PUMP SCHEDULE

Flow Rate Pump Set


Pump Pump Ref Head (Bar) Serve to
(L/S) Configuration
From E2
basement to
Water transfer CR 45-8-2 1 duty + 1 E1, E2 & E3
14 14
pump set Grundfos standby Towers over
head tank.

From W2
basement to
W1, W2 &
Water transfer CR 64-7-1 1 duty + 1
16 16 W3 towers
pump set Grundfos standby
Over head
tanks

1set of each
Water booster CH 8-50 1 duty + 1 towers (6
2 3
pump set Grundfos standby tower)
Doc. No. :

Nasa Multiplex Rev. No. : 0


Date :

Test Certificate for Domestic Water Pumps ETA


M&E Division
Client Project Design Consultant MEP Consultants
EMAAR Properties Burj Dubai – The Residences Woods Bagot Roberts & Partners

Location / Area :
Verification Sign
S. No. Activities / Items to be Inspected
of Engineer
Check the make, model and type of the installed
1.
pump as per approved drawings and submittal.
Check the location of pumps as per approved
2.
drawings.
Ensure the method statement and test report formats
3.
are approved prior to testing and commissioning.
Check availability for access to all components for
4.
testing and commissioning.
Check shipping bolts/clamps are removed prior to
5.
start up.
Ensure alignment is checked and completed as per
6.
manufacturer’s instructions.
Check the provisions for anti-vibration as per
7.
approved details and submittals.
Check all piping connections are complete including
8.
flexible connections as per approved details.
Check all nuts, bolts, screws etc, are secure and
9.
tightened as required.
Rotate the pump shaft manually and ensure it rotates
10.
freely.

11. Check the emergency manual start.

12. Check automatic start and stop.

13. Check auxiliary alarm contacts.


Check identification labels/tags are provided as per
14.
approved submittals/details.
Installation of pump/s certified by manufacturer or
15.
their authorised representative.
On initial start up check for correct direction of
16.
rotation.
17. Check for any unusual noise and vibration on start up.

Electrical Checks prior to Start-up

Check all cabling and control wiring is completed and


18.
tightened as required.
Check the provision of grounding as per approved
19.
drawings and details.
Check cables have been tested verify test reports prior
20.
to start-up.
Check the isolator is fixed close to pumps for
21. emergency shutdown and maintenance, as per
approved drawings.
Check the line voltage and phase rotations as per
22.
requirement prior to start up.
23. Ensure all identification works are complete.
Check the current drawn by pump motor is normal on
24.
initial startup
Record all test results on approved commissioning
25.
format.

REMARKS

ETA QC ENGINEER
NAME

SIGNATURE
DATE