Professional Documents
Culture Documents
Annexure For Testing & Commissioning of Domestic Water Pumps
Annexure For Testing & Commissioning of Domestic Water Pumps
From W2
basement to
W1, W2 &
Water transfer CR 64-7-1 1 duty + 1
16 16 W3 towers
pump set Grundfos standby
Over head
tanks
1set of each
Water booster CH 8-50 1 duty + 1 towers (6
2 3
pump set Grundfos standby tower)
Doc. No. :
Location / Area :
Verification Sign
S. No. Activities / Items to be Inspected
of Engineer
Check the make, model and type of the installed
1.
pump as per approved drawings and submittal.
Check the location of pumps as per approved
2.
drawings.
Ensure the method statement and test report formats
3.
are approved prior to testing and commissioning.
Check availability for access to all components for
4.
testing and commissioning.
Check shipping bolts/clamps are removed prior to
5.
start up.
Ensure alignment is checked and completed as per
6.
manufacturer’s instructions.
Check the provisions for anti-vibration as per
7.
approved details and submittals.
Check all piping connections are complete including
8.
flexible connections as per approved details.
Check all nuts, bolts, screws etc, are secure and
9.
tightened as required.
Rotate the pump shaft manually and ensure it rotates
10.
freely.
REMARKS
ETA QC ENGINEER
NAME
SIGNATURE
DATE