
without strain on joints.
- Fully extend flexible ductwork, without overstretching, and support to form smooth
curvature without kinking, sagging or slumping.
- Install ductwork with a fall away from fans, dampers and other accessories wherever
possible.
64 COMPLETION:
- Thoroughly examine ductwork for obvious leakage, and make good if necessary.
- Test for correct operation of all fans, equipment, controls and sensors, and make good
if necessary.
- At Practical Completion hand over to the CA all necessary instructions, tools, keys,
etc.
V90 GENERAL LIGHTING AND POWER
05 THE INSTALLATION
- Special systems: night storage heaters.
10 INSTALLATION GENERALLY
- Electricity supply company: Confirm or determine suitability of supply and earthing
arrangement, and connection when required.
- Standard: Install, test and commission the electrical work in accordance with BS 7671
(The IEE Wiring Regulations) and requirements of the electricity supply company to
provide a safe, well insulated, earth protected system capable of supplying the
anticipated maximum demand.
- Accessories, fasteners, connectors, etc: Types recommended for the purpose by
electrical equipment manufacturer.
- Fasteners: Avoid contact between dissimilar metals. Use corrosion resistant fasteners
in locations where moisture may occur.
27 CABLES IN PLASTER
- Protection: Cover with galvanized steel or plastic channel nailed to substrate.
30 MICC CABLES
- Bending: Do not corrugate sheath.
- Connection to equipment and boxes: PVC shrouded glands.
- Testing: Test each length immediately after fixing. Repeat test between 24 and 48
hours later.
51 ELECTRICAL ACCESSORIES
- Manufacturer:
- Submit name of selected manufacturer and submit relevant catalogues if requested.
90 SMOKE ALARMS
- Type: Self-contained to BS 5446-1, Kitemark certified.
- Operation: Mains with DC battery back-up.
90 SMOKE DETECTORS
- Type: Self-contained to BS 5446-1, Kitemark certified.
- Operation: optical detector, battery operated with 10 year life lithium battery and hush
button facility..
10 FABRICATION
- Standard: BS 1186-2.
- Sections: Accurate in profile and length, and free from twist and bowing. Form out of solid
unless shown otherwise.
- Machined surfaces: Smooth and free from tearing, wooliness, chip bruising and other
machining defects.
- Joints: Tight and close fitting.
- Assembled components: Rigid. Free from distortion.
- Screws: Provide pilot holes. Sink heads of countersink screws at least 2 mm below timber
surfaces visible in completed work.
40 MOISTURE CONTENT
- Timber and wood based products: Maintain within range specified for the component during
manufacture and storage.
50 FINISHING
- Joinery surfaces: Smooth, even and suitable to receive finishes.
- Arrises: Eased unless shown otherwise on drawings.
- End grain in external components: Seal with primer or sealer as section M60 and allow to dry
before assembly.
Z11 PURPOSE MADE METALWORK
10 FABRICATION GENERALLY:
- Grades of metals, section dimensions and properties to be to the appropriate British Standard.
When not specified, select grades and sections appropriate for the purpose.
- Unless specified otherwise, fasteners to be of the same metal as the component, with matching
coating or finish.
- Do not permit contact between dissimilar metals in components which are to be fixed where
moisture may be present or occur.
- Finished components to be rigid and free from distortion, cracks, burrs and sharp arrises.
Moving parts must move freely and without binding.
20 COLD FORMED WORK: Use brake presses or cold rolling to produce accurate profiles with
straight arrises.
30 WELDING/BRAZING GENERALLY:
- Thoroughly clean surfaces to be joined.
- Ensure accurate fit using clamps and jigs where practicable. Use tack welds only for temporary
attachment.
- Make joints with parent and filler metal fully bonded throughout with no inclusions, holes,
porosity or cracks.
- Prevent weld spatter falling on surfaces of materials which will be self-finished and visible in
completed work.
- Remove all traces of flux residue, slag and weld spatter.
40 WELDING OF STEEL: Metal arc welding to BS 5135 and BS EN 1011-1, or other methods
subject to approval.
70 GALVANIZING: To BS EN ISO 1461. Provide all necessary vent and drain holes and seal to
approval after galvanizing.
90 ANODIZING: To BS 3987.
10 GENERALLY:
- Application to be carried out after cutting and machining, but before assembly, by a processor
licensed by the treatment solution manufacturer for the specified treatment.
- For each batch of timber, provide a certificate of assurance that treatment has been carried out
as specified.
20 BWPDA COMMODITY SPECIFICATIONS, where specified, are those defined in the latest
edition of the British Wood Preserving and Damp-proofing Association Manual. Solution
strengths and treatment cycles to be selected to achieve the service life (if specified) and to suit
timber treatability.
10 FIXING GENERALLY: Use fixing and jointing methods and types, sizes, quantities and
spacings of fasteners which are suitable having regard to:
- Nature of and compatibility with product/material being fixed and fixed to,
- Recommendations of manufacturers of fasteners and manufacturers of components, products
or materials being fixed and fixed to,
- Materials and loads to be supported,
- Conditions expected in use,
- Appearance, this being subject to approval.
30 FIXING THROUGH FINISHES: Ensure that fasteners and plugs (if used) have ample
penetration into the backing.
35 PACKINGS
- Provide non-compressible, rot proof packings at fixing points to take up tolerances and prevent
distortion.
- Ensure that packings do not intrude into zones that are to be filled with sealant.
40 CRAMP FIXING:
- When not specified otherwise, position cramps not more than 150 mm from each end of frame
sections and at 600 mm maximum centres.
- Secure cramps to frames with matching screws as masonry work proceeds, and fully bed in
mortar.
50 PELLETING: Countersink screw heads 6 mm below timber surface and glue in grain-matched
pellets cut from matching timber. Finish off flush with face.
60 ADHESIVES:
- Types: As specified in the relevant section.
- Surfaces to receive adhesive to be sound, unfrozen and free from contamination likely to affect
bond. Where necessary, clean as recommended by manufacturer.
- Adjust surface regularity and texture as necessary to suit bonding and gap filling
characteristics of adhesive.
- Observe manufacturer's and statutory requirements for storage and safe usage of adhesives.
- Do not use in unsuitable environments or beyond the storage period recommended by the
manufacturer.
- Apply using recommended spreaders/applicators to ensure correct coverage. Bring surfaces
together within recommended time period and apply pressure to ensure full bonding.
- Remove surplus using methods recommended by manufacturer, without damaging surfaces.
10 MORTAR MIX PROPORTIONS and other particular requirements are specified elsewhere.
40 CEMENT FOR MORTAR: When not specified otherwise, to be Portland cement or Portland
blastfurnace cement, to class 42.5 or 52.5, manufactured and supplied under the BSI Kitemark
scheme for cement. All cements must comply with the appropriate British Standard.
50 ADMIXTURES: To BS 4887. Do not use in mortar unless specified or approved. Do not use
calcium chloride or any admixtures containing calcium chloride.
70 MAKING HYDRAULIC LIME:SAND MORTAR: Mix thoroughly, first in the dry state and
then with water. Follow the lime manufacturer’s recommendations for each stage of the mix.
Add only sufficient water to produce a workable mix.
20 SUITABILITY OF JOINTS
- Presealing checks:
- Joint dimensions: Within limits specified for the sealant.
- Substrate quality: Surfaces regular, undamaged and stable.
- Joints not fit to receive sealant: Submit proposals for rectification.
30 PREPARING JOINTS
- Surfaces to which sealant must adhere: Remove temporary coatings, tapes, loosely adhering
material, dust, oil, grease, surface water and contaminants that may affect bond.
- Vulnerable surfaces adjacent to joints: Mask to prevent staining or smearing with primer or
sealant.
- Primer, backing strip, bond breaker: Types recommended by sealant manufacturer.
- Backing strip and/or bond breaker installation: Insert into joint to correct depth, without
stretching or twisting, leaving no gaps.
- Protection: Keep joints clean and protect from damage until sealant is applied.
40 APPLYING SEALANTS
- Substrate: Dry (unless recommended otherwise) and unaffected by frost, ice or snow.
- Environmental conditions: Mix and apply primers and sealants within temperature and
humidity ranges recommended by manufacturers. Do not dry or raise temperature of joints by
heating.
- Sealant application: Fill joints completely and neatly, ensuring firm adhesion to substrates.
- Sealant profiles:
- Butt and lap joints: Slightly concave.
- Fillet joints: Flat or slightly convex.
- Protection: Protect finished joints from contamination or damage until sealant has cured.