ITEM DESCRIPTION QTY UNIT RATE AMOUNT TOTAL

BILL NR1
ELEMENT
CONCRETE WORKS (Mixing ratio1:3:6)
This section covers the following:
BEAMS 13 M3
SLAB 30 M3
STAIRS 3 M3

1 CARPENTRY

a 25X300mm formwork board for slab 247 nos 1,100 271,700.00


-
b 25X300mm formwork board for beams 153 nos 1,100 168,300.00
-
d 50x75mm formwork 300 nos 300 90,000.00
-
e bamboo for vertical support 450 nos 350 157,500.00
-
f nails 5" 4" 3" 2 1/2" 6 bags 7,000 42,000.00
-
g binding wire 1 bdle 9,000 9,000.00
-
g workmanship 330 m2 600 198,000.00

CONCRETE WORKS (Mixing ratio1:3:6)


CARPENTRY WORKS CARRIED TO SUMMARY 936,500.00 936,500
ITEM DESCRIPTION QTY UNIT RATE AMOUNT TOTAL
CONCRETE WORKS (Mixing ratio1:3:6)
CONTINUE

2 IRON BENDING

a 20mm 0.5 tons 215,000 107,500.00


-
b 16mm 3 tons 215,000 645,000.00
-
d 12mm 4.5 tons 215,000 967,500.00
-
e 10mm 1.5 tons 230,000 345,000.00
-
f 8mm 0.5 tons 230,000 115,000.00
-
g binding wire 4 bdle 9,000 36,000.00

g Workmanship 10 tons 20,000 200,000.00

IRON BENDING WORKS CARRIED TO SUMMARY 2,416,000.00 2,416,000.00

3 ELECTRICAL AND MECHANICAL (PIPING)

a Electrical piping item sum 100 50,000

b Mechanical piping item sum 10 10

g Workmanship item sum 50 50,000

ELECTRICAL AND MECHANICAL WORKS


CARRIED TO SUMMARY 100,010.00 100,010.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT TOTAL
CONCRETE WORKS (Mixing ratio1:3:6)
CONTINUE

4 BRICKLAYING

a Cement 150 bags 2,500 375,000.00


-
b Sand 60 tons 2,200 132,000.00
-
d Granite 80 tons 4,250 340,000.00
-
e Workmanship 43 m3 3,000 129,000.00

BRICKLAYING WORKS CARRIED TO SUMMARY 976,000.00 976,000.00

Total 4,428,510.00
SUPERVISION
0.1% of Grand total sum 0.1 % 4,428,510 442,851.00 442,851.00

BILL NR1
ELEMENT
CONCRETE WORKS (Mixing ratio1:3:6)
GRAND TOTAL CARRIED TO SUMMARY Grand Total 4,871,361.00