Dream organizer

3.1 Project Costing


Function-oriented software matrices use a measure of the functionality
delivered by the application as a normalization value. Since “Functionality cannot be
measures directly,it must be derived indirectly using other direct measures”. Albrecht, who
suggested a measure called the function point, first proposed function-oriented metrics.
Function point are derived using an empirical relationship based on countable (direct)
measure of software’s information domain and assessment of software complexity.
We have chosen Function Point Analysis for our Project Cost Estimation.
1. Number of external inputs: 5
2. Number of external outputs: 4
3. Number of external inquiries: 4
4. Number of internal logic files: 4
5. Number of external logic files: 2

External Inputs:
 Sign Up
 Sign In
 Invoice
 Business Profile
 Date of booking

External Outputs:
 Sign Up
 Sign In
 Invoice
 Show events list

Internal Logic File:


 List of Events
 Booking
 Notifications
 User profiles

External Inquires:
 List of Events
 Booking
 Notifications
 User profiles

External Interface Files:


 Dream organizer app interfaces
 Splash Screen

Department of IT, Govt. Graduate College for Women Satellite Town, Gujranwala
Dream organizer

Scale :

0- No Important
1- Incidental
2- Moderate
3- Average
4- Significant
5- Essential

3.1.1 Project Cost Estimation By Function Point Analysis

Type of Component Complexity of Components


Low Average High Total
External Inputs 0*5= 0 5*4= 20 0*6= 0 20

External Outputs 0*5= 0 4*5= 20 0*7= 0 20


External Inquiries 0*3= 0 4*4= 16 0*6= 0 16

Internal Logical Files 0*7= 0 0*10= 10 4*15= 0 60

External Interface 0*5= 0 0*7= 35 2*10= 0 20


Files
Total Number of Unadjusted Function Points: 136

Calculation of (Fi):

Sr.# Questions Scale


1 Does the system require heavy configuration? 4
2 Is communication required? 5
3 Are there distributed processing functions? 0
4 Is performance critical? 2

5 Will the system run in an existing, heavily utilized operational 4


environment?

Department of IT, Govt. Graduate College for Women Satellite Town, Gujranwala
Dream organizer

6 Does the system require online data entry? 0


7 Does the online data entry require the input transaction to be 0
built over operations?
8 Are the files updated online? 0

9 Are the inputs, output, files or inquiries complex? 2

10 Is the internal processing complex? 3

11 Is the code designed to be reusable? 4


12 Are conversion / installation included in the design? 2

13 Is the system designed for multiple installations in different 4


organizations?
14 Is the application designed to facilitate change? 5

Value Adjusted Factors (Fi) 35

Calculation of Function Point (FP):


𝐅𝐏𝐞𝐬𝐭𝐢𝐦𝐚𝐭𝐞𝐝 = Count Total * (0.65 + 0.01 * (Fi))
= 136* (0.65 + 0.01 * 35)
= 136* 1
=136
Final Function Point Calculation is:
Final Adjusted FP = UFC*VAF
=136*136
=18,496

Cost per Function Point:

Labor Rate =Rs. 42,000


Cost per FP =Labor Rate / Productivity parameter
= 42,000 / 10
= 4200
Total Project cost:
Total Project Cost = FPestimated * Cost Per FP

Department of IT, Govt. Graduate College for Women Satellite Town, Gujranwala
Dream organizer

= 18,496*4200
= 77,683,200
Total Estimated Effort:
Total Estimated Effort = FP est. / productivity parameter
= 136 / 10
= 13.6
Duration of Project
Duration of Project = Effort month / No. of persons
Duration of Project = 13.6 / 2
Duration of Project = 6.8 months.

Department of IT, Govt. Graduate College for Women Satellite Town, Gujranwala