Shade the most appropriate answer in the answer sheet Time 40 minutes
1. The Chlorine plus Fluorine content shall not exceed
a. 0.0025gm
b. 0.00ggm
c. 1% of the residue by weight
d. none of the above
2. What is the procedure requirements of this specification?
a. Procedure does not required to do PT
b. PT shall be performed in accordance with a procedure written as per the
guidance of this specification.
c. PT shall be performed in accordance with a procedure written based on the
technician’s experience.
d. PT shall be performed in accordance with a procedure written by the supplier.
3. Final interpretation shall be made within:
a. 7 minutes
b. 60 minutes
c. 7 to 60 minutes
d. any time
4. The minimum standard temperature limit is:
a. 50 degree F
b. 125 degree F
c. 50 degree C
d. 100 degree C
5. The reference documents used in this procedure are:
a. SE-165,SE-1209, SA-609 and SE-1219
b. SE-165,SE-1209, SE-1219 and SA-530
c. SE-165,SE-1209, SE-1219 and SE-1220
d. AWS-D1.1, ABS, API-1104
6. Excess water washable penetrant shall be removed a. with a water spray
b. with water spray at the pressure exceeding 50psi
c. with water spray and the pressure not exceeding 50psi
d. with a solvent
7. The Sulphur content shall not exceed
a. 0.0025gm
b. 0.00ggm
c. 1% of the residue by weight
d. none of the above
8. Non-aqueous developer application is accomplished by;
LIQUID PENETRANT TEST
Level-II Specific
b. post-emulsifying
c. solvent removable
d. all of the above
16. When color contrast and fluorescent examinations are required to be performed on a
specimen, which method should be done first?
a. First color contrast then fluorescent
b. First fluorescent then color contrast
c. any method can be performed first
d. none of the above
17. Non-aqueous developer application shall be applied only on a _______________
surface.
a. wet
b. dry
c. oily
d. dusted
18. The maximum standard temperature limit is:
a. 50 degree
b. 125 degree F
c. 50 degree C
d. 100 degree C
19. Aqueous developer application shall be applied only on a _______________ surface.
a. wet
b. dry
c. either wet or dry surface
d. oily
20. How much penetrant dwell time (minimum) should be given to detect lack of fusion
in aluminum weld.
a. 7 minutes
b. 5 minutes
c. 10 minutes
d. should be established experimentally.
LIQUID PENETRANT TEST
Level-II Specific