MER - INS - WI - Digest Manta Retrieve Phase
MER - INS - WI - Digest Manta Retrieve Phase
MER_INS_WI_Digest Manta
Retrieve Phase
Purpose
The purpose of this instruction is to define the charging, testing, and starting procedures for MANTA1.0
Nodes.
Authority
Party Manager
The Party Manager has overall responsibility for the monitoring of the operation, and to ensure there
are sufficient personnel for the task, and they are trained and competent.
Chief Instrumentation
Instrument Chief or Shift leader Instrumentation has overall responsibility for monitoring of operation at
task.
Employees
PXGEO empowers and expects, any employee to initiate a STOP & STEP BACK if they consider an
operation to be unsafe, inadequately planned or un-controlled. All Employees involved in any operation
on-board the vessels/yard are responsible for the safety of their working environment as well as the work
environment of their colleagues.
Hazards / Safety
General
• PPE/Precautions: No specific PPE required, beyond that required for the work area
Employee Training
• All personnel are to be trained in accordance with the Crew Training Matrix.
• All new personnel are required to have on the job specific training conducted by the shift
supervisor, recorded and submitted to HSE. New personnel are identified and assigned a mentor
– This is in accordance with the Short Service Employee policy in place by SBGS. All SSE are to
be supervised until assessed as competent.
Definition
• The Global Standard for QHSE Definitions apply to this document. In addition, the following
specific definitions apply:
• PPE - Personal Protective Equipment
• TRA -Task Risk Assessment
• Digest - Human/Manta Interface software
• DAC – Download and Charging Rack
o Each Mini Control system comprises one Download and Charging (DAC) Rack, providing
the ability to manage 18 nodes simultaneously per system.
• DAR – Digital Autonomous Recorder
• NSS - Node Storage & Service System
• MANTA – New model of Manta nodes used on crew since January 2021
Overview
Carrying out the task:
• Toolbox Meeting / Shift Change over Meeting carried out with all personnel involved in the
task/shift.
• Take over from previous shift. Follow up on DAC Log book.
• If a fault is diagnosed this is to be reported to the Shift Leader who will conduct the fault finding
measures.
Reference
Digest Command and Control User Guide- November 2022. ( Authors: Software Team / Manta Crew ).
Attachments
None
General Guidelines
• Before you begin, it is critical to understand the charging scheme:
o The Trickle Chg ON will be used to keep the node fully charged. It will keep a current
charge of 0.005 mA.
o Unplugging a charging node/s without properly powering off may result in a current
spike that will damage the DAR.
Retrieve Phase
• Using the cap connector remover tool, gently remove the connector caps (counterclockwise).
• Plug the nodes accordingly and follow the connector notch as guide then rotate (clock wise).
• Manta nodes will begin to appear within 82 seconds of being plugged in. Otherwise, unplug the
cable and wait 82 seconds before reconnecting the manta node.
• Operations
Go Retrieve For a selected node or shelf of nodes will initiate the sequence defined
Chained in the Retrieve Phase operation. The operations are displayed on
operation Connects upper middle screen. Typical Retrieve operations are stop
recording, skew measurement, download data and limits. Operations
that are not permitted are locked.
• Select a Shelf
o A shelf comprises 6 nodes as per the physical layout in the DAC.
o Step DOWNLOAD
o Step Limit.
• The node cell will be Green when the process is done. If the node has an error it will be highlight
with a Red error box around the node
• You can verify the status by node with the button Past Orders
• After download, you must see the message: “download finished OK” (in Past ORDERS)
• Take a screen shot and informed the QC that the nodes are successfully downloaded with any issues.
• Charge the nodes.
• Wait for the QC’s email saying that all nodes are good to redploy and once fully charge you can run the
deploy phase again.
Table of Amendments
Rev Date Rev No. Amendments Author Comments
30-Jan-23 1.0 First version Osborn Peralta – Instrument Field Engineer Created for Mercury