Professional Documents
Culture Documents
Villa Accomplishment Report
Villa Accomplishment Report
1 EARTH WORKS
A. Excavation Works
A1 LABOR COST
a.) 3 Laborers
TOTAL FOR EARTH WORKS
2 CONCRETE WORKS
A. MATERIAL COST
a.) Portland Cement 46 bags 7,176.00 3,864.00
b.) Coarse Sand 3.1 cu.m 1,773.20 954.80
c.) Gravel 4.2 cu.m 2,948.40 1,587.60
d.) 16 mm Ø x 6m RSB
e.) 12 mm Ø x 6m RSB 36 pcs
f.) 10 mm Ø x 6m RSB 41 pcs 5,863.00 3,157.00
g.) #16 Tie Wire
h.) Hacksaw Blade
TOTAL FOR CONCRETE WORKS
3 MASONRY WORKS
A. MATERIAL COST
a.) 4" CHB
b.) Pozzolan Cement
c.) Coarse Sand
d.) 10 mm Ø x 6 m RSB
e.) # 16 Tie wire
f.) Hacksaw Blade
TOTAL FOR MASONRY WORKS
4 SCHEDULE DOORS & WINDOWS
A. MATERIAL COST
D-1(1.60mX2.10m)alum. Framed
a.) glass Panel, Sliding Door
100% 0% 100%
100% 0% 100%
- 100% -
27,324.00 6,614.07
Name of Project: PROPOSED GUIUAN RESORT
Owner : MARCOS TO DE JESUS RUBY PADULLON-QUILONO
Location SULANGAN GUIUAN, EASTERN SAMAR
Architect: ARCHT. RAMIL M. MATE, Uap
Statement of Work Accomplished: July18-23,2022
VILLA-2
NO. DESCRIPTION QTY UNIT MATERIAL
UNIT COST
1 EARTH WORKS
A. Excavation Works
A1 LABOR COST
a.) 3 Laborers
TOTAL FOR EARTH WORKS
2 CONCRETE WORKS
A. MATERIAL COST
a.) Portland Cement
b.) Coarse Sand
c.) Gravel
d.) 16 mm Ø x 6m RSB
e.) 12 mm Ø x 6m RSB
f.) 10 mm Ø x 6m RSB
g.) #16 Tie Wire
h.) Hacksaw Blade
TOTAL FOR CONCRETE WORKS
3 MASONRY WORKS
A. MATERIAL COST
a.) 4" CHB
b.) Pozzolan Cement
c.) Coarse Sand
d.) 10 mm Ø x 6 m RSB
e.) # 16 Tie wire
f.) Hacksaw Blade
TOTAL FOR MASONRY WORKS
4 SCHEDULE DOORS & WINDOWS
A. MATERIAL COST
D-1(1.60mX2.10m)alum. Framed
a.) glass Panel, Sliding Door
1 EARTH WORKS
A. Excavation Works
A1 LABOR COST
a.) 3 Laborers
TOTAL FOR EARTH WORKS
2 CONCRETE WORKS
A. MATERIAL COST
a.) Portland Cement 2 bags
b.) Coarse Sand 0.125 cu.m.
c.) Gravel 0.17 cu.m.
d.) 16 mm Ø x 6m RSB 12 pcs
e.) 12 mm Ø x 6m RSB
f.) 10 mm Ø x 6m RSB
g.) #16 Tie Wire
h.) Hacksaw Blade
TOTAL FOR CONCRETE WORKS
3 MASONRY WORKS
A. MATERIAL COST
a.) 4" CHB 44 pcs
b.) Pozzolan Cement 2 bags
c.) Coarse Sand 0.19 cu.m.
d.) 10 mm Ø x 6 m RSB
e.) # 16 Tie wire
f.) Hacksaw Blade
TOTAL FOR MASONRY WORKS
4 SCHEDULE DOORS & WINDOWS
A. MATERIAL COST
D-1(1.60mX2.10m)alum. Framed glass
a.) Panel, Sliding Door
100% 0% 100%
100% 0% 100% -
6,002.00 568.09
1,021.20 58.40