P1(B) Package MAHSR

PROJECT SUMMARY
Date:- 7/22/2022
GAD 1441
P-1
S.N. Structure Scope Today This Month Till Last Month Till Date Balance Remarks
1 Pile 5 0 5
2 Pile Cap PCC 1 0 1
3 Pile Cap 1 0 1
4 Pier Starter 1 0 1
5 Pier 1 0 1
6 Pier Cap 1 0 1

P-2
S.N. Structure Scope Today This Month Till Last Month Till Date Balance Remarks
1 Test Pile 1 0 1 0 0 Test Pile Head Completed
2 Reaction Pile 4 4 0 0 Reaction Pile No.01,02 Head Completed
3 Pile 9 9
4 Pile Cap PCC 1 1
5 Pile Cap 1 1
6 Pier Starter 1 1
7 Pier 1 1
8 Pier Cap 1 1

P-3
S.N. Structure Scope Today This Month Till Last Month Till Date Balance Remarks
1 Pile 9 9
2 Pile Cap PCC 1 1
3 Pile Cap 1 1
4 Pier Starter 1 1
5 Pier 1 1
6 Pier Cap 1 1

P-4
S.N. Structure Scope Today This Month Till Last Month Till Date Balance Remarks
1 Pile 9 9
2 Pile Cap PCC 1 1
3 Pile Cap 1 1
4 Pier Starter 1 1
5 Pier 1 1
6 Pier Cap 1 1

P-5
S.N. Structure Scope Today This Month Till Last Month Till Date Balance Remarks
1 Pile 5 5
2 Pile Cap PCC 1 1
3 Pile Cap 1 1
4 Pier Starter 1 1
5 Pier 1 1
6 Pier Cap 1 1

LABOUR REPORT
DAY SHIFT LABOURS NUMBERS NIGHT SHIFT NUMBERS
LABOURS
LABOUR CATOGERIES SKILL UNSKILL LABOUR CATOGERIES SKILL UNSKILL
8 17 NIL

TOTAL LABOURS 8 17 TOTAL LABOURS 0 0


TOTAL LABOURS 25

Activities details Machineries & Materials


Reaction Pile (No.4) Shutering Fixing Works is in Progress 1 Piling Rig 0
Reaction Pile (No.3) Reinforcement Fixing & Binding Works is in Progress 2 Polymer Tank 0
3 JCB 1
4 Crane 1
5 Pile Cap Shutter 0
6 Pier Shutter 0
7 Pier Cap Shutter 0