1 - Conceptual Cost Estimating - Part

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Conceptual Cost Estimating

Part (1)
Dr. Mohammad S. El-Mashaleh

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 1

Purpose of estimating

• The purpose of estimating is to


determine the forecast costs required to
complete a project in accordance with
contract plans and specifications

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 2

1
• Because construction estimates are prepared
before a project is constructed, the estimate
is, at best, an approximation of the actual
costs

• The true costs of the project will not be known


until the project has been completed and all
costs have been recorded

• Thus, the estimator does not establish the


cost of a project. Rather, he simply
establishes the amount of money the
contractor will receive for constructing the
project
Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 3

Types of estimates
• There are several estimates and re-
estimates for a project, based on the
stage of project development

• Estimates are performed throughout the


life of a project, beginning with the first
estimate and extending through the
various phases of design and into
construction
Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 4

2
• Laitinen (1998) indicates that each building
component is estimated, on average, seven
times during the course of a project

• Peurify and Oberlender (2002) show 4


estimates and re-estimates before
construction starts

Sponsor's Preliminary Detailed


Procurement Construction
study engineering engineering

Initial estimate Re-estimate Re-estimate Bid-estimate

Source: Peurify and Oberlender (2002, p. 4) Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 5

Sponsor's Preliminary Detailed


Procurement Construction
study engineering engineering

Initial estimate Re-estimate Re-estimate Bid-estimate

• Initial cost estimates form the basis to which


all future estimates are compared

• Future estimates are often expected to agree


with (i.e., be equal to or less than) the initial
estimates
Source: Peurify and Oberlender (2002, p. 4) Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 6

3
• Cost estimates can be divided into
two different types, depending on the
purposes for which they are prepared
and the amount of information known
when the estimates are prepared

• These are:
(1) Approximate estimates
(2) Detailed estimates

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 7

(1) Approximate estimates


• Also called: feasibility, screening,
authorization, preliminary, conceptual,
order-of-magnitude, equipment-
factored, or budget estimates

(2) Detailed estimates


• Also called: final, bid/tender, or
definitive

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 8

4
• Different organizations make use of
different “estimate” classifications

• Consider the following examples

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 9

Association for Advancement of Cost


Engineering (AACE) International Cost
Estimation Classifications
Estimate Level of End usage Expected
class project (Typical purpose accuracy
definition of estimate) range
Class 5 0% to 2% Concept screening -50% to +100%

Class 4 1% to 5% Study or feasibility -30% to +50%

Class 3 10% to 40% Budget, authorization, -20% to +30%


or control

Class 2 30% to 70% Control or bid/tender -15% to +20%

Class 1 50% to 100% Check estimate or -10% to +15%


bid/tender
Construction Project Management
Dept. of Civil Eng. Source: AACE (1997) Dr. Mohammad El-Mashaleh
Hashemite University 10

5
Construction Industry Institute (CII)
Cost Estimate Definitions

Estimate class Percent range Description/


methodology
Order-of-Magnitude ± (30 to 50%) Feasibility study – cost/capacity
curves
Factored Estimate ± (25 to 30%) Major equipment – factors applied
for costs

Control Estimate ± (10 to 15%) Quantities from mech/elect/civil


drawings
Detailed or definitive ±(<10%) Based on detailed drawings

Source: CII (1986)

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 11

Halpin (2006)
Estimate Level of project definition Expected
class accuracy range

Conceptual Prior to the commencement of ±10%


design
Preliminary Design 40% complete Not indicated

Engineer’s Design complete ±3%


estimate
*Bid estimate Design complete ±3%
(prepared by
GC)
* A rough rule of thumb states that the preparation of a bid estimate by the contractor will
cost 0.25%-1% of total bid price

Source: Halpin (2006, p.205) Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 12

6
Peurify and Oberlender (2002)
Conceptual Level of design Accuracy
estimate
level

Level I Little or no design -10 to +40%

Level II Completion of preliminary -5 to +25%


design
Level III Completion of final design -3 to +10%

Source: Peurify and Oberlender (2002, p.64-65) Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 13

Source: Merritt (1975) Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 14

7
Preparation of conceptual estimates

• The conceptual estimate is generally


prepared by the owner during the
owner’s feasibility study or by the
designer during the design phase

• It may be prepared by the contractor for


negotiated work between an owner and
a contractor

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 15

• Multi-builder owners are involved with the


construction of projects on a continual basis

• Examples on these owners: electrical utilities,


oil and gas firms, retail stores with nationwide
locations

• To initiate a project, these firms generally


conduct an owner’s study

• The owner’s study consists of a technical


feasibility study and an economic feasibility
study of the proposed project

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 16

8
• The economic feasibility study includes
a conceptual cost estimate for the
project

• Also, designers prepare conceptual cost


estimates throughout the design
process

• The estimate is used in the selection of


design alternatives and to keep the
owner informed of forecast costs
Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 17

• In negotiated contracts, the contractor may be


asked to prepare a conceptual cost estimate
for the project for which there are no, or
limited, plans and specifications

• Cost information from previous projects of


similar type and size is essential

• The estimator must combine all known


information with his personal experience and
use considerable judgment to prepare reliable
conceptual estimate

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 18

9
Sources for preparation of
conceptual cost estimates
• Usually derived from one of two
sources:

(1) Pricing manuals that are published


annually by several organizations

(2) Cost records from previous projects of


similar type and size
Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 19

(1) Pricing manuals

• For buildings, public works, and heavy


construction projects, the RS Means
Cost Guide is commonly used

• Also Walker’s building estimator


reference book is used in building
construction

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 20

10
• The Richardson’s manual for construction
estimating is a common reference for
petrochemical and processing projects

• These pricing manuals provide costs per unit


for various types of projects, such as cost per
square foot of building area for offices,
warehouses, and maintenance buildings

• These costs are derived from previous


projects that have been completed at
numerous geographic locations

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 21

Example from RS Means

• RS Means shows cost per SF for


different types of buildings

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 22

11
Source: R. S. Means (2000, p. 575) Construction Project Management
Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 23

• If size is different than the “typical” one,


then modify for size by using the cost
modifier curve

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 24

12
Example 1

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 25

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 26

13
• More detailed information from pricing manuals

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University Source: Oberlender (2000, p. 82) 27

Construction Project Management


Dept. of Civil Eng. Source: Oberlender (2000, p. 82) Dr. Mohammad El-Mashaleh
Hashemite University 28

14
(2) Cost records from previous
projects of similar type and size
• The best source of information for preparation
of conceptual cost estimates is the cost
records from previous projects

• Although the range of costs will vary among


projects, the estimator can develop unit costs
to forecast the cost of future projects

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 29

Several methods for determining


conceptual cost estimates
• Average
• Index value (inverse)
• Index value (root of products)
• Weighted average

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 30

15
Formulas

C1 + C2 + .... + Cn
Average =
n

n
Index Value (inverse) =
1 1 1
( ) + ( ) + ..... + ( )
C1 C2 Cn

1
Index Value (root of product) = (C1 × C2 × ...... × Cn ) n

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 31

CMin + 4CAvg + CMax


Weighted average =
6

CMin = minimum unit cost of previous projects


CAvg = average unit cost of previous projects
CMax = maximum unit cost of previous projects

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 32

16
Example 2

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 33

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 34

17
Example 3

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 35

Construction Project Management


Dept. of Civil Eng.
Dr. Mohammad El-Mashaleh
Hashemite University 36

18

You might also like