With reference to the trailing mail, we would like to bring to your notice that Tondiarpet Station

ES-02 GFC drawing No: DDC101-DD-STO-ST-DW-54039(A2) dt: 20/03/2019 was sent to M/s.NCCL.
With respect to the same, it is to be noted that due to non-availability of man power the Structural works
were started by Nov’2019 only. Further, you had indicated hindrance in Pump Room external wall and
proposed to change the design on 17/11/2019. In the proposal, no indication regarding this linking bridge
foundation was provided by M/s.NCCL.

Based on your proposal, M/s.SYSTRA had changed the design and sent the revised GFC
Drawing No: DDC101-DD-STO-ST-DW-54039(A3) dt: 25/11/2019. In spite of repeated instruction
provided by M/s.CMRL to you since Jan 2020 (before lock down) to complete the foundation of linking
bridge area, neither any labors were deployed nor were design hindrances indicated by M/s.NCCL.
During our Weekly Site visit had on 07/07/2020, this issue of foundation was raised and till date no action
against the same was taken.

We understand that the issues are are baseless and are raised purposely. Therefore, Further delays
w.r.t Design issues or any other issues shall not be accepted in Entry Structure-02 foundation and you are
instructed to start the works with immediate effect.