Professional Documents
Culture Documents
Method Statement For Formworks - Rev 01
Method Statement For Formworks - Rev 01
FORMWORKS
Document No.:01-070-01
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
TABLE OF CONTENTS
1.0 PURPOSE 03
2.0 SCOPE OF WORK 03
3.0 REFERENCES 03
4.0 PLANTS, EQUIPMENT AND MATERIALS 03
4.1 PLANT AND EQUIPMENTS 03
4.2 MATERIALS 03
5.0. SITE PLANNING AND PREPARATION 04
6.0 WORK PROCEDURE 04
6.1 PREPARATION 04
6.2 INSTALLATION 04
6.3 REMOVAL OF FORMS 05
6.4 SITE CLEAN-UP AND RESTORATION 06
6.5 SITE WELFARE 06
6.6 ORGANISATION, RESPONSIBILITY & SUPERVISION 06
6.7 WORK FORCE 07
7.0 HEALTH AND SAFETY 07
7.1. RISK ASSESSMENT 07
7.2 ENVIRONMENTAL SAFETY & HEALTH CONTRACTOR REQUIREMENTS 07
7.3. PROTECTIVE AND SAFETY EQUIPMENT 07
7.4. CONTRACTUAL REQUIREMENT 07
7.5. INFORMATION TO PERSONNEL 08
7.6. EMERGENCY PROCEDURE 08
7.7. PERMITS REQUIREMENT 08
8.0 ENVIRONMENTAL ISSUES 08
8.1. ENVIRONMENTAL IMPACT ASSESSMENT 08
9.0 QUALITY CONTROL 09
9.1. CONTRACTUAL REQUIREMENTS 09
9.2. CRITICAL WORKS 09
9.3. INSPECTION AND TESTING 09
9.4. REQUEST FOR INSPECTION (RFI) 09
9.5. FOLLOW UP AND EVALUATION 09
9.6 BEFORE CONCRETING 09
9.7 DURING AND AFTER CONCRETING 09
10.0 SAFETY ACTION PLAN 10
11.0 CONFIRMATION OF INSTRUCTIONS TO OPERATIVES 10
12.0 APPENDICES 10
1.0 PURPOSE
The intent of this document is to provide a complete Method Statement for the use of materials,
equipment, tools and plants; it includes the manpower and construction methodology in compliance
with RC requirements, drawings and technical specification with safety measures and quality control
2.0 SCOPE OF WORK
This method statement sets out requirements for the fabrication, erection and stripping of formwork for
concrete works. The scope of works is to provide guidance to prevent injury to persons engaged in
erecting and dismantling formwork and associated equipment as per RC Guideline and Specification
(RC GLS).
Refer Appendix-3 for the list of sites where we intend to use the formwork accordingly.
3.0 REFERENCES
The following documents has mainly been used as reference in the preparation of this Method
Statement
RC GLS SEC. 03105 CAST-IN-PLACE CONCRETE FORMS & ACCESSORIES (Rev 1)
APPROVED CONSTRUCTION EH&S PLAN (CODE-1)
6.2.1 All dimensions are related to finished concrete. Other details shall be in accordance with
the appropriate provisions of ACI 301 / ACI 318, using either 12mm or 18mm thick marine
plywood and ribbed with 2”x4” timber. Form frame shall have longitudinal ribs, and ribs
shall be free from deformities and defects to resist buckling effect when subjected to
enormous dead load of concrete.
6.2.2 Fix 25mm plastic chamfer strips to exposed exterior corners of the concrete structure or as
specified on the construction drawing.
6.2.3 Assemble and fix the forms to the correct position as marked by the Surveyor. Check the
dimension to conform to the required size and shape of the concrete member, subject to the
tolerances prescribed in the project specification.
6.2.4 Secure the forms to its position properly by using tie rods, clamps, or wood cleats or
combination of which that is suitable depending on site condition. Forms must be watertight
to prevent run-off of cement paste from the fresh concrete and to avoid honeycombs.
6.2.5 Wall forms shall be in layer of sectional units. The joints formed by the assembly of these
sectional units must be fitted well, aligned and secured properly.
6.2.6 In the case of overhead formworks, make sure that the scaffolding and other part of the
staging are properly fixed and have passed the safety requirements.
6.2.7 Provide bracings on sides of forms to prevent any movement or displacement. For overhead
formwork, bracings can be anchored on part of the scaffold found suitable.
6.2.8 Check verticality by attaching plumbs on the sides of the forms or by using spirit level.
6.2.9 Forms for rectangular and square shaped structures shall be maintained at right angle.
6.2.10 Mark the top of concrete elevation by fixing nail on two opposite sides inside the form and
on starter bars for wider areas of pouring.
6.2.11 Clean the inside forms. For deep forms, provide an opening at the bottom of the formworks
big enough for dirt, small wood pieces and other debris to pass through when air blown.
6.2.12 Deep formwork shall have a cut out / window opening at every 2.0 meter and side chutes or
provide extension to boom of concrete pump like flexible hose or funnel to eliminate higher
drop of concrete and concrete segregation.
6.2.13 Forms shall be free of noticeable wrinkles, warps, big patches, and other such defects.
Contact surface of forms shall be clean, and free of ruts and other roughness.
6.2.14 Determine the wind velocity during installation of wide and big pre-fabricated formworks
and stop when the wind speed dictates that it’s unsafe to do lifting works.
6.2.15 Water stops shall be polyvinyl chloride material and fixed at necessary locations based on
the approved drawings.
6.2.16 Water stops shall be made continuous by heat welding and corners also shall be mitered.
Water stops shall be nailed into forms, using wood strips if necessary.
6.4.1 Properly dispose the demolished materials. Demolished material shall not be allowed to
accumulate on site.
6.4.2 Remove and transport debris and rubbish in a manner that will prevent spillage on existing
canal adjacent to the working area.
6.4.3 Leave site clean, neat and order in good condition.
6.4.4 Remove all tools used, equipment and materials from the site upon completion of work.
6.4.5 Level site to required elevation and profile and clean the area.
6.4.6 Clean and repair damages caused by installation and construction activities used for
temporary works.
6.4.7 Restore existing and permanent facilities used during construction to original or better
condition.
Welfare facilities on site shall be provided like rest areas, toilet or washrooms, shaded area,
chilled water dispensing area, smoking area, prayer area.
6.6 ORGANISATION, RESPONSIBILITY & SUPERVISION
Construction Manager – will be the one to plan and coordinate all the activities in the site
and will be responsible for coordinating with all other departments as well.
Safety Personnel – will be the one to establish all necessary warning signs and barricades
establish the high risk areas in coordination with the Construction Manager and constantly
monitor the activity in terms of safety to all the workers. Furthermore he will give advice on
current and forecasted safety issues and concern.
Site Engineer - will be the one to implement the instruction of the Construction Manager in
the site, he will also directly supervise constantly the manpower and equipment working in
the area and implement all safety regulation and precaution set by the safety personnel.
Quality Control Inspector – Will be the one to inspect and monitor the area before
recommending to RC Engineer for inspection through RFI. (Request for inspection)
Safety Manager – Will be responsible for managing day to day activities and will identify
hazards, evaluate risks, advise safe and best practices for the safety of all personals.
Safety Officer – will report directly to safety manager, and will assist him to organise the site
as per RC approved procedures
Supervisor – will be the one to supervise and assign the works as per schedule.
9.7.1 Before the initial set of the concrete, the elevations, camber, and plumbness of formworks
systems should be checked, using total station or any other device or tool.
10.1 Saudi Withcon Co. Ltd., safety supervisor shall carry out the safety site inspections to
ensure that safety requirements laid out in the safe work plan are followed during and after
the concrete works. Safety Manager / Supervisor shall review the Safety Action Plan and
secure Work Permit if necessary prior to start of any activities.
10.2 Barricading “swing” areas of heavy equipment shall be checked before work begins.
10.3 Equipment, tools and materials inspection.
10.4 All equipment for concrete works shall have to be inspected by Saudi Withcon Co. Ltd.,
Safety Manager / Supervisor prior to use at site to ensure their safe worthiness at work.
10.5 Enough working spaces will be provided and the enter/exit access. Proper barricading and
safety signboards, emergency equipments introduced. Designated safety person shall
monitor and act throughout the whole work activity.
10.6 During concrete works, first the area shall be under safety work area for the whole duration
of the activity. All the precautionary measures shall be taken considering the probability of
emergency. In hospitalization cases, ambulance will be provided.
10.7 Emergency exit point, assembly area, emergency evacuation plan and emergency numbers
shall be posted on the boards
11.0 CONFIRMATION OF INSTRUCTIONS TO OPERATIVES
Those names listed below confirm receipt of the method statement and have had the contents explained to
them/understand it and are aware of the site ES&H requirements.
Note to contractor supervisor – Any significant change from this method statement requires it to be revised and resubmitted to OBI before
work can commence.
12.0 APPENDICES
APPENDIX—1 RISK ASSESSMENTS
APPENDIX—1A RISK ASSESSMENTS FOR WORKING AT HEIGHT, SCAFFOLDING ERECTION AND DISMANTLING
APPENDIX—1B RISK ASSESSMENTS FOR LIFTING OPERATION
APPENDIX—2 INSPECTION AND TEST PLAN (ITP’S)
APPENDIX—3 LIST OF SITES IN CONTRACT 560-S28 WHERE WE INTEND TO USE FORMWORK
APPENDIX—4 TYPICAL STRUCTURAL CALCULATION FOR FORMWORKS AND SUPPORTS (CODE-1 STATUS)
APPENDIX—5 560-S28 CONSTRUCTION EH&H PLAN FOR FORMWORK (PAGES-37-39, CODE-1 STATUS)