Download as pdf or txt
Download as pdf or txt
You are on page 1of 81

FACULTY OF BUILT ENVIRONMENT

DEPARTMENT OF QUANTITY SURVEYING

INDUSTRIAL TRAINING REPORT


BQES 4102
STUDENT NAME NURUL AQILAH BINTI MOHD ISA
MATRIC NO. BEQ150080 SESSION 2018/2019
COURSE COORDINATOR SR DR SAIPOL BARI ABD KARIM
COMPANY NAME/ADDRESS ARH JURUKUR BAHAN SDN BHD

224A, JALAN NEGARA 2, TAMAN MELAWATI

Tel: 03-41068192/3/4/5 | Fax: 03-41068190 | Email:
info@arh.com.my
INDUSTRIAL SUPERVISOR NURUL' AIN BINTI BAHARUDIN
STARTING DATE 18-Feb-19 END DATE 5-Jul-19

DECLARATION

‘I hereby declare that this industrial training report is the result of my own
research and all the resources and references have been clearly stated.’

5 JULY 2019 NURUL AQILAH MOHD ISA

BEQ150080

ACKNOWLEDGEMENT

I would like to extend my deepest gratitude and respect to my supervisor,


Puan Nurul’ Ain Baharudin, for her continuous support and assistances
throughout the completion of this industrial training. Without her guidance, this
industrial training would not have become possible. Her willingness to spend her
time to encourage me to keep on going whenever I was at lost is something that
I will cherish forever. Thank you for putting up with me throughout the
completion of this industrial training.

Not to forget, our coordinator, Sr Dr Saipol Bari bin Abd Karim, who have
always been supporting and provide guidance for us since day one until the very
last day of our industrial training period. Thank you for always ensuring us to be
on the right track.

Above all, I cannot thank my parent enough for all the support,
encouragement and for being understanding. Their patience in putting up with
my inconsistent mood and needs are very much appreciated. Not to forget my
siblings who have been there whenever I need someone to hear my problems,
and for being the ones who cheered me up whenever I was on my knees.

Lastly, to my friends who have been together with me through ups and
downs to make the industrial training report possible, please know that I am
beyond grateful to have all of you around.

Thank you.

ii

TABLE OF CONTENTS

PAGE NO.
DECLARATION i
ACKNOWLEDGEMENT ii
LIST OF FIGURES vi
LIST OF APPENDIXES vii
LIST OF ABBREVIATIONS viii
CHAPTER ONE 1
INTRODUCTION 1
1.1 Company’s Background 1
1.2 Organization Chart 5
CHAPTER TWO 6
PROJECT PARTICIPATED 6
2.1 Types of Area of Expertise 6
2.2 Relevance of Work Done with Course Taken 7
2.2 Summary of Project Participated 9
CHAPTER THREE 14
CRITICAL ANALYSIS 14
3.2 Area A – Pre-Construction 14
3.2.1 Project’s Background 14
3.2.2 Background Issue 15
3.2.3 Solutions 16
3.2.4 Recommendation and reason for the selection 17
3.2.5 Consequences 18
3.2.6 Lesson Learnt 19
3.3 Area E- Post Contract Cost Control 20
3.3.1 Project’s background 20
3.3.2 Main issue 21
3.3.3 Solutions 22
3.3.4 Recommendation and reason for the selection 23
3.3.5 Implication on selected option 24

iii

3.3.6 Lesson Learnt 25


CONCLUSION 26
APPENDICES 27

iv

LIST OF TABLES

TABLE TITLE PAGE NO.

Table 1 List of Project done by ARH Jurukur Bahan 3


Sdn Bhd
Table 2 List of project participated 9

Table 3 EV3A Project details 14

Table 4 Supplier’s presentation in term of moiety 18


Table 5 DRB-HICOM project details 20

LIST OF FIGURES

FIGURE TITLE PAGE NO.


Figure 1 ARH Jurukur Bahan Logo 1
Figure 2 Organization Chart 5
Figure 3 Area of expertise covered 7
Figure 4 Construction of new roof on the existing building 14
Figure 5 New pitch roof 14
Figure 6 Construction of RC retaining wall around the 20
TNB substation

vi

LIST OF APPENDICES

APPENDIX TITLE PAGE NO.


1. Elemental Cost Analysis for double storey
house
2. Elemental Cost Analysis for Faculty of
Engineering
3. Bills of Quantities for Roof
4. Supplier’s Bills of Quantites on Waterproofing
5. TNB Substation
6. Roofing system
7. Work Dairy Logbook

vii

LIST OF ABBREVIATIONS

Board of Quantity Surveyors Malaysia BQSM


Assessment for Professional Competence APC
Building Information Modeling BIM
Material on Site MOS
Variation Order VO

viii

CHAPTER ONE

INTRODUCTION

1.1 Company’s Background


Figure 1 ARH Jurukur Bahan Logo

Name of Firm: ARH Jurukur Bahan Sdn Bhd

Address: 224A, Jalan Negara 2, Taman Melawati 53100 Kuala Lumpur

Branches in Malaysia: Ulu Klang (Kuala Lumpur), Ipoh (Perak) and Johor Bharu (Johor Bharu)

Year of Establishment: 1988

Awards & Certification: ISO 9001- 2015 by Certification International (UK) Limited

Name of Supervisor: Nurul’ Ain binti Baharudin

Position of Supervisor: Contract Executive

Originally, the firm was first known as Azhar Rouse & Hisham Sdn and
was incorporated in 1988 as a corporate body Quantity Surveying professional
practice registered with the Board of Quantity Surveyors Malaysia. ARH Jurukur
Bahan Sdn Bhd is also registered with the Ministry of Finance to provide quantity

surveying consultancy services to all Government projects. The firm’s name


indicates its founder directors who are Encik Ahmad Rouse and Dato’ Hisham Hj
Jafrey. Later in 1995, once the firm had successfully established itself, Encik
Bahrudin Hj Rahmat and Encik Azlee Hj Abdullah were appointed to the Board of
Directors. Then, in December 2001, Azhar Rouse & Hisham Sdn was converted
to a Private Limited Company and changed its name to ARH Jurukur Bahan Sdn
Bhd.

In June 2003, the firm was awarded the prestigious ISO 9001-2000
certification by Certification International (UK) Limited. After 6 years, the firm
managed to reaffirmed its commitment and subsequently has received the ISO
9001-2008 certification from the same certification body. Currently ARH is
earnestly committed in its effort to obtain the new ISO 9001- 2015 certification.

As time goes by, the firm had slowly gets its place in the industry. Hence, due to
the progression of the firm and increase in number of staff employed, in 2009,
Encik Noor Masyri Mohd Shaari was appointed to the Board of Directors,
followed by the appointments of Encik Shahrul Azlan Abd Ghani and Puan Zunita
Che Omar in 2016. This change in the organisation was a major step forward
that demonstrated the firm’s aspiration and development from traditional
professional partnership practice into a leading major consultancy business.

Until today, ARH Jurukur Bahan Sdn Bhd has committed to provide a diverse
range of construction related consultancy services to a wide range of clients in
both the public and private sectors both locally and overseas. The firm’s range of
core services is design to be flexible enough to be adapted to your individual
requirements. These services are delivered via a personal and professional
approach by a highly skilled, dedicated and passionate team, a combination that
results in a successful project from inception to completion.

Over the years, the firm had established an excellent reputation and building on
their wealth of experience, the firm is now able to offer the perfect combination of
traditional quality and cutting edge innovation.

They carry out a full range of professional Quantity Surveying services in all
sectors of the property and construction industries, and employ a proactive
approach at each stage of the project development process.

In order to keep up with the changing nature of our construction industry, ARH
Jurukur Bahan Sdn Bhd had geared towards maximizing the use of modern
means of communication amongst their staff and Clients. The following are some
of the examples of technology and software used in ARH Jurukur Bahan Sdn
Bhd;
• Binalink software (a fully integrated computerized bills of quantities
production package)
• Microsoft Office Suite – Excel, Word, Powerpoint and Outlook.
• Microsoft Project Programming software.
• A central server (Data & Email) and individual workstations offering Local
Area Network
and intranet facilities to all staffs
• High Speed Internet connectivity
Until today, ARH Jurukur Bahan Sdn Bhd has successfully open up to 3 branches which
are located in Ipoh, Johor Bharu and Kuala Lumpur whereby Kuala Lumpur branch is the
headquarter. After being successfully emerged, this firm has involved in many kinds of
construction projects regardless its sectors such as administrative building, residential
building, international building and many more. The following Table 1 shows the list of
project that ARH Jurukur Bahan has been incorporated with;

Table 3 List of Project done by ARH Jurukur Bahan Sdn Bhd

NO SECTOR PROJECT
1 Administrative Building -Suruhanjaya Tenaga EE Office Building,
Putrajaya, Wilayah Persekutuan
-Menara Hasil Office Building, Johor Bahru,
Johor
2. Residential Building -Seri Pilmoor High-End Semi-D, Ara
Damansara, Selangor

-Ara Hills Apartment, Ara Damansara,


Selangor
3. Health & Welfare Building -Sultanah Bahiyah Hospital, Alor Setar,
Kedah
-Serdang Hospital, Serdang, Selangor
4. Transport & Industrial -Senai Airport, Johor Bahru, Johor
Building - CIQ Complex, Johor Bahru, Johor
5. Educational, Cultural & -Multimedia University, Cyberjaya, Selangor
Scientific Building - Sultan Abdul Samad ID & Conservation
Works, Kuala Lumpur, WP
6. Refreshment, -Austin Hills Golf & Country Club,
Entertainment & Johor Bahru, Johor
Recreational Building -Sebana Marina & Clubhouse,
Johor Bahru, Johor
7. Religious Building -Naza Mosque, Shah Alam, Selangor
- Masjid Kota Iskandar, Johor
8. Green/Sustainable - Energy Commission Headquarters,
Building Putrajaya, Wilayah Persekutuan
- KL Sentral Park, Kuala Lumpur, Wilayah
Persekutuan
9. Civil Engineering Works - Cable Stay Bypass Bridge, Muar, Johor
- EDL Expressway, Johor Bahru, Johor
10. Land, Planning & - Sanitary Landfill, Bukit Tagar, Selangor
Landscapes - UIAM Landscaping Works, Gombak,
Selangor
11. International - Petronas HQ Office Building, Khartoum,
Sudan
- Malaysian Embassy Upgrading Works,
Manila, Philippines

1.2 Organization Chart



Managing Director

Dato’ Hisham Hj Jafrey

Directors


Sr Bahrudin Sr Azlee Hj Sr Noor Masyri Sr Shahrul Sr Zunita
Hj Rahmat Abdullah Mohd Shaari Azlan Abdul Che Omar
Ghani

Associates


Sr Md Khalis Sr Nasafian
Hj Ismail Mohd Shariff

Figure 2 Organization Chart

CHAPTER TWO

PROJECT PARTICIPATED

2.1 Types of Area of Expertise


As accordance to the requirements stated by the university, students will have to go through at
least 7 out of 14 areas of expertise set by the Board of Quantity Surveyors Malaysia (BQSM)
under the Assessment for Professional Competence (APC) as listed below: -

A. Pre-construction

B. Contract Administration

C. Construction Contract Operations

D. Cost Planning and Quantification of Construction Work

E. Post Contract Cost Control

F. Construction Services

G. Project Management

H. Research and Development

I. Public Development Policy

J. General Management and Construction Finance

K. Life Cycle Costing

L. Facilities Management

M. Sustainability and Green Building Index (GBI)

N. Building Information Modeling (BIM)

2.2 Relevance of Work Done with Course Taken


Area of Expertise Covered

Building
Information
Modeling (BIM)
2%
Contract
Public Administration
Project Development Pre Construction 1%
Management Policy 21%
9% 17%

Post Contract Cost


Control
38% Construction
Contract
Operations
12%


Figure 2 Area of expertise covered

Throughout my Industrial Training period, I have been given tasks related to Quantity Surveyor’s
field, starting from pre-contract stage until post-contract stage. These tasks given surely have something
to do with what I have learned during 3 and half year studies in the University of Malaya.

Based on Figure 1, I have covered 8 out 14 areas as listed in the requirement which are; Post
Contract Cost Control, Pre-Construction, Public Development Policy, Project Management, Construction
Contract Operations, Construction Services, Contract Administration and Building Information Modelling
(BIM).

Most of the time, I have been given the task related to our core subjects such as Measurement
of Construction Works, Construction Law, Professional Practice and Project Management. It comes to
my attention that it is important to be well prepared with information regarding the project we are
involved in before going out to the meeting. A part of that, it is no doubt that communication among
construction players are vital to avoid some misunderstanding. Also, it is quite fascinating to learn new
software such as Binalink for taking off works as it gets to strengthen my skills with IT Management in
Construction. Being trusted to present the firm by going to site valuation and prepare recommendation
for interim payment is such an eye opening on real life Quantity Surveyor’s nature of work.

2.2 Summary of Project Participated


Table 4 List of project participated

Client Project Task


Sime Darby Cadangan membina dan Involve in;
Elmina menyiapkan 203 unit rumah teres 2 i. Taking Off
Development Sdn tingkat (Fasa EV3A) beserta 2 unit infrastructure works
Bhd wakaf, 1 unit pencawang elektrik on sewerage for re-
(double chamber) dan kerja-kerja measurement.
infrastruktur berkaitan di atas Lot ii. Taking Off
360, Elmina West, Sekyen U15, infrastructure works
40160 Shah Alam, Selangor Darul on water reticulation
Ehsan for re-measurement.
iii. Taking Off
infrastructure works
on roadworks for re-
measurement.
iv. Taking Off
infrastructure works
on walkway for re-
measurement.
v. Taking Off
infrastructure works
on drainage for re-
measurement.
vi. Preparing Variation
Order documentation

Sime Darby Cadangan membina dan Involve in;


Elmina menyiapkan 151 unit rumah teres 2 i. Taking Off
Development Sdn tingkat (Fasa EV3B) beserta 2 unit infrastructure works
Bhd wakaf, 1 unit pencawang elektrik on sewerage for re-
(double chamber) dan kerja-kerja measurement.
infrastruktur berkaitan di atas PT ii. Taking Off
50037 dan Lot 360, Elmina West, infrastructure works
Sekyen U15, 40160 Shah Alam, on water reticulation
Selangor Darul Ehsan for re-measurement.
iii. Taking Off
infrastructure works
on roadworks for re-
measurement.
iv. Taking Off
infrastructure works
on walkway for re-
measurement.
v. Taking Off
infrastructure works
on drainage for re-
measurement.

vi. Preparing Variation


Order documentation

Sime Darby Proposed construction for 72 units Involve in;


Elmina of 2 storey terrace house and i. Produce certificate for
Development Sdn related infrastructure works at Lot the recommendation
Bhd 360, Phase G3C, Elmina Seksyen for interim payment.
U16, 40150 Shah Alam, Selangor ii. Preparing
Darul Ehsan documentation for
site meeting
iii. Site valuation
iv. Client-consultant
meeting
v. Site meeting
Glenmarie Proposed construction and Attending;
Development completion of new pitch roof above i. Materials
(Pahang) Sdn Bhd existing concrete roof slab, façade presentation at DRB-
upgrading, enhance works, HICOM on
drainage system, finishing & any waterproofing of roof
related works, at campus, DRB- at Subang Jaya
HICOM University of Automotive
Malaysia, Mukim Langgar, Daerah
Pekan, Pahang Darul Makmur for
Glenmarie Development (Pahang)
Sdn Bhd
Kerajaan Cadangan pembinaan Langat i. Review
Malaysia; Centralised Sewage Treatment Engineer’s
Kementerian Plant dan penyambungan paip drawing for taking
Tenaga, pembentungan di kawasan tadahan off.
Teknologi Hijau Lembangan Sungai Langat secara Assists in;
dan Air; reka dan bina. ii. Preparing
Jabatan sewerage
Perkhidmatan measurement for
Pembentungan Zone 7
iii. Preparing BQ for
sewerage
measurement
iv. Preparing
documentation for
sewerage
measurement
v. Preparing
summary of works
Sime Darby USJ Proposed softscape work for i. Assist in
Development Sdn proposed (phase 5T4(ii) stratified preparing tender
Bhd housing development phase 5T documents for
comprising of 72 units nominated sub-
condominium Block ‘B’ and related contractor

10

infrastructure works at Putra ii. Involve in taking


Heights, Selangor Darul Ehsan off softscape
(parcel ‘E1’)) works
iii. Preparing query
list
Sime Darby USJ Proposed design, supply and i. Involve in taking
Development Sdn installation of engineered timber off timber floor
Bhd finishes for proposed phase 5T4(ii) finish works
stratified housing development ii. Assist in
phase 5T comprising of 72 units preparing tender
condominium Block 'B' and related documents for
infrastructure works at Putra nominated sub-
Heights, Selangor Darul Ehsan contractor
(Parcel 'E1') iii. Preparing query
list
iv. Attend pre-site &
site possession
meeting
v. Review insurance
policy submitted
by Contractor
vi. Rationalization of
Rates
vii. Assist in
preparing contract
documents
Sime Darby Ara Additional visitor carpark for i. Attending open
Damansara proposed residential development tender session at
Development Sdn for rectification Phase 1E&2E at Sime Darby
Bhd Ara Damansara, Mukim Property Berhad,
Damansara, Daerah Petaling, Ara Damansara
Selangor Darul Ehsan (HQ)
ii. Assist in
preparing tender
report
iii. Attend tender
clarification
meeting at Oasis
Ara Damansara
iv. Preparing
addendum
Jabatan Kerja Projek menaiktaraf Jalan Lingkaran i. Attending site
Raya Malaysia Tengah (MRR2) persimpangan valuation
(JKR) Taman Melati dan kerja kerja
berkaitan secara reka dan bina
Sime Darby Proposed earthworks, suction tank i. Preparing tender
KLGCC 2.879 MLD, Pump House with document
Development Sdn 600mm diameter Pumping Main
Bhd and TNB Subsatation for KLGCC
Resort development along Jalan

11

1/70D, off Jalan Bukit Kiara, Kuala


Lumpur
Pengurusan Aset Pakej 1 – Kerja-kerja membekal i. Preparing tender
Air dan memasang paip jenis keluli document for
lembut (mild steel, m.s.) nominated sub-
bergaripusat nominal 800mm dan contractor
1200mm, serta memasang,
menyiapkan, mengujiterima dan
mentauliah kerja-kerja sivil,
mekanikal, elektrikal dan yang
berkaitan di tangka sedutan
berkapasiti 20ml dan rumah pam
utama di Bandar Baru Enstek,
Seremban, Negeri Sembilan Darul
Khusus

i. Pre-construction

At this stage, I involved in preparing tender documents for various projects, be it


residential sector or even infrastructure sector. The task given requires me to be
more particular when preparing the tender documents as accordance to the client
needs. Few amendments encountered during the preparation stage. Besides, I even
get to attend the open tender session for additional visitor carpark project. Most
importantly, I also get to involve in the taking off process for minor elements such as
timber floor finish and softscape works for residential building. During completing the
task, I have encountered few problems but eventually managed to get it done in time.

ii. Contract Administration

In this area, I was required to attend tender clarification meeting for the additional
visitor carpark project. The purpose of this event is to clarify any misunderstanding or
to hear out suggestion from the tenderers. It is an important event as it will help the
consultant team to amend unforeseen things.

iii. Construction Contract Operations

This area focuses on the preparation and review of sub-contract tenders. As for that,
I have attended materials presentation to find the best waterproofing method to be
installed in roofing system. I have also prepared tender documents for nominated-
sub contractor for the proposed softscape works for residential project.

12

iv. Post Contract Cost Control

This area focused on the costing and financial management which includes the
carrying out of interim valuations and dealing with claims. As I have been to site
valuation myself, most of the recommendation of the interim payments is prepared
by me with guidance by my supervisor. It is crucial to carefully conduct valuation to
avoid any underpayment or overpayment to the contractor.

v. Project Management

This area covers the aspect of managing a construction project whereby it is required
for me to get updated with issues involved in development of the construction project
as well as the related technical and legal implications. It includes project coordination
as well as monitoring and budget control along the construction period. To cater with
this requirement, I have been actively involved in both site meetings and client-
consultant every 2 weeks to get updated on the progress works for Elmina Project
Phase G3C (residential sector).

vi. Public Development Policy

Even though ARH Jurukur Bhan Sdn Bhd is in the private sector, they also involved
in many public infrastructure projects. As for myself, I have been involved in the
taking off process for the construction of sewerage treatment plant as well as
attending valuation for MRR2 project. Covering this area has taught me some of the
regulatory requirements in handling private sector’s project in comparison to the
public sector itself.

vii. Building Information Modelling (BIM)

Even though I have only spent few hours in this area, it is merely enough for me to
understand the basic skills to use new software in short period of time.

13

CHAPTER THREE

CRITICAL ANALYSIS

3.2 Area A – Pre-Construction

3.2.1 Project’s Background


Project Title: PROPOSED CONSTRUCTION AND COMPLETION NEW PITCH ROOF ABOVE
EXISTING CONCRETE SLAB, FAÇADE UPGRADING, ENHANCE WORKS, DRAINAGE
SYSTEM, FINISHING AND ANY RELATED WORKS AT CAMPUS, DRRB-HICOM
UNIVERSITY OF AUTOMOTIVE MALAYSIA (DRB-HICOM U), MUKIM LANGGAR, DAERAH
PEKAN, PAHANG DARUL MAKMUR FOR GLENMARIE DEVELOPMENT (PAHANG) SDN
BHD

Table 5 EV3A Project details

Client Glenmarie Development (Pahang) Sdn Bhd


Contract Sum RM 5,118,995.00
Contract Period 7 months
LAD/day RM 700.00/day
Condition of Contract PAM 2006 (With Quantities)
Architect Pakatan Akitek Sdn Bhd
Quantity Surveyor ARH Jurukur Bahan Sdn Bhd


Figure 4 Construction of new roof on the existing building Figure 5 New pitch roof installed

14

3.2.2 Background Issue


Issue: Material Selection and Evaluation before Tender Process

In a construction, it is essential to select a suitable material to be used, especially for high rise
building. A part of considering the type of building to be constructed, it is also important for the
project team to consider the site location, as certain part in Malaysia will gone through monsoon
season which in southwest (late May to September) and northwest (November to March). As for
this particular project, since it is located in Pekan, Pahang, the raining season occurs during the
months from November to March due to the north-east monsoon season. It happens to be the
high level of tabulation rain and has caused a minor destruction to the roofing system.

The issue arose when the building was facing some serious leakage problem even the building
has not been there for a long time. The client was aware of this and highlighted this problem to
the new project team. Originally, the building has adopted a flat roof system which includes
waterproofing. It is uncertain to the project team whether the design is incompetent or the
quality of the waterproofing substance is at stake.

Therefore, the client has instructed the Consultant to come up with the best solution which suit
tender budget allocated by their management amounting to RM 600,000.00 for the said trade. In
addition, one of the floor below roof structure is currently closed due to the leakage problem. It
is expected that overall tender process up to tender award and completion of project will be at
the soonest to avoid jeopardizing the building function.

15

3.2.3 Solutions

Several options were presented to the client before the decision was made. Materials
presentation was held at DRB-HICOM in Subang Jaya to evaluate the best material to be used
for the proposal of the new roof.

i. Option A - Re-waterproofing

Item Description Remarks


1. Material Pentens SPU-1000 Advantages
2. Durability • Eco-friendly
• High elasticity
• Strong and tough, extremely
high mechanical properties
• Hard wearing
• Outstanding impact
resistance
• No abnormality even
submerges in water for a long
time
• Fast set return to service in
minute
3. Cost Area = 1,255m2
Cost/m2 for roofing works including
all associated works
= RM 239,150.00/m2

ii. Option B – Metal Deck Roof

Item Description Remarks


1. Material Metal Sheet
2. Durability • Can withstand wind up to 140
mph
• No corrosion and crack
• Impact resistant
• Made up of recycled material
and can be recycled
• Rain and snow shedding
• Easy installation
3. Cost Area= 2,450m2
Cost for roofing works including all
associated works= RM 551,695.00

16

3.2.4 Recommendation and reason for the selection

Since the main purpose of tendering this project is to find the best possible material to withstand
the extreme weather in the area, Option B is chosen in respect due to the followings:

i. Material specification

Metal sheet roofing is relatively competent material to withstand such extreme


weather due to its high wind and impact resistant. As for the location wise, the
roofing system able to shed heavy rain and is suitable to be used during monsoon
season within that area. Moreover, metal can be an electrical conductor, but in
contrast, metal roofing does not attract lightning, nor is it any more likely to be struck
than any other type of roofing. This material is also highly resistant to fire. The
material is also can be easily installed especially for this building which has quite big
area.

ii. To avoid recurring leakage

Since it is uncertain on the major cause of the leakage problem, it is unlikely to be


the cause of waterproofing itself as the previous roofing system had also includes
waterproofing system on it.

iii. Within the stipulated budget

As discussed with the Client, their management will approve quickly the tender
requisition even though the cost implication on choosing this option is relatively
higher than Option A has to offer since this option is still under budget. If the tender
amount is not exceeding their budget. Thus, this will not hinder the target to operate
the floor below roof structure as soon as possible.

17

3.2.5 Implication on selected option


Roof failure is the deterioration of structural components caused by water intrusion. The use of
flat roof system is unsuitable for certain area due to their high tabulation rain. There is high
tendency for water puddle to occur on flat roof system.

Hence as a result, the client proposed to construct a new pitch roof above the existing concrete
roof slab by using metal sheet roofing for this project.

Based on the material presentation, the Client has decided to continue with the tender process
using metal roof spec in near time. They are more concern on tackling the leakage issue rather
than costing matter. However, below is the result of both supplier presentation in term of moiety:

Table 4 Supplier's presentation in term of moiety

Item Description Supplier Price Management Different Percentage


(RM) Budget (RM) (RM) (%)

1. Waterproofing 239,150.00 600,000.00 (360,850.00) 60.00


2. Metal roofing 551,695.00 600,000.00 (48,305.00) 8.00

The location of this project influenced the choice of material that has been proposed. For
example, the selection of roof covering must take into consideration the surrounding
environment as the site is located near the coastal area of South China Sea.

18

3.2.6 Lesson Learnt


i. Proper planning

The main purpose of proper planning is to achieve the most expected result such as
design relative to a set of prioritized criteria or constraints as per client’s requirement.
These include maximizing factors such as productivity, strength, reliability, longevity,
efficiency and utilization. Planning helps in choosing a better option to cater with any
problem arises. A QS should strengthen their management skills in order to perform
better and provide the team with a reliable time schedule to be followed to avoid any
discrepancies.

ii. Coordination between Consultants

A project could run smoothly if the project team perform a great teamwork to make it
happen. Every consultant appointed by the Client should play their role into their
optimum level and open for discussion with other team players. The designers
should take into consideration on every aspect, a part of focusing on the aesthetical
value itself. The Engineer should give the best advice on the material aspects,
considering the location of the site, the weather and site surrounding. A better
material proposal shall then be submitted to the QS for estimation. QS should look
thoroughly on both materials and cost in order to provide the best estimates to
presented to the Client.

iii. Knowledge on the material

Knowledge on construction technology is as important as having the knowledge to


estimate budget and provide measurement in any construction project. As a QS, the
process of choosing materials might not be part of our major concern as the
Engineer would give their points of view on this, however, we might need to have
knowledge on choosing a better offer which gives minimum implication on cost, time
or performance in a long run.

19

3.3 Area E- Post Contract Cost Control

3.3.1 Project’s background


Project Title: CADANGAN MEMBINA DAN MENYIAPKAN 203 UNIT RUMAH TERES 2
TINGKAT (FASA EV3A) BESERTA 3 UNIT WAKAF,1 UNIT PENCAWANG ELEKTRIK
(DOUBLE CHAMBER) DAN KERJA-KERJA INFRASTRUKTUR BERKAITAN DI ATAS LOT 360,
ELMINA WEST, SEKSYEN U15, 40160 SHAH ALAM, SELANGOR DARUL EHSAN

Table 5 DRB-HICOM project details

Client Sime Darby Elmina Development Sdn Bhd


Contract Sum RM 72,346,237.60
Contract Period 18 months
LAD/day RM 26,300.00/day
Condition of Contract PAM 1998-With Quantities (Revised October 1998)
Architect PARADIGM Architects Sdn Bhd
M&E Engineer Perunding Juruwas Sdn Bhd
C&S Engineer Perunding Aziz, Azali & Tee Sdn Bhd
Quantity Surveyor ARH Jurukur Bahan Sdn Bhd

This development consist of 203 units terrace house with approximately 2,500 sf/unit in gross
floor area.


Figure 6 Construction of RC retaining wall around the TNB substation

20

3.3.2 Main issue


Issue: Preparation of Variation Order (VO)

A variation order (VO) is any change or modification to the design, quality or scope of work that
is subject to an agreement with respect to the volume or nature of work carried out. VOs can be
caused either by the consultant, contractor or the employer himself. Since the project is using
PAM 2006 Form of Contract, problems encountered will be risen up and the Architect shall
issue VO on that particular problem. Raised VO will be subjected to re-measurement; thus, it
will have some cost impact on the construction cost, be it addition or it can be in form of
omission.

As for this particular project, there was a major platform level different approximately 2.3m high
between the TNB substation and the main road behind it. There was no indication of separate
level in the contract drawing until it was highlighted by the Main Contractor to the
Superintendent Officer (S.O.) through Request for Information (RFI) during construction. The
RFI is required for confirmation of any discrepancies in order to proceed with the work. It was
later found out that the slope at the TNB substation need to be protected at all cost to ensure it
is safe to the people around it. The client was aware on this and has required us to minimize the
implication of variation order towards the overall contract.

According to PAM 2006 Form of Contract, one of the alterations and modifications include the
addition, omission or substitution of any work except for the changes due to the rectification of
negligence, omission, default and/or breach of contract by the Contractor. All of the changes
stated shall be borne by the Contractor himself. Once the VO was raised to the Architect’s
attention, the Architect will issue and Architect’s Instruction (AI) ordering a Variation or
sanctioning the Variation made by the Contractor. Based on PAM 2006 Form of Contract, the
VO will not vitiate the Contract. Any pending on the valuation of Variations will cause the
Contractor to bear the cost and expenditure all Variations that have been instructed.

21

3.3.3 Solutions

Several options were presented to the client before the decision made. All two options given
were based on discussion with the S.O. and Engineer.

i. Option A - To build a retaining wall behind the TNB substation.

The relevant drawing was handed over to us for further estimation.

Item Description Remarks


1. Cost Proposed estimate;
Excavation: 72m3 x RM16.50 =
RM1,1188.00
Concrete: 54m3 x RM242.50 =
RM13,095.00
Formwork: 153m2 x RM28.00 =
RM4,284.00
Rebar: 3.113kg x RM2.70 = RM8,405.10

TOTAL = RM26,972.10
2. Time Required 2 weeks to complete
3. BP Drawings As advised by Engineer, no submission of
new layout to the Authority is needed

ii. Option B - To lower down main road level to suit TNB platform level.

A set of sketches brief method statement by engineer were given to the QS;

Item Description Remarks


1. Cost Proposed estimate;
Excavation: 1,380m3 x RM16.50 =
RM22.770.00
Realign Drain: 35m x RM150.00 =
RM5,250.00

TOTAL = RM28,020.00
2. Time Required 3 weeks to complete
3. BP Drawings As advised by Engineer, there will be no
requirement for revised layout.

22

3.3.4 Recommendation and reason for the selection


As the project was in tight schedule which they need to hand over the project in another 3 months’ time,
option A is adopted for the following reason;

i. Time Constraint

It is a priority to take the fastest completion time to avoid any extension of time. Based on
two options stated, Option A is the most suitable to adopt in order to comply with the
handing over due date. In comparison to Option B, Option A only takes about 2 weeks to be
completed while Option B needs extra 7 days to be completed.

ii. Cost Impact

In terms of cost, both options offer between RM 25,000.00 to RM 29,000.00. Since the client
has highlighted on minimizing the implication of VO, Option A is the best option to fulfill this
requirement. Option A offers a total of RM 26,972.10 is allocated for the construction RC
retaining wall compared to Option B which offers a total of RM 28,020.00 to lower down the
road level.

iii. Safety Issue

Option A offers a lower cost and time implication which both have fulfilled the client’s
requirement which is to minimize the implication of variation order towards the overall
contract sum. RC retaining wall used for slope protection can be useful in ensuring site
safety to its surrounding. Option B on the other hand require a lot of works to be done such
as demolition of the existing roads and pavements in order to lower down the road level to
suit with the TNB substation level. Hence, Option A is recommended to be implied as a VO
for this project.

23

3.3.5 Implication on selected option

As a result, the contractor has submitted a claim for provision of RC retaining wall behind TNB
substation as instructed by the Client. The amount of Variation Order will be finalized once the
works have completed and joint measurement will be done accordingly.

In compliance to the safety issue, the authority (TNB) require the client to complete all external
works before TNB supply electricity to the housing area has been catered while at the same
time the project team managed to ensure site safety to the user later on. On the other hand, as
it is a provision to add the RC retaining wall, hence there are not just cost implication but also it
has affected the time provided as accordance to the work program.

24

3.3.6 Lesson Learnt


i. To have a basic technical knowledge



In order to come out with a better solution, QS should have at least a basic technical
knowledge. This will help the individual to evaluate and put into consideration every
aspect including the structural part or the design part. For example, Option B
requires one to consider the flow of foul water during rainy days which might cause
flood at the end of the day due to inappropriate action taken to lower down the road
level.

ii. Proper planning

A proper planning needed to be done during the discussion with the clients on their
requirement on certain project. Even if every project is subjected to unforeseen
circumstances to happen, a proper planning should minimize the impact at the later
stage. For example, team players should play their role to the optimum and provide
the best suggestion and advice to the client.

iii. Roles of QS

QS have been trained professionally and among those who are qualified and have sufficient
experienced in dealing with anything related to construction cost, management and
communication on behalf of the Client. Dealing with VO are part of bread and butter in QS
profession. QS must provide a better judgement when VO has been issued based on Client’s
requirement.

25

CONCLUSION

Within short period of time, I have learned so much from my supervisor as well as my
colleagues who have been very helpful all along. Most importantly, the knowledge they shared
by answering my never-ending questions are very useful for me to be used to complete the task
given.

During my training period, I have been to so many places with different kind of purpose.
To name a few, I have been to Oasis Damansara for pre-site possession meeting, open tender
process as well as to attend tender clarification meeting, either by myself or with my colleague.
Getting to know people from different area of expertise is very an eye-opening. I get to witness
how the meeting was conducted, and how every construction players play their role, including
the Quantity Surveyor itself. Things discussed were clearly being stated to avoid
miscommunications, as well as to justify yourself when being asked. To that, I learned that
communication is the key to ensure a smooth progress during discussion. Teamwork is also
vital to get things done as per requirement and within time given. Any discrepancies discussed
will be negotiated properly and professionally.

A part of that, I get to experienced being a QS myself when attending meetings with
client. One thing I get to learn from my experience is that, time management is equally important
as communication. Being late to a meeting is not something to be easily let slide aside. Learning
to respect other’s time is vital in order for others to respect ours. Every person has their own
other commitment to be fulfilled, thus being early in the meeting needed to be implemented into
practice. Moreover, every task given has its own due date. Getting the task done in time let you
to discover many other things in one day and not only that one particular task.

Last but not least, I also learned that QS's scope of works is not only limited into being a
consultant but also to be a contractor or developer. It may differ in certain area but most QS
regardless their field will be needed to provide the same services.

26

APPENDICES
TNB SUBSTATION

27

28

ROOFING SYSTEM

29

ROYAL INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - FORM 1 8 - Residential Buildings


A - 2 - 298
JOB TITLE : Cadangan membina dan menyiapkan 67 unit rumah teres dua tingkat beserta 1 CLIENT : Private
unit pencawang elektrik dan kerja-kerja infrastruktur berkaitan di atas sebahagian
Lot 360, Fasa G3B, Elmina, Seksyen U16, Shah Alam, Selangor Darul Ehsan

LOCATION : Shah Alam, Selangor Darul Ehsan TENDER DATE : 25th April 2016

INFORMATION TOTAL PROJECT


Project and Contract Information
Project Details and Site Condition : Contract :
Intermediate Lot (Type 'A' & Type 'A1') PAM form of Contract (With Quantities)

Market Conditions : COMPETITIVE


Contract particulars : Competitive Tender List
RM Int (JV)/L
Type of Contract : PAM form of Contract (With Quantities) Cost Fluctuation: Yes

Basis of Tender : No / 40,688,817.20


Bills of Quantities / Open / Selected /
Competition Government 44,043,000.00

Bills of Appr. Quant. Negotiated Private / 44,153,990.99

Provisional Sums RM 8,507.46 46,268,092.14


Schedule of rates / / Serials
Spec. & Drawings Prime Cost Sums RM 25,313.43

Contract Period Stipulated by Client: 18 Months Preliminaries RM 27,687.18

Contract Period Offered by Builders: 18 Months Contigencies RM -

Numbers of Tenders Issued : 10 Contract Sum RM 445,649.17

Numbers of Tenders Received : 5

ANALYSIS OF SINGLE BUILDING


Design/Shape Information
Accomodation and Design Features:
Residential building of double storey house comprises of 4 bedrooms, 5 toilets, living room, wet kitchen, dry kitchen, dining area, 2 stores,family area and car porch.

Areas :
Functional unit: 263 m² Design / Shapes
Lower Ground Floor - m² Percentage of Gross Floor Area
Ground floor 130 m²
Upper Floors 168 m² External Wall Area = 128 (a) Below Ground Floor -
%
Gross Floor Area 298 m² Gross Floor Area 298
(b) Single-Storey
50 %
Usable Area 263 m² = 0.43 Construction
Circulation Area 36 m²
Ancillary Area 0 m² (c) Two-storey
50 %
Internal Division 14 m² Storey Heights: Construction
Gross Floor Area 313 m²
Av. Below Ground Floor - m (d) 3-storey Construction
- %
Floor Spaces NOT Enclosed: 364 m²
At Ground Floor 3.60 m
Roof Area : 121 m² (e) 20-storey Construction
- %
(Structural and Plant Rooms) Above Ground Floor 3.50 m
(average)

Brief Cost
Contract sum RM 445,649.17 Functional Unit Costs :
excluding external works RM 1,461.05 per m2
Provisional Sums RM 8,507.46

Prime Cost Sums RM 25,313.43

Preliminaries RM 27,687.18 being 6.62 % of remainder

Contigencies RM - being 0.00 % Contract Sum

Contract Sum less Contingencies RM 445,649.17

REMARKS:
ROYAL INSTITUTION OF SURVEYORS MALAYSIA BUILDING
COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - Form 2


8 - Residential Buildings
A - 2 - 298
SUMMARY OF ELEMENT COSTS

Gross Floor Area : 298 m² TENDER DATE : 25th April 2016


Preliminaries Shown Separately
Total Cost Cost per m2 Element Element Element Reinforced Rein- Formwork
of Element GFA Unit unit rate Ratio per Concrete forcement
RM RM Quantity RM m2 GFA m3 kg m2
1. Substructure
1A Piling 25,913.67 86.84 522 m 49.64 0.02
1B Work Below Lowest Floor 21,698.21 72.71 130 m2 166.91 0.44
Finish

Group Element Total : 47,611.88 159.55 - - -

2 Superstructure
2A Frame 33,659.00 112.79 130 m2 258.92 0.44
2B Upper Floor 13,600.86 45.58 168 m2 80.78 0.56
2C Roof 45,465.30 152.36 364 m2 124.90 1.22
2D Stairs 4,740.32 15.89 - - - - - - -
2E External Wall 8,297.34 27.81 79 m2 104.95 0.26 - - -
2F Windows & External Doors 14,435.45 48.37 49 m2 296.90 0.16 - - -
2G Internal Walls & Partitions 19,888.89 66.65 475 m2 41.87 1.59 - - -
2H Internal Doors 20,203.68 67.70 27 m2 756.13 0.09 - - -
Group Element Total : 160,290.84 537.15

3. Finishes
3A Internal Wall Finishes 43,672.63 146.35 1,029 m² 42.44 0.14
3B Internal Floor Finishes 19,665.77 65.90 260 m² 75.64 0.25
3C Internal Ceiling Finishes 7,855.72 26.33 260 m² 30.21 0.10
3D External Finishes 13,916.71 46.64 0 m² - -

Group Element Total : 85,110.83 285.21


Tendered Sums
4. Fittings and Furnishing - - P.C.Sums Allowed (RM)
(RM)

5. Services
5A Sanitary Appliances 15,634.31 52.39 77 Nos 203.04 0.26
5B Plumbing Installation 18,978.83 63.60 - - -
5C Refuse Disposal - - - - -
5D Air-conditioning & Ventilation - - - -
-
System
5E Electrical Installation 28,635.52 95.96 - - -
5F Fire Protection Installation - - - -
5G Lift & Conveyor Installation - - - - -
5H Communication Installation - - - - -
Special Installation (Generator - - - -
5J -
Set System)
5K Builder's Profit & Attendance on - - - -
-
Services
5L Builder's Work in Connection - - -
-
With Services

Group Element Total : 63,248.66 211.95 - -

Sub-total excluding External Works, 356,262.21 1,193.87

6. External Works
6A Site Work 34,481.47 115.55 - - -
6B Drainage 15,849.76 53.11 - - -
6C External Services 8,255.12 27.66 - - -
6D Ancillary Buildings 3,113.43 10.43 - - -
6E Recreational Facilities - - - - -
Group Element Total : 61,699.78 206.76

Preliminaries 27,687.18 92.78

TOTAL ( less Contigencies ) 445,649.17 1,493.41


ROYAL INSTITUTION OF SURVEYOR MALAYSIA
BUILDING COST INFORMATION CENTRE
ELEMENTAL COST ANALYSIS - Form 3 8 - Residential Buildings
A - 2 - 298
BRIEF SPECIFICATION
GROSS FLOOR AREA : 298 m² TENDER DATE : 25th April 2016
ELEMENT SPECIFICATION
1 Substructure
1A Piling 175mm x 175mm reinforced precast concrete Grade 45 in 6m length initial pile and extension pile
1B Work Below Lowest Floor Finish Vibrated reinforced concrete Grade 25 to porch slab, ground slab, apron slab and beam

2 Superstructure
2A Frame Vibrated reinforced concrete Grade 25 to suspended floor beam, roof beam, upper roof
beam,parapet wall, kerb and column
2B Upper Floors Vibrated reinforced concrete Grade 25 to suspended floor slab.
2C Roof Reinforced concrete Grade 25 roof slab, ledge slab, water tank slab, plinth slab, gutter slab and
gutter wall.
2D Staircase Vibrated reinforced concrete Grade 25 to staircase, landing beam and landing slab.
2E External Walls Vibrated reinforced concrete Grade 25 to stiffener and hood.
2F Windows & External Doors 1200mm x 600mm and 600mm x 800mm Top hung window with frosted glass panel, 1800mm x
1500mm Framed window with clear float glass panel, 2400mm x 2100mm Framed casement with
fixed glass window, 600mm x 2100mm Top hung with fixed glass window, 3700mm x 2100mm
Framed sliding glass with fixed glass louvres ventilation panel with anti-vermin netting, 600mm x
2400mm and 3700mm x 2400mm Framed casement louvres grille panel.

2G Internal Walls & Partition 110mm thick half brick walls


2H Internal Doors 1200mm x 2400mm timber with laminated finish,, 900mm x 2400mm honeycomb core HDF door,
750mm x 2400mm and 750mm x 2100mm honeycomb HDF waterproof door panel, 900mm x
2100mm H.W. fixed timber louvres door, 900mm x 2450mm G.M.S. door frame and grille with
powder coated finish, 4643mm x 2400mm sliding door with clean float glass panel and 1150mm x
2400mm slide door system.
3 Finishes
3A Internal Wall finishes porcelain tiles and ICI-Dulux
3B Internal Floor Finishes mosaic strip matt finish porcelain tiles, porcelain tiles, waterproofing coating
3C Internal Ceiling Finishes Skim coat plaster, Boral unispan plaster board
3D External Finishes porcelain tiles, plasticiser, ICI-Dulux or alkali resisting sealer
4 Fittings and Furnishings - Not Applicable-
5 Services
5A Sanitary Appliances Closed-coupled washdown pedestal dual outlet water closet,closed-coupled washdown pedestal
water closet, semi-recessed square basin, zinc bottle trap, wall hung basin, semi-recessed toilet
roll holder, shower head, hand shower, shower trap, hand biddet, bip tap, paper holder, single
drainer kitchen sink, floor trap and mirror.
5B Plumbing Installation 174mm diameter circular gutter, 110mm diameter rainwater downpipe, 120mm x 80mm wide
rectangular rainwater downpipe, UPVC dome outlet with debris trap cover, UPVC gutter surfaces,
UPVC rainwater downpipe surfaces
5C Refuse disposal - Not Applicable-
5D Air-Conditioning & Ventilation - Not Applicable-
System
5E Electrical Installation - Not Applicable-
5F Fire Protection Installation - Not Applicable-
5G Lift & Conveyor Installation - Not Applicable-
5H Communication Installation - Not Applicable-
5J Special Installation - Not Applicable-
5K Builders's Profit & Attendance on - Not Applicable-
Services
5L Builders's Work in Connection With - Not Applicable-
Services

6 External Works
6A Site Works Site preparation and earthworks, Roadworks,PVC coated chain link fencing and gate, mild steel
sliding entrance gate, composite fence wall, split block gate posts and landscaping
6B Drainage half round precast concrete drain, drain sump, mild steel angle bracket plate, river washed pebble
laid and spread over on drain sump
6C External Services - Not Applicable-
6D Ancillary Building TNB Substation
6E Recreation Facilities - Not Applicable-
ROYAL INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - FORM 1 7 - Educational, Cultural, Scientific Buildings


A - 3 - 7707
JOB TITLE : Proposed construction and completion of the faculty of engineering Block B (FOE-B) CLIENT : PRIVATE
and centre of research and innovaion (CoRI) at DRB-HICOM, University of
Automotive Malaysia (DHUAM), Mukim Langgar, Daerah Pekan, Pahang Darul
Makmur for Messrs Glenmarie Development (Pahang) Sdn. Bhd.
LOCATION : Mukim Langgar, Daerah Pekan, Pahang Darul Makmur TENDER DATE : 15/12/2015

INFORMATION TOTAL PROJECT


Project and Contract Information
Project Details and Site Condition : Contract :
Proposed construction and completion of the faculty of engineering Block B (FOE-B) at DRB- PAM Contract 2006 -With Quantities
HITCOM, University of Automotive Malaysia (DHUAM)

The site is located at Daerah Pekan and overall site generally flat.
Market Conditions : COMPETITIVE
Contract particulars : Competitive Tender List
RM Int (JV)/L
Type of Contract : PAM Contract 2006 -With Quantities Cost Fluctuation: Yes

Basis of Tender : No /
Bills of Quantities / Open / Selected /
Competition Government

Bills of Appr. Quant. Negotiated Private /

Provisional Sums RM 5,954,000.00


Schedule of rates / / Serials
Spec. & Drawings Prime Cost Sums RM 1,405,000.00

Contract Period Stipulated by Client: 12 months Preliminaries RM 1,233,167.50

Contract Period Offered by Builders: 12months Contigencies RM -

Numbers of Tenders Issued : Contract Sum RM 35,500,000.00

Numbers of Tenders Received :

ANALYSIS OF SINGLE BUILDING


Design/Shape Information
Accomodation and Design Features:
Square building with one open entrance for user with enclosed wall.

Areas :
Functional unit: 852 m² Design / Shapes
Lower Ground Floor - m² Percentage of Gross Floor Area
Ground floor 4,820 m²
Upper Floors 2,887 m² External Wall Area = 1152 (a) Below Ground Floor -
%
Gross Floor Area 7707 m² Gross Floor Area 7707
(b) Single-Storey
0 %
Usable Area 6878 m² = 0.15 Construction
Circulation Area 597 m²
Ancillary Area 233 m² (c) Two-storey
- %
Internal Division 334 m² Storey Heights: Construction
Gross Floor Area 8041 m²
Av. Below Ground Floor - m (d) 3-storey Construction
100 %
Floor Spaces NOT Enclosed: 346 m²
At Ground Floor 4.70 m
Roof Area : 6649 m² (e) 20-storey Construction
- %
Above Ground Floor 3.70 m
(average)

Brief Cost
Contract sum RM 35,500,000.00 Functional Unit Costs :
excluding external works RM 22,660.04 per m2
Provisional Sums RM 5,954,000.00

Prime Cost Sums RM 1,405,000.00

Preliminaries RM 1,233,167.50 being 3.60 % of remainder

Contigencies RM - being 0.00 % Contract Sum

Contract Sum less Contingencies RM 35,500,000.00


ROYAL INSTITUTION OF SURVEYORS MALAYSIA BUILDING
COST INFORMATION CENTRE

ELEMENTAL COST ANALYSIS - Form 2


7 - Educational, Cultural, Scientific Buildings
A - 3 - 7700
SUMMARY OF ELEMENT COSTS

Gross Floor Area : 7,707 m² TENDER DATE : 15/12/2015


Preliminaries Shown Separately
Total Cost Cost per m2 Element Element Element Reinforced Rein- Formwork
of Element GFA Unit unit rate Ratio per Concrete forcement
RM RM Quantity RM m2 GFA m3 kg m2
1. Substructure
1A Piling - - 3,978 m2 - 0.52
1B Work Below Lowest Floor 997,780.40 129.46 5,154 m2 193.59 0.67
Finish

Group Element Total : 997,780.40 129.46 - - -

2 Superstructure
2A Frame 1,547,958.70 200.84 5,154 m2 300.34 0.67
2B Upper Floor 831,860.00 107.93 - m2 - -
2C Roof 1,954,971.70 253.65 176 m2 11,116.00 0.02
2D Stairs 75,976.80 9.86 - - - - - - -
2E External Wall 295,118.00 38.29 1,152 m2 256.18 0.15 - - -
2F Windows & External Doors 421,520.30 54.69 392 m2 1,075.20 0.05 - - -
2G Internal Walls & Partitions 391,613.60 50.81 1,110 m2 352.81 0.14 - - -
2H Internal Doors 534,118.70 69.30 11 m2 48,596.89 0.00 - - -

Group Element Total : 6,053,137.80 785.37 - - -

3. Finishes
3A Internal Wall Finishes 633,371.00 82.18 3,562 m² 177.81 0.02
3B Internal Floor Finishes 189,744.60 24.62 1,292 m² 146.86 0.02
3C Internal Ceiling Finishes 428,399.40 55.58 1,518 m² 282.21 0.04
3D External Finishes 223,942.10 29.06 - - -

Group Element Total : 1,475,457.10 191.43


Tendered Sums
4. Fittings and Furnishing - - P.C.Sums Allowed (RM)
(RM)

5. Services
5A Sanitary Appliances 218,521.70 28.35 275 Nos 794.62 0.04
5B Plumbing Installation 957,413.00 124.22 - - -
5C Refuse Disposal - - - - -
5D Air-conditioning & Ventilation 3,398,748.00 440.97 - -
-
System
5E Electrical Installation 3,422,706.90 444.08 - - -
5F Fire Protection Installation 1,285,864.30 166.84 - - -
5G Lift & Conveyor Installation - - - - -
5H Communication Installation - - - - -
Special Installation (Generator 263,560.20 34.20 - -
5J -
Set System)
5K Builder's Profit & Attendance on - - - -
-
Services
5L Builder's Work in Connection - - - -
-
With Services

Group Element Total : 9,546,814.10 1,238.66 - -

Sub-total excluding External Works, 18,073,189.40 2,344.91

6. External Works
6A Site Work 34,650.00 4.50 - - -
6B Drainage 1,261,555.64 163.68 - - -
6C External Services 1,353,003.50 175.55 - - -
6D Ancillary Buildings - - - - -
6E Recreational Facilities - - - - -
Group Element Total : 2,649,209.14 343.72

Preliminaries 1,233,167.50 160.00

TOTAL ( less Contigencies ) 21,955,566.04 2,848.64


ROYAL INSTITUTION OF SURVEYOR MALAYSIA
BUILDING COST INFORMATION CENTRE
ELEMENTAL COST ANALYSIS - Form 3 7 - Educational, Cultural, Scientific Buildings
A - 3 - 7700
BRIEF SPECIFICATION
GROSS FLOOR AREA : 7700 m² TENDER DATE : 15/12/2015
ELEMENT SPECIFICATION
1 Substructure
1A Piling - Not Applicable-

1B Work Below Lowest Floor Finish Reinforced concrete Grade 35, High tensilel reinforcement bar to BS 4483

2 Superstructure
2A Frame Reinforced concrete Grade 35, High tensile steel road and mild steel reinforcement to BS449
2B Upper Floors Reinforced concrete Grade 35
2C Roof Reinforced concrete Grade 35 roof slab,cmposite insulated metal roofing, metal sheet,
galvanised iron sheetmild steel to BS 449, glass panel skylight roofing, gutter
2D Staircase Reinforced concrete Grade 25 in staircase complete with mild steel handrailing and balustrading
2E External Walls Half brickwall in common clay bricks in gauged mortar (1:3), standard aluminium framed fix
louvres panel
2F Windows & External Doors 1800mm x 2000mm, 2700mm x 2000mm, 5400mm x 2000mm, 6200mm x 2000mm, 7200mm x
2000mm high composite casement window; 750mm x 2000mm, 1900mm x 1200mm fixed glass
window; 950mm x 600mm, 2800mm x 600mm, 4500mm x 600mm high top hung glass window
2G Internal Walls & Partition Reinforced concrete Grade 25
2H Internal Doors 900mm x 2100mm, 1800mm x 2100mm, 1650mm x 2100mm, 2550mm x 2100mm powder
coated aluminium door; 900mm x 2100mm and 1650mm x 2100mm , 1800mm x 2100mm,
2550mm x 2100mm, 1900mm x 2700mm solid timber swing door; 635mm x 2100mm, 1200mm
x 2100mm and 1800mm x 2100mm fire rated door; 3000mm x 4700mm electrical aluminium
roller shutter complete with ironmongeries
3 Finishes
3A Internal Wall finishes 19mm thick cement and sand, Wall tiles and alkali resisting primer

3B Internal Floor Finishes ceramic tiles, homogenous tiles, 'axel aquashield 100'
3C Internal Ceiling Finishes mineral fibre board, skim coat plaster, cement board
3D External Finishes 19mm thick cement and sand (1:6) mixed with an approved plasticiser, alkali resisting wall
sealer, weathershield paint
4 Fittings and Furnishings - Not Applicable-
5 Services
5A Sanitary Appliances Eudora' and 'Manchester' Dyna Wash water closet, 'Waterloo' squat water closet, Daytona floor
standing urinal bowl, counter top console basin, handicap basin, semji recessed paper holder,
semi recessed soap holder, water heater SL30 shower tap and shower head, elbowline basin
pillar tap, action pillar tap,1/2" angle valve lever handle set, floor trap, stainless steel Hairline
finishes grab bar, urinal panel
5B Plumbing Installation No. 20 Gauge galvanised iron sheet, unplasticised rigid polyvinyl (UPVC) pipework and fittings to
BS4576, Steel box gutter, mordant solution, metallic primer and alkyd resin
5C Refuse disposal - Not Applicable-
5D Air-Conditioning & Ventilation - Not Applicable-
System
5E Electrical Installation - Not Applicable-
5F Fire Protection Installation - Not Applicable-
5G Lift & Conveyor Installation - Not Applicable-
5H Communication Installation - Not Applicable-
5J Special Installation - Not Applicable-
5K Builders's Profit & Attendance on - Not Applicable-
Services
5L Builders's Work in Connection With - Not Applicable-
Services

6 External Works
6A Site Works Site preparation and earthworks, Roadworks, Fencing, Landscaping
6B Drainage Stormwater drainage systems, foul drainage system and water reticulation system which include
all the fittings and accessories.
6C External Services - Not Applicable-
6D Ancillary Building - Not Applicable-
6E Recreation Facilities - Not Applicable-

You might also like