Professional Documents
Culture Documents
ASimulationProgramforLout outOperationUsingSelf propelledModularTransporters
ASimulationProgramforLout outOperationUsingSelf propelledModularTransporters
net/publication/337514744
CITATIONS READS
0 4,295
3 authors:
Dong Xu
Tianjin University
94 PUBLICATIONS 864 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Study on coupling mechanisms of vortex-induced vibration of flexible submarine pipelines and 3-dimensional local scour of sandy seabed View project
All content following this page was uploaded by Haiming Zhu on 17 May 2020.
OMAE2019-95673
1
Contact author: dzf@tju.edu.cn
Suspension compensations
When the working surface is uneven, the hydraulic system
of SPMTs will adjust the length of each suspension to adapt to it.
The length difference is usually called compensation. A positive
compensation indicates the suspension being extended, while the
value becomes negative when the suspension is compressed
Figure 7: The axle loads within a suspension group are equal. (Figure 10).
Where n is the number of axles in group D, while m is the number
of axles in group A. 𝑃𝑖 is the force that the i-th axle applied on
the surface underneath.
Wharf-ramps-deck surface
SPMTs drive through the wharf, ramps, and deck
successively. The surface formed by wharf, ramps, and deck is
referred to as “working surface” in the following paragraph. We
can define a function that measures the height at any position to
describe the working surface, as shown in Figure 9. Once the
trim, heel, draft and tide level are known, we can learn the height
and angle of the deck relative to the wharf. The slope of ramps
can be obtained as well based on the position of the stern. Figure 10: The compensations of suspensions.
Figure 12 shows the structure of the program. Users have The database is an indispensable part of the program. The
full control of SPMTs and vessel in the virtual load-out information of SPMT units, vessels, wharf layouts, and tide
environment. As discussed above, it is not necessary to take tables of ports are stored as presets under different categories.
hydrodynamic forces into consideration. Hence, the program can Users can also add new data to the database. It is convenient to
instantly finish the calculation, update the views and dashboard, input a set of information by picking a stored preset.
and give user real-time feedback on user’s interactions.
CASE STUDY
Figure 12: Structure of the program. In this section, we explain the load-out simulation of a
3,000-ton module in order to demonstrate how the program
For an upcoming load-out operation, engineers can drill in works.
the program beforehand. Firstly, engineers should input the
following information into the “Setting Panel” of the program: Table 1: Basic information about the module.
a. The assembly plan of SPMT units. As well as the Item Unit Value
suspension grouping plan. Wight t 3000
b. The selected vessel for the task. Length m 25
c. The initial ballast plan. Width m 25
d. The selected initial tide level. Height m 15
The program will pass the information into the analysis Limit Value of Compensation mm 250
procedure and update the views and dashboard after the Warning Value of Compensation mm 200
calculation cycle. Usually, the initial ballast plan and tide level
need to be adjusted several times until we gain a satisfied set-up.
Secondly, users can give instructions by pressing action
buttons in “Operation Control Panel” or “Right-click Menu”.
The action buttons are corresponding to the actions in analysis
procedure. They are listed below:
a. Move SPMTs in any direction for a certain step.
b. Ballast, de-ballast or transfer water between tanks.
c. Wait for the tide level to change for a certain time.
Each action will trigger a re-calculation and auto-update. The
feedback helps the users make the decisions of what action to be
taken. E.g., if the parameters in the dashboard are of good
condition, users can continue to move SPMTs onboard.
Otherwise, the other two actions are required.
In most cases, the module can be successfully transported
onboard after a few attempts. However, it is possible that the
load-out cannot be completed no matter how to operate. That Figure 14: Arrangement of the suspension groups.
means the set-up plan needs modification and the above process
has to be repeated. Table 2: Basic information about the vessel.
During the simulation, the time required of every action was Item Unit Value
added up. The overall time is an important parameter for load- Length (P.P.) m 108
out planning. Breadth m 28
The suspension compensations were monitored. There is an Depth m 7.28
option of turning on those indicators in Figure 13. The number Height m 15
under a wheel represents the compensation of the suspension. If Scanting draft m 5
a compensation goes beyond warning value, the color of the Design draft m 3.5
wheel turns blue. If the number exceeds the limit value, the color Pumping Capacity m3/h 1400
goes red. This will remind users to take necessary measures.
(a)
(b)
(d)
Figure 15: The process of the test simulation.
In the third step, we moved SPMTs until all the axle lines steps divided into three groups, which are “Set-up”,
are on deck (c). We had to take out a great volume of water since “Calculation”, and “Actions”. In “Set-up” group, the load-out
the loads on the deck increased dramatically. The tanks near stern set-up plan will be made. The “Actions” includes necessary
were completely de-ballasted and some water was taken out from operations. The “Calculation” contains the approach of solving
the bow as well to keep the deck even. mechanical problems based on the following theories:
Finally, we continued moving SPMTs until the module a. Axle loads can be calculated according to the principle of
reached the target area (d). In this step, the equivalent acting the hydraulic system.
point of loads moved to the bow. Therefore, we needed to b. The loads on the deck are determined by the position of
transfer water back to the stern. SPMTs.
It took 123 minutes for the entire process. This load-out c. Trim, heel, and draft of the vessel are related to the loads
plan may not be optimal and can be optimized in further on the deck and ballast condition. Ship hydrostatic theory
simulations. is applied.
d. Tide level must be considered when describing the
CONCLUSIONS wharf-ramps-deck surface.
This paper focused on the load-out of offshore structure e. Suspension compensations are considered as the safety
modules using SPMTs. We researched the load-out process and indicators and can be calculated since the volume of
established an analysis procedure. The procedure consists of hydraulic fluid is a constant.