Professional Documents
Culture Documents
AnnisaS2 MDY OptimizingCommissioningSchedulingEPCCIndustryProjectsby
AnnisaS2 MDY OptimizingCommissioningSchedulingEPCCIndustryProjectsby
AnnisaS2 MDY OptimizingCommissioningSchedulingEPCCIndustryProjectsby
net/publication/341979695
CITATION READS
1 2,008
3 authors:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Perancangan Peta Jalan Pengembangunan Industri Hasil Pertanian pada Wilayah Kabupaten dengan Metode VRISA dan Rantai Nilai View project
All content following this page was uploaded by Muhammad Dachyar on 06 June 2020.
Abstract
Engineering Procurement Construction Commissioning (EPCC) project has a trial/testing
phase to achieve the performance guarantee required in the contract before the plant handed
over to the operator. This project has enormous challenges, such as overlapping phases and
interdependencies between activities, very accurate details of activities, and uncertainties in the
accuracy of predictions that arise during the project. Many EPCC project scheduling is not
aligned with commissioning schedule. Therefore, time and resource arrangements are an
important factor in the successful completion of plant commissioning. This paper aims to
minimize commissioning delays by increasing commissioning scheduling in gas processing
industry plant projects using the Analytical Hierarchy Process (AHP) and Critical Path Method
(CPM). AHP method produces a commissioning system priorities, then used in CPM scheduling.
The results showed a short duration commissioning schedule, because of some parallel activities
between pre-commissioning and construction. The duration of completion commissioning time
reduces from 309 days to 293 days.
1. Introduction
A large sustainable development is carried out both in the infrastructure and industrial
sectors to create a construction industry that can compete globally. A significant difference
between ordinary construction projects and EPCC projects is in the commissioning phase
that is carried out after construction in industrial construction projects. The success of
EPCC project is influenced by the success of commissioning and performance tests.
Commissioning has been described as the most critical of all stages of EPCC project. The
commissioning process mainly focuses on adjustments and testing. As such,
commissioning is the process in which most failures are detected [1].
Commissioning is quality processes used in construction buildings to verify that the
project has completed the design, construction, and operation and maint enance
requirements of the owner [2], [3].
The phase sequence of EPCC project is:
1. Engineering Phase
Engineering is a detailed system-based planning and design process that focuses on
operational and maintenance effectiveness [4].
2. Procurement Phase
The procurement of equipment and services in the project starts from the purchase
planning process, vendor selection, bid evaluation, vendor determination, until
contracts with selected vendors [4].
3. Construction Phase
The stage of construction or installation of buildings or equipment following the
specifications and materials specified at the engineering stage [2], [4].
2. Methods
In this study the methodology used consists of data collection, data processing and
comparison of research results. Data obtained from some literature, surveys of experts,
and. Data is processed by integrating AHP and CPM methods, respectively.
This study was designed with commissioning as the goal and utilities system as the criterion.
All data from research is entered into Super Decision software to calculate the weight of each
criterion.
Fuel Gas System Drain System in Hot Oil System in Chemical Injection
Nitrogen in service
in service service service System in service
Gas processing plant process flow is using the method of separating the hydrocarbon gas from
the well to become sales gas that will be distributed to other plants. Hydrocarbon gas from the
Arung well is put into a separator to separate the gas and liquid phases, then the gas is continued
to the Acid Gas Removal Pre-treatment system and the Acid Gas Removal Unit to remove
hydrogen sulfide gas. The clean gas is called sweet gas or sales gas which is the product of this
plant. Figure 4 shows commissioning sequence for the process system.
PROCESS SYSTEM
Acid Gas Disposal System in
service
Gas Metering
Wellhead System in Separation System in
AGRU System in service System in
service service
service
Liquid Metering
Liquid Handling System
System in
in service
service
Based on duration basis in table 2, it could be calculate actual duration for each activity in
every system by considering work volume. For instance, in Liquid Metering System has 25 lines
of piping, the duration for flushing/blowing activity is 4 days.
Table 4. Comparison of Project Duration and Completion Times for The Three
Scenarios
Total Duration
Scenario Start Date Finish Date Remarks
(days)
Pre-commissioning activities
are carried out after
A 280 14-Jul-21 4-Jun-22
construction is complete (in
series)
Pre-commissioning activities
are carried out in conjuction
B 309 14-Apr-21 8-Apr-22
with construction (area
oriented)
Pre-commissioning activities
are carried out in conjuction
C 293 14-Apr-21 21-Mar-22
with construction (system
oriented)
4. Conclusion
Commissioning scheduling of gas processing plant in this study was performed by using AHP
and CPM method. The AHP method is used to determine the priority of the commissioning
system sequence. The CPM method is used to develop a commissioning schedule. In this study,
three scenarios were simulated with different scheduling scenario conditions. The optimum
conditions produced to obtain the fastest duration and completion time are scenario C which
means that pre-commissioning activities are carried out simultaneously with construction work
and system-oriented. Scenario C produced 293 days duration. It can reduce the duration from 309
days to 293 days.
References
[1] S. Poeschl, F. Wirth, and T. Bauernhansl, “Strategic process planning for commissioning processes in mechanical
engineering,” Int. J. Prod. Res., vol. 7543, 2018, doi: 10.1080/00207543.2018.1556408.
[2] M. E. Brito, R. de O. A. Lopes, L. Rocha, and E. L. Qualharini, “Beyond Buildability: Operability and
Commissioning of Industrial Facilities,” Procedia - Soc. Behav. Sci., vol. 226, no. October 2015, pp. 67–74, 2016,
doi: 10.1016/j.sbspro.2016.06.163.
[3] W. L. Gillis and E. A. Cudney, “A Standard for the Commissioning Process,” Front. Eng. Manag., vol. 2, no. 1, p.
39, 2015, doi: 10.15302/j-fem-2015006.
[4] M. Dachyar and Z. A. H. Sanjiwo, “Business Process Re-Engineering of Engineering Procurement Construction
(EPC) Project in Oil and Gas Industry in Indonesia,” Indian J. Sci. Technol., vol. 11, no. 9, pp. 1–8, 2018, doi:
10.17485/ijst/2018/v11i9/92741.
[5] J. T. O’Connor and B. D. Mock, “Construction, Commissioning, and Startup Execution: Problematic Activities
on Capital Projects,” J. Constr. Eng. Manag., vol. 145, no. 4, p. 04019009, 2019, doi: 10.1061/(asce)co.1943-
7862.0001621.
[6] B. Mock and J. T. O’Connor, “Owner and contractor solution strategies for industrial commissioning,” Constr.
Innov., vol. 19, no. 2, pp. 256–279, 2019, doi: 10.1108/CI-09-2018-0079.
[7] W. L. Gillis and E. A. Cudney, “A methodology for applying quality function deployment to the commissioning
process,” EMJ - Eng. Manag. J., vol. 27, no. 4, pp. 177–187, 2015, doi: 10.1080/10429247.2015.1098174.
[8] C. Lakshmi Tulasi and A. Ramakrishna Rao, “Resource allocation in project scheduling application of AHP,” Int.
J. Appl. Eng. Res., vol. 10, no. 8, pp. 20403–20414, 2015.
[9] T. Saaty and L. Vargas, “Models, methods, concepts & applications of the analytic hierarchy process,” … -Driven
Demand Oper. Manag. Model., vol. 175, pp. 1–20, 2012, doi: 10.1007/978-1-4614-3597-6.
[10] M. Dachyar and U. D. Saputra, “COMPARISON BETWEEN CRITICAL CHAIN AND CRITICAL PATH
METHOD IN TELECOMMUNICATION TOWER CONSTRUCTION PROJECT MANAGEMENT,” no.
August, pp. 3–6, 2009.