Site Technical Query

No. STQ
Discipline : 194/MDI-PP/STQ/VIII/2022
Title :
Project No. 2914
CJ6 on Clarifier Inner Channel Date:
Engineering
August 19th, 2022

Unit: Engineering Item: Structure Design Contractor: MDI-PP JV

Subject: Proposed to change CJ6 on Clarifier Inner Channel


Refer to contract drawing no. 83501430-01-240-C0002 for "Clarifier Section and Details", it is mantion that CJ6 should be apply on inner
channel between slab and wall. We propose to change CJ6 to CJ with assumption that inner channel is not an item that must be watertight.

Attachment □ YES □ NO Attachment :

Cost Impact □ YES □ NO Schedule Impact □ YES □ NO


CONTRACTOR (MDI PP JV)
Prepared by Approved by Approved by

Johannes A. S. - Coordination Manager Fajar Arifin - Project Manager Desiree Lihawa - Contractor Reperesentative
Date: Date: Date:
ENGINEER Description:

ENGINEER (CMC)
Checked by CMC CMC Comments :

Peter Vroege
Date: __________________

CLOSE OUT REQUIRED □ YES □ NO


CLOSE OUT – CONTRACTOR
Coordination Manager

Name
Signature
Date

Site Manager
Name
Signature
Date
Date
Work Item
Contract Option 1 Option 2 Option 3
Last wall casted 16-Aug-22 16-Aug-22 16-Aug-22 16-Aug-22

Inner channel complete casted 10-Sep-22 10-Sep-22 10-Sep-22 10-Sep-22


Slab grouting 11-Sep-22 30-Sep-22 30-Sep-22 30-Aug-22
Wall sealant application 13-Sep-22 30-Aug-22 30-Aug-22 30-Aug-22
Slab sealant application 9-Oct-22 7-Oct-22 7-Oct-22 6-Sep-22
Water tightness test started 16-Oct-22 13-Sep-22 13-Sep-22 13-Sep-22
Water tightness test finish 30-Oct-22 27-Sep-22 27-Sep-22 27-Sep-22
MEP installation 30-Nov-22 30-Nov-22 30-Nov-22 30-Nov-22
Pre-commissioning 15-Dec-22 15-Dec-22 15-Dec-22 15-Dec-22
Commissioning 30-Dec-22 30-Dec-22 30-Dec-22 30-Dec-22

Time Line
Work Item Contract
16-Aug 23-Aug 30-Aug 6-Sep 13-Sep 20-Sep
Last wall casted 16-Aug-22
Inner channel complete casted 10-Sep-22
Slab grouting 11-Sep-22
Wall sealant application 13-Sep-22
Slab sealant application 9-Oct-22
Water tightness test started 16-Oct-22

Water tightness test finish 30-Oct-22


MEP installation 30-Nov-22
Pre-commissioning 15-Dec-22

Commissioning 30-Dec-22