Risk Assessment: Act/Hse/Ra 001: Use The Risk Score Calculator To Determine The Level of Risk of Each Hazard

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane
Revision: 0

RISK SCORE CALCULATOR Project Name: xxx


Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls RA Ref No.: xxx
What w ould be the
CONSEQUENCE Frequent/Almost certain (5) Rarely (1) Can the hazard be Elim inated or removed
Continuous or will happen
Often (4) Likely (3) Possible (2) Less than once every 5 RA compilation
of an occurrence be? 6 to 12 times a year 1 to 5 times a year Once every 5 years from the w ork place? Review date:
frequently years Date:
Catastrophic (5) Can the product or process be substituted for Date:
High 25 High 20 High 15 Medium 10 Medium 5
Multiple Fatalities a less hazardous alternative?
Serious (4) Can the hazard be engineered aw ay w ith
High 20 High 16 High 12 Medium 8 Low 4 Compiled by:
Class 1 single fatality guards or barriers?
Moderate (3)
Can Adm inistration Controls be adopted
Class2 (AWI or LTI) or Class 1 High 15 High 12 Medium 9 Medium 6 Low 3 Reviewed by:
Permanently disabling effects
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work Medium 10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipm ent & Approved by:
restrictions. MTI Clothing be w orn to safe guard against
Insignificant (1) hazards?
FAI
Medium 10 Medium 4 Low 3 Low 2 Low 1

Overall Task Details Relevant Applicable MAS:


Additional Training required: NOC’s Required for task:
 01412 – Lifting Operations;
Lifting operations using Tower crane within site boundary
 00941 – Lifting equipment Riggers / Slingers As applicable

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR

i. Worker pedestrian routes to be designed and implemented with clear


 Collision with plant or vehicles and
signage to provide segregation;
live traffic;
Access of Tower crane  Plant and workers in ii. Instruction to workers at induction on use of access routes around the Workers not
 Workers struck by plant, very high 12
1 sections to work areas same working area 3 4 project; complying with Regular topic in TBT’s Low
risk of fatality; High
as delivery truck; flagmen
iii. Flagmen to be used to control crane movements;
 Uncontrolled crane reversing;
iv. The Logistics plan shall clearly illustrate crane access and egress points;

 Excavations;  See Risk Assessment 010 –


i. Crane foundations to be designed by approved persons, to clear design
 Use of plant – Excavations;
criteria;
excavators etc.; 20
2 Tower crane  See Risk Assessment 014 – use of 4 5 Low
foundations High ii. Foundations given adequate curing time before crane erection;
 Use of concrete; Mobile Concrete pump;
iii. Temporary Works Coordinator to control excavations and concrete pours;
 Temporary Works;  Failure due to incorrect design;

i. Ensure crane is erected to standards by trained competent erection


personnel;

 Fall from height; ii. No crane erection in adverse weather or high wind speed;

 Falling materials from height; iii. Concise erection Method Statement compiled and available in work area
for review;
 Use of untrained erectors;
iv. Area below works cleared and barriers implemented;
 Works at Height;  Erection in adverse weather; v. Solid barriers should be situated, where practicable, to protect erected
Siting, setting up and 12 crane from traffic routes; Failure of crash Crane quarantined until
3  Working in proximity  Collision with overhead services; 3 4
High detector
Low
testing of Tower crane to existing structures vi. Consideration given to overhead services and existing structures when repaired and tested
 Blocking access routes; siting tower crane;
and services;
 Load striking moving and/or
vii. All Tower cranes to be Third Party Certificated by a DM approved
stationary structures; inspector prior to use, documentation available on arrival to site;
 Use of untested crane;
viii. Load tests undertaken prior to use and available for review;
 Use of unqualified operator;
ix. Operators to have in-date Third Party certificate by approved body,
available for review;
x. Crane load indicator to be installed and functioning correctly;

Page 1 of 2 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane
Revision: 0

xi. Crash detectors installed and functioning correctly;

i. HLG Minimum Acceptable Standard HLG/OHS/MAS/00941 to be adhered


to at all times;
ii. Lift Plan to be completed prior to any lift taking place by crane supervisor
and engineer;
 Incident due to use of defective Machine
lifting gear / equipment; iii. Ensure all lifting tackle and equipment have valid test certificate before breakdown
 Operator competency use (6 monthly 3 rd party inspections); Machine isolated and
Lifting of equipment  Crane collapse due to lifting loads
and health; quarantined until repaired.
and material beyond SWL; 20 iv. Method statements and risk assessments to be submitted and adhered to
4 4 5 Low
 Lift planning; HIGH for technical and/or non-routine lifts; Hydraulic fluid spill
(Tower crane Operator)  No crane documentation in place; Spoil removed and treated as
v. Crane load indicator to be functioning correctly, and not to be overridden hazardous waste
 Tower crane operator collapse whilst under any circumstances;
in cab; Operator deemed
vi. Operator to adhere to crane safe working load limits , weight of load and Removed from operation
unfit to operate
COG established before lifting; crane
vii. Tower crane operator subject to regular health checks;

i. Lift controlled by designated trained rigger/banks man using approved


hand signals only;
 Persons underneath load struck by
ii. No personnel situated or walking under elevated loads, avoid over-
materials;
sailing of personnel if practicable;
 Load swinging / spinning
 Lifting operations iii. No over-sailing of loads over live traffic routes without road closure; Work stopped, area cleared
uncontrolled;
around workers; iv. No lifts undertaken when wind speed exceeds 40kph; Incident – falling and full investigation
Tower Crane  Falling materials; 20 materials undertaken
5  Workers in crane 4 5 v. No blind lifts without visual and communication aids, radios etc.; Low
supervision
operating radius;  Damage to lifting slings from sharp High
edges; vi. Tag lines shall be used to guide materials while lifting, 2 lines minimum
10m in length;
 Over-sailing of material over live
vii. Slings protected from sharp edges with rubber etc.;
traffic routes;
viii. Riggers to undertake visual inspection of all lifting equipment daily;
 High winds – adverse weather;
ix. Tower crane allowed to ‘weather vane’ in high winds;

i. Ensure crane is jumped or dismantled to standards by trained competent


 Fall from height; erection personnel;

 Falling materials from height; ii. No dismantling or jumping in adverse weather or high winds;
Jumping and  Works at Height; 20
Storage of Designated area established
6 dismantling of Tower  Use of untrained personnel; 4 5 iii. Concise Dismantling Method Statement compiled and available in work dismantled Low
High clear of access routes
Crane area for review; material
 Dismantling in adverse weather;
iv. Area below works cleared and barriers implemented during jumping or
dismantling;

Page 2 of 2 HSEQ -Rev-01(Aug-2018)

You might also like