I Renovation of I Building
1 General Preliminaries
Site inspection, Site supervision, submission 2D & 3D drawings for client approval prior to proceeds any works and as - built
1.1 1.00 lot
drawing after the complettion of the projet.( Civil, MEP, FF, IT).
1.2 Mobilization and Demobilization including hauling and dumping of debris materials to the specified and approved dumping 1.00 lot
site outside the vicinity area.
1.3
Traffic Safety and Control
1.00 lot
Provision of safety requirements; 2 units of fire extinguisher ( Powder 6 kgs. ) safety barriers, safety lights, safety signages, etc.)
Demolition and Removal of existing facilities and all items that are not use as directed by the client whether it is under Civil,
2.1 1.00 lot
MEP, FF, IT and others.
2.2 Sandblasting of existing exterior and interior paint and repair / filling the cracks on the walls 1.00 lot
Supply and installation of fire resistant gypsum board suspended ceiling with cob design including aluminum runner and
2.3 required accessories
2.3.1 Fire resistant gypsum board ceiling for offices, lobby, commn areas, etc.. 1240.00 m2
2.3.2 Fire & moisture resistant gypsum ceiling board for toillet and pantry area 130.00 m2
2.4 Supply and installation of plastered CHB bock wall partition 1.00 lot
2.5 Supply and installation of double dry walls partition 1.00 lot
Supply and Installation of frosted and clear glass walls partition with complete accessories ( The contractor has to specify
2.6 1.00 lot
thickness of glass )
2.7 Supply and installation of doors ( The contractor has to specify the thickness of glass )
2.7.1 Supply and installation of frameless swing glass doors with complete accessories 45.00 units
2.7.2 Supply and installation of frameless sliding glass doors with complete accessories 3.00 units
2.7.4 Supply and Installation of heavy-duty aluminum main doors in all toilets including all required accessories; door closer, 4.00 units
hinges, lock, handle, stopper, etc…
2.7.5 Supply and Installation of heavy-duty aluminum cubicle doors in all toilets including all required accessories; hinges, lock,
10.00 units
handle, stopper, etc…
Supply and Installation of heavy-duty wooden door including all required accessories; hinges, lock, door closer, stopper, etc..
2.8 3.00 units
( with good varnish finish )
2.9 Supply and Installation fire rated metal door ( with good paint finish ) 1.00 unit
2.10 Supply and application of paint on exterior and interior walls, ceiling and all other required area. 1.00 lot
Supply and installation of unglazed floor tiles in all offices, hallways, reception, entrance, pantry, toilet, etc.. Including all
2.13 miscellaneous items. 1367.00 m2
2.14 Supply and installation of wall tiles in all toilet and pantry and all required accessories; adhesive, grout, tile trim, etc.. 1.00 lot
2.15 Supply and installation of granite riser and threads in the all exterior stairs. 1.00 lot
2.16 Supply and installation of granite lavatory counter for toilets 1.00 lot
2.17 Supply and installation of granite lavatory counter for pantry including under and over hang cabinet 1.00 lot
Note: the contractor has to submit design thickness and specification of glass for client approval prior to proceed any works.
3.1 Relocation of electrical main panel board including laying of cable and any other related works 1.00 lot
3.2 Complete electrical works; Rewiring, new location of switches, outlet, lighting fixtures and all other related works 1.00 lot
3.3 Supply and installation of water heater (50 liters capacity) 6.00 units
Note: the contractor has to submit electrical drawing for client approval prior to proceed any works.
Option 1 - Checking and utilize the existing centralized AC (the contractor has to repair, replace broken or damaged parts and
4.1 reconditioning of the existing centralized AC) if not feasible go for option 2 1.00 lot
4.2 Option 2 - Supply and Installation of split type AC ( all condenser must be on the roof ) ( Carrier or Zamil )
4.2.5 Supply and Installation of 1.5 tons ceiling mounted AC 2.00 units
5.1 Supply and installation of hot and cold water line including all fittings and accessories. ( CPVC schedule 80 ) 1.00 lot
5.2 Supply and installation of sanitary pipe including all fittings and accessories. ( UPVC schedule 40 ) 1.00 lot
Supply and installation of overhead fiberglass water tank including all pipe connection, fittings, accessories and all related
5.3 1.00 lot
materials to complete the works.
5.4 Supply and installation of new plumbing fixtures and all required accessories.
Complete checking, repair and recondition of existing fire fighting system and not limited to; Pump room or supply room, Fire
6.1 1.00 lot
hose reel cabinet, Sprinkler system, Fire alarm system, Fire hydrant, deluge system, etc..
Note: The contractor has the full responsibility for all firefighting system and it must be working and in good condition.
85,000.00 85,000.00
20,000.00 20,000.00
15,000.00 15,000.00
120,000.00
705,600.00
705600
297,600.00
297600
272,800.00
220
28,600.00
220
180,000.00
180000
36,800.00
36800
4,316,800.00
4316800
540,000.00
12000
48,000.00
16000
16,800.00
2800
14,400.00
3600
23,000.00
2300
10,500.00
3500
3,000.00
3000
1,512,000.00
1512000
32,000.00
32000
46,800.00
46800
341,750.00
250
107,800.00
107800
56,000.00
56000
30,000.00
30000
48,000.00
48000
36,000.00
36000
8,704,250.00
1,890,000.00 1,890,000.00
366,000.00
366,000.00
9,600.00
1,600.00
-
2,265,600.00
55,000.00
55,000.00
72,000.00
6000
71,500.00
5500
56,000.00
4000
78,000.00
13000
20,000.00
10000
352,500.00
56,000.00
56,000.00
12,000.00
12,000.00
24,000.00
24,000.00
16,200.00
1800
5,600.00
1400
12,000.00
1200
1,100.00
1100
4,000.00
2000
20,800.00
1600
6,400.00
3200
1,800.00
150
2,400.00
120
40,000.00
4000
9,600.00
800
9,000.00
900
6,600.00
550
18,000.00
1800
3,000.00
300
12,000.00
1500
260,500.00
145,000.00
145,000.00
145,000.00
-
220,000.00 220,000.00
11,847,850.00
1,777,177.50
13,625,027.50
Project:
Location:
Subject:
Date:
Item
1.1
1.2
1.3
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
2.16
2.17
2.18
3.1
3.2
3.3
4.1
4.2
5.1
5.2
5.3
5.4
6
6.1
7.1
SGP_ RDP_ Renovation of admin building
Dry Port Riyadh
Bill of Quantities
May 16, 2022
Description
Renovation of I Building
General Preliminaries
Site inspection, Site supervision, submission 2D & 3D drawings for client approval prior to proceeds any works and
drawing after the complettion of the projet.( Civil, MEP, FF, IT).
Mobilization and Demobilization including hauling and dumping of debris materials to the specified and approved
site outside the vicinity area.
Provision of safety requirements; 2 units of fire extinguisher ( Powder 6 kgs. ) safety barriers, safety lights, safety sig
Demolition and Removal of existing facilities and all items that are not use as directed by the client whether it is und
MEP, FF, IT and others.
Sandblasting of existing exterior and interior paint and repair / filling the cracks on the walls
Supply and installation of fire resistant gypsum board suspended ceiling with cob design including aluminum runn
required accessories
2.3.1 Fire resistant gypsum board ceiling for offices, lobby, commn areas, etc..
2.3.2 Fire & moisture resistant gypsum ceiling board for toillet and pantry area
Supply and Installation of frosted and clear glass walls partition with complete accessories ( The contractor has to sp
thickness of glass )
Supply and installation of doors ( The contractor has to specify the thickness of glass )
2.7.1 Supply and installation of frameless swing glass doors with complete accessories
2.7.2 Supply and installation of frameless sliding glass doors with complete accessories
2.7.3 ACS control door
2.7.4 Supply and Installation of heavy-duty aluminum main doors in all toilets including all required accessories; do
hinges, lock, handle, stopper, etc…
2.7.5 Supply and Installation of heavy-duty aluminum cubicle doors in all toilets including all required accessories;
handle, stopper, etc…
Supply and Installation of heavy-duty wooden door including all required accessories; hinges, lock, door closer, sto
( with good varnish finish )
Supply and Installation fire rated metal door ( with good paint finish )
Supply and application of paint on exterior and interior walls, ceiling and all other required area.
Supply and installation of unglazed floor tiles in all offices, hallways, reception, entrance, pantry, toilet, etc.. Includi
miscellaneous items.
Supply and installation of wall tiles in all toilet and pantry and all required accessories; adhesive, grout, tile trim, et
Supply and installation of granite riser and threads in the all exterior stairs.
Supply and installation of granite lavatory counter for pantry including under and over hang cabinet
Note: the contractor has to submit design thickness and specification of glass for client approval prior to proceed an
Sub - Total
Electrical Works
Relocation of electrical main panel board including laying of cable and any other related works
Complete electrical works; Rewiring, new location of switches, outlet, lighting fixtures and all other related works
Note: the contractor has to submit electrical drawing for client approval prior to proceed any works.
Option 1 - Checking and utilize the existing centralized AC (the contractor has to repair, replace broken or damaged
reconditioning of the existing centralized AC) if not feasible go for option 2
Option 2 - Supply and Installation of split type AC ( all condenser must be on the roof ) ( Carrier or Zamil )
Supply and installation of hot and cold water line including all fittings and accessories. ( CPVC schedule 80 )
Supply and installation of sanitary pipe including all fittings and accessories. ( UPVC schedule 40 )
Supply and installation of overhead fiberglass water tank including all pipe connection, fittings, accessories and all
materials to complete the works.
Supply and installation of new plumbing fixtures and all required accessories.
Complete checking, repair and recondition of existing fire fighting system and not limited to; Pump room or supply
hose reel cabinet, Sprinkler system, Fire alarm system, Fire hydrant, deluge system, etc..
Note: The contractor has the full responsibility for all firefighting system and it must be working and in good condit
Under IT department
Sub - Tot
Note : the contractor shall include in the pricing for all materials, labor, tools /equipment, etc.. and also the contracto
check the actual measurement and include all items not mentined in the BOQ but required in the project to complet
( The contractor has the full responsiblity for all the missing items with no cost )
15 % Value Added
120,000.00
1240.00 m2 272,800.00
220
130.00 m2 28,600.00
220
1.00 lot 180,000.00
180000
1.00 lot 36,800.00
36800
1.00 lot 4,316,800.00
4316800
8,704,250.00
2,265,600.00
145,000.00
1.00 N/A -
220,000.00 220,000.00
11,847,850.00
1,777,177.50
13,625,027.50
ProjecSGP_ RDP_ Renovation of admin building
LocatDry Port Riyadh
SubjecBill of Quantities
Date: May 16, 2022
I Renovation of I Building
1 General Preliminaries
Site inspection, Site supervision, submission 2D & 3D drawings for client approval prior to
1.1 proceeds any works and as - built drawing after the complettion of the projet.( Civil, MEP, 1.00 lot 35,000.00
FF, IT).
Mobilization and Demobilization including hauling and dumping of debris materials to the
1.2 1.00 lot 20,000.00
specified and approved dumping site outside the vicinity area.
1.3 Traffic Safety and Control
Provision of safety requirements; 2 units of fire extinguisher ( Powder 6 kgs. ) safety 1.00 lot 15,000.00
barriers, safety lights, safety signages, etc.)
Sub - Total General Preliminaries
2 Civil Works
Demolition and Removal of existing facilities and all items that are not use as directed by
2.1 1.00 lot
the client whether it is under Civil, MEP, FF, IT and others. 198450
2.2 Sandblasting of existing exterior and interior paint and repair / filling the cracks on the walls 1.00 lot 223200
Supply and installation of fire resistant gypsum board suspended ceiling with cob design
2.3
including aluminum runner and required accessories
2.3.1 Fire resistant gypsum board ceiling for offices, lobby, commn areas, etc.. 1240.00 m2 110
2.3.2 Fire & moisture resistant gypsum ceiling board for toillet and pantry area 130.00 m2 150
2.4 Supply and installation of plastered CHB bock wall partition 1.00 lot 150000
2.5 Supply and installation of double dry walls partition 1.00 lot 276000
Supply and Installation of frosted and clear glass walls partition with complete accessories
2.6 1.00 lot
( The contractor has to specify thickness of glass ) 2953600
2.7 Supply and installation of doors ( The contractor has to specify the thickness of glass )
2.7.1 Supply and installation of frameless swing glass doors with complete accessories 45.00 units 8000
2.7.2 Supply and installation of frameless sliding glass doors with complete accessories 3.00 units 14000
2.7.3 ACS control door 6.00 units 2000
2.7.4 Supply and Installation of heavy-duty aluminum main doors in all toilets including all
4.00 units
required accessories; door closer, hinges, lock, handle, stopper, etc… 2500
2.7.5 Supply and Installation of heavy-duty aluminum cubicle doors in all toilets including
10.00 units
all required accessories; hinges, lock, handle, stopper, etc… 1600
Supply and Installation of heavy-duty wooden door including all required accessories;
2.8 3.00 units 3000
hinges, lock, door closer, stopper, etc..( with good varnish finish )
2.9 Supply and Installation fire rated metal door ( with good paint finish ) 1.00 unit 3000
Supply and application of paint on exterior and interior walls, ceiling and all other required
2.10 1.00 lot 1134000
area.
2.11 Supply and installation of stainless railings 1.00 lot 24000
2.12 Supply and installation of fabric window blinds 1.00 lot 28800
Supply and installation of unglazed floor tiles in all offices, hallways, reception, entrance,
2.13 1367.00 m2
pantry, toilet, etc.. Including all miscellaneous items. 220
2.14 Supply and installation of wall tiles in all toilet and pantry and all required accessories; 1.00 lot 107800
adhesive, grout, tile trim, etc..
2.15 Supply and installation of granite riser and threads in the all exterior stairs. 1.00 lot 21000
2.16 Supply and installation of granite lavatory counter for toilets 1.00 lot 30000
Supply and installation of granite lavatory counter for pantry including under and over
2.17 1.00 lot 48000
hang cabinet
2.18 Supply and installation of information counter 1.00 lot 36000
Note: the contractor has to submit design thickness and specification of glass for client
approval prior to proceed any works.
Sub - Total Civil Works
3 Electrical Works
Relocation of electrical main panel board including laying of cable and any other related
3.1 1.00 lot 2,890,000.00
works
Complete electrical works; Rewiring, new location of switches, outlet, lighting fixtures and
3.2 1.00 lot 282,000.00
all other related works
3.3 Supply and installation of water heater (50 liters capacity) 6.00 units 1,600.00
Note: the contractor has to submit electrical drawing for client approval prior to proceed
any works.
Sub - Total Electrical Works
4 Mechanical works
Option 1 - Checking and utilize the existing centralized AC (the contractor has to repair,
4.1 replace broken or damaged parts and reconditioning of the existing centralized AC) if not 1.00 lot
feasible go for option 2 3,500.00
Option 2 - Supply and Installation of split type AC ( all condenser must be on the roof )
4.2
( Carrier or Zamil )
Note : the contractor shall include in the pricing for all materials, labor, tools /equipment, 1 130,000.00
etc.. and also the contractor must check the actual measurement and include all items not
mentined in the BOQ but required in the project to complete the works. ( The contractor has
the full responsiblity for all the missing items with no cost )
Total amount exclusive VAT
15 % Value Added Tax ( VAT )
Total project cost inclusive 15 % VAT
8
Total cost (SAR )
M2 RT M2 RT
35,000.00
35000 35000
20,000.00
20000 20000
15,000.00
15000 15000
70,000.00
70000
198,450.00
441 450 198450 198450 Precast wall
223,200.00 EXTR.744 300 223200 223200 INTR 5940
0
6,139,490.00 0
0
2,890,000.00 1 2890000 2890000 2890000
282,000.00 1 282000 282000 282000
9,600.00 6 1600 9600 9600
- 0
3,181,600.00 0
0
35,000.00
1 35000 35000 35000
0
60,000.00
12 5000 60000 60000
52,000.00
13 4000 52000 52000
49,000.00
14 3500 49000 49000
78,000.00
6 13000 78000 78000
20,000.00
2 10000 20000 20000
294,000.00 0
0
32,000.00 4 8000 32000 32000
12,000.00 4 3000 12000 12000
18,000.00
4 4500 18000 18000
0
16,200.00 9 1800 16200 16200
5,600.00 4 1400 5600 5600
12,000.00 10 1200 12000 12000
1,100.00 1 1100 1100 1100
4,000.00 2 2000 4000 4000
20,800.00 13 1600 20800 20800
6,400.00 2 3200 6400 6400
1,800.00 12 150 1800 1800
2,400.00 20 120 2400 2400
40,000.00 10 4000 40000 40000
9,600.00 12 800 9600 9600
9,000.00 10 900 9000 9000
6,600.00 12 550 6600 6600
18,000.00 10 1800 18000 18000
3,000.00 10 300 3000 3000
12,000.00 8 1500 12000 12000
230,500.00 0
0
122,000.00
1 122000 122000 122000
0
122,000.00 0
0
- 0
0
- 0 0
130,000.00
163000 163000
10,167,590.00 10200590
1,525,138.50
11,692,728.50
SGP_ RDP_ Renovation of admin building
Renovation of I Building
SN SPACE Area(m2
PRICE
4000
4544000
36 NEAR PANTFLOOR 36
216 WALL 216
252 252
ocation of switches, outlet, lighting fixtures and all other related works
tures and all required accessories.
of existing fire fighting system and not limited to; Pump room or supply room, Fire hose reel cabinet, Sprinkler system, Fire alarm system,
W SPLIT UNIT TYPE
ncluding laying of cable and any other related works x4 pannel
OUT SIDE PAINTarea INSIDE BUILDING PAINT
55X3X2 324 ROOMS AREA 5940
25X2X3 150 CORRIDOOR 360
1.5X55X2 165 260 6300
0.5X25X2 25
0.5X25X2 25
55X0.5X2 55
744 193440
kler system, Fire alarm system, Fire hydrant, deluge system, etc..