Professional Documents
Culture Documents
Unit 10
Unit 10
10.1 INTRODUCTION
Project require a large number of persons during execution. The limitation of number
of subordinates that a person can effectively manage would have restricted the size of
an organisation if we were not able to group activities and people into departments.
Although, for a long time, there has been one pattern of grouping, considerable
developments have taken place in the manner of grouping people and activities and
arriving at an oganisation structure.
There is an increasing realization that organisations must be dynamic in nature and
should be able to restructure themselves to respond to changes in the environment.
Last few years have seen major organisational restructuring which has been lowly
dictated by increasing competition, rapid changes in technology, high cost of
marketing and changing consumer demands and expectations.
vi) Can easily cope with mass production activities to established specifications.
h) Disadvantages
iii) Co-ordination is complex and longer lead time required for decisions.
With the growth of project management activities, it was increasingly realized that
the traditional hierarchical organisational structure was inadequate.
67
Project Planning and Scheduling Activity 1
What is the critical role of appropriate organisation structure in effective management
of projects?
…………………………………………………………………………………………
…………………………………………………………………………………………
…………………………………………………………………………………………
68
a) Project Leader or Co-ordinator Project Costing and Financing
As a first step to resolve the problem, each department assigned somebody as a
project leader or co-ordinator for the project. It was a temporary assignment and the
oganisation structure was as shown in the above figure.
This mechanism proved quite effective for co-ordinating work within the department
with the exception of stray case of wrong choice of project leader Conflicts did arise
because many section managers were afraid that if they took direction from the
project leader it would be an admission by them that he was next in line of succession
to the department manger's job.
Besides when project leaders had to co-ordinate with other departments, conflicts
arose. Project leader of one department did not have the authority to lease with other
departments' personnel. Creation of these positions led to internal conflicts within the
departments and many individuals loathed the job of project leaders and wanted to
return to their safe jobs in the department. Where intra-department effort was
required, General Manager had no option but to act as the Project Manager.
b) Task Force Concept
Owing to problems with the framework of 'project leaders', it was felt that integration
of work of an individual project could be achieved if each department placed a
representative on the task force who would jointly solve the problems as they
occurred. Task force consisted both full time and part time personnel from each
department. Meetings were held every day to review the progress and to discuss
potential problem areas. Functional managers soon discovered that their nominees
were spending too much time in unproductive meetings than in performing their own
functional jobs. Many functional managers positioned unqualified and inexperienced
individuals on task forces. As a result, they became ineffective.
This concept was a major step for resolving conflicts and for integrating work and in
most case things improved. These could be formed very rapidly. However,
integration was rather complicated-work flow was difficult to control as functional
support was difficult to obtain as it was in the hands of functional managers. Also for
external projects, task force concept was grossly ineffective.
c) Liaison Department
Next step in the evolution process of integrating protect work was the induction of
liaison departments in project engineering organisations handling many projects at
the same time as shown in the following figure :
Project Managers served as a focal point - a centre for information and his main
function was to keep the General Manager informed of the status of the project and to
push papers and production people into completing activities on time. Project
Managers had the monitoring authority. However, work allocation and performance
appraisal reports of individuals on the projects continued to be made by the
functional departments who refused to take instructions from the project managers as
it would amount to admitting that they are in line of succession to the post of General
Manager.
e) Project Managers with Shared Authority
In this situation, project managers were given some authority vested in the General
Manager - they could assign work or prioritise duties in functional departments.
However functional managers still had the authority of performance appraisals and
enforcement of professional and organisational standards in the completion of the
activities:_ Individuals on the job were caught up in a web of conflicting
relationships which got aggravated as functional managers were forced to share their
authority with project managers. This could not last long because:
i) Shared responsibility led to major conflicts
ii) Functional managers were reluctant to give their authority to project managers
f) Project Managers with Line Authority
In large organisations, project managers were given all the staff on full time basis to
work exclusively for achieving the project goals. It operates like a division within a
division. This type of organisation can work as long as there is a continuous flow of
projects.As long as the work is stable, conflicts will be minimum. Project managers
not only assign work but also 'conduct performance appraisals and merit-reviews.
Each individual reports to one person only Communication channels are strong and
reaction time is very rapid.
The major disadvantage with this pure form of organization is the cost of such
organisation. There is no possibility of sharing individuals with other projects in
order to reduce costs. Personnel tend to stay longer than they are needed as project
managers know that once they released an employee, it will be almost impossible to
get him back. As each project nears completion, personnel become uneasy and try to
70 prove their worth. Although in such organisations, responses are fast and projects get
completed on schedule, technology suffers
owing to lack of strong functional support. The experience gained on one project may Project Costing and Financing
not be available to other projects and duplication of effort might ensue. Conflicts
occur with other similar project organisations whenever two projects use the same
piece of equipment of facility at the same time.
Each Project Manager derives his authority from the General Manager and represents
a profit centre. He has total responsibility for the project and is accountable for its
success. Functional Departments have responsibility to ensure technical and
professional standards on the project. Functional Managers ensure unified technical
expertise and complete exchange of information and experience on other projects.
Matrix management is a collaborative function and decision making rests with the
team instead of the project manager in a pure project organisation.
Since project managers do not have any formal authority they have. to resort to their
technical competence and their interpersonnel skills in order to be elective. Project
Manager acts as a unifying force for project control. He must maintain open channels
with the functional departments.
Individuals at the interface level have two bosses - he must take direction from both
project manager and functional manager The performance appraisal rests with the
functional manager who normally consults the project manager Even so there can be
conflicts but the individual at
71
Project Planning and Scheduling the interface can help by suggesting to both the managers to communicate with each
other and resolve the problem. This poses two kinds of challenges to the project
manager viz.,
i) How to motivate individuals working on the project - full or part time - so that
their loyalties are with the project?
ii) How to convince individuals to work to project directions when they might
conflict with department policy or if the individual feels his functional boss may
not regard these instructions favourably?
b) Rules for matrix Organisation Structure
i) if individuals spend more time on the project, it ensures loyalty
ii) Horizontal as well are vertical channels existing for making commitments.
iii) Conflict resolution should be quick and effective.
iv) Communication channels and access between managers must be good.
v) All managers must provide input for the detailed project planning.
vi) Both horizontally and vertically oriented managers must be willing to
negotiate for resources.
vii) Horizontal lines must be permitted to operate as a separate entity except for
administrative matters.
vi) Each person has a home where he returns after project completion. Each person
can be motivated showing him his career path.
vii) Strong technical base and problem solving capability can be developed and
expert knowledge is available to all projects.
viii) Key people can be shared and cost on projects can be minimised. Since people
work on a variety of jobs, it provides challenges and opportunities and
consequently higher, job satisfaction.
ix) Conflicts are minimal and can be solved easily and quickly.
x) We obtain better balance between time. cost and performance.
xi) Development of skills of specialists and generalists is rapid.
xii) Authority and responsibility are shared.
xiii) Stress is distributed among the team and functional managers.
73
Project Planning and Scheduling The above diagram shows that individual project managers report to General
Manager: This kind of Organisation works satisfactorily when the number of projects
is not large and organisation is quite small. As a result, General Manager has
sufficient time to co-ordinate activities of project managers.
(b) Large Organisation
When number of projects is large and companies grow in size, General Manages may
not he able to co-ordinate that many projects. In such events, a new position is
created - Chief Projects Manager or equivalent as shown in the figure :
74
10.11 ORGANISATION STRUCTURES IN TWENTY – FIRST Project Costing and Financing
CENTURY
Horizontal lines of matrix organisation structure are profit centres; consequently
project management would offer the best opportunity for training future managers
and executives to be cost conscious and profit-oriented. Owing to increasing
competition of global economy and rapid changes in technology and communication
network, there will be a shirt in favour of flat organisations by doing away with
several layers of functional managers. Project matrix structure is expected to
increasingly dominate the style of management in future. Project learns will be
responsible for the complete operations of existing products.
Increasing use of computers and information technology will further integrate
functional departments and 'smart terminals' will play major role in project control.
Top managers will be more directly involved in the control of total business
oganisations with the help of project managers who would span the middle level and
lead project teams to look after specific tasks of operational management.
Activity 2
Compare and contrast the matrix type of project organisation structure with the
traditional hierarchical structure where 'unity command' is the rule.
…………………………………………………………………………………………
…………………………………………………………………………………………
…………………………………………………………………………………………
10.12 SUMMARY
Involvement of large number of personnel for execution of' project heads to
systematic formulation of organisation. Over a period of time a number of
departmentalisation have emerged. Advantages and disadvantages of hierarchical
organisation are discussed. A typical matrix, called grid organisation structure is
shown and discussed with respect to project. Both complexities emphasized in this
unit. Owing to increasing competition of global economy and rapid changes in
technology and communication network, there will a shift in favour of flat
organisations by doing away with several layers of functional managers.