Professional Documents
Culture Documents
E D P E Barrick G M Inc.: Lectronic Etonator Erformance Valuation Oldstrike Ines
E D P E Barrick G M Inc.: Lectronic Etonator Erformance Valuation Oldstrike Ines
PERFORMANCE EVALUATION
Abstract
In March of 2001, Barrick Goldstrike became the first surface gold operation in North
America to evaluate the advantages of electronic detonators. A detailed study was
conducted to quantify the benefits of the use of electronic detonators to the downstream
excavation, crushing and ore processing operations. The following methods were used
to quantify blast performance:
The rock fragmentation produced by the use of the electronic detonators was quantified
using digital image analysis. Ninety percent of the blast fragmentation produced by the
use of the electronic detonators was less than 4 inches (a reduction of over 44 percent
over a similar blast with pyrotechnic detonators). One benefit of this decrease was
reflected by the improved performance of the excavator.
One of the main advantages of the electronic detonators is the wide range of available
delay times. With this flexibility, the ore blasts can be designed to limit dilution by
separating the various ore types into distinct piles. A test blast was conducted that
successfully proved this concept.
The initial findings of this study indicated that the use of electronic delays benefited the
excavation, hauling and crushing operations at Barrick’s Goldstrike operation. Ongoing
studies are defining the advantages of the use of electronic delays in terms of increased
productivity and efficiency of the ore recovery operations.
Careful records were maintained of the loading and stemming of each blast. The blast
detonation sequence was recorded using:
l Two high-speed 16mm film cameras (500 fps)
l One high-speed video (1000 fps)
l Three digital video cameras
l One digital seismograph
This paper includes the data recorded during the study, the procedures used to compare
the performance of electronic delays to standard pyrotechnical delays as well as the
conclusions drawn from the analysis of the data.
DETONATORAPPLICATION
The flexibility provided by the electronic detonators allows the blast designer to develop
timing configurations that are not possible with pyrotechnic delays. A geology specific
detonation sequence was determined the day before the blast taking into account
fragmentation and ore dilution considerations. This plan was transferred to a delay
configuration diagram for use in the field.
At Barrick’s Goldstrike operation detonators are not placed in the blastholes due to
potential hazards in hot holes. Before loading begins, the temperature of each hole is
checked. A polyethylene liner is placed in hot holes to separate the explosives fkom the
wall of the blasthole. The blastholes are primed with cast boosters tied onto 18 grain
detonating cord. An inhibited emulsion blend product is typically used in all the
blastholes to slow the exothermic reaction between the sulfides and the ammonium
nitrate. Once the blastholes are loaded the electronic detonators are connected to the
detonating cord downlines using a field block connector as shown in figure 2.
After connecting the caps to the cord the tiring times are encoded into each cap according
to the predetermined design using a hand held programming unit as shown in figure 3.
After the caps are programmed they are hooked to a ‘bus line” using special connectors
At this point the blasting machine performs a check of all the detonators to make sure that
they are tied-in and functioning properly. When the shot is ready to be fired the blasting
machine rechecks the detonators and then initiates the blast.
The transition from pyrotechnic to electronic detonators was relatively easy for the blast
crew. It should be noted that after one day of training the blast crew was able to tie-in
and program the blast with limited supervision.
FIELD EVALUATIONS
Full-scale blast evaluations were conducted to determine the effect that the use of
electronic detonators had on fragmentation, ore dilution, excavator productivity,
vibration control and mill throughput. Each of the tests is covered in detail in the
sections that follow.
FRAGMENTATION
CONSIDERATIONS
The post-blast fragmentation of the rockmass directly influences the productivity of
excavation, crushing and milling operations. In some cases, the overall recovery
efficiency can be reduced by improper size distribution.
The obvious question is: Will the additional cost of the use of electronic detonators be
offset by increases in productivity and/or efficiency downstream?
The blast was designed to pull the ore toward the middle of the blast with a “Vl”
configuration. Images taken around 290ms after detonation and after the blast are shown
in figure 8.
The fragmentation produced by the test and conventional blasts was quantified with the
use of WipFrag image analysis techniques. A total of 75 digital images were taken of
various parts of the muckpile that was produced with the use of electronic detonators.
Image scaling rods were placed in the foreground and background of the images to
provide accurate size evaluation. A typical digital fragmentation image is shown in figure
9.
The cumulative blast fragmentation data describes the fragmentation in terms of the
screen size that various percentages of the material will pass through. This cumulative
data is shown in the table 2.
The standard pyrotechnic blast produced a P90 of 7.07 inches. Ninety percent of the
material in the electronic blast was less than 4 inches in diameter, 44 percent smaller than
the pyrotechnic blast. The complete fragmentation distribution curves are shown in
figures 10,11,12 ,and 13.
The electronically delayed blast produced a mean fragmentation size that was 18 percent
less (3.67 to 4.47 inches) than the pyrotechnically delayed blast. WipFrag calculated the
mode (most common fragment size) of the pyrotechnic blast to be 71 percent larger than
the mode of the electronic blast (5.98 to 3.50 inches).
It should be noted that this fragmentation data is based on only two blasts. However, the
results are encouraging enough to warrant further evaluation. Future tests will be
conducted to determine the influence of increased fragmentation on all downstream
processes.
EXCAVATORPRODUCTIVITY
CONSIDERATIONS
Blast fragmentation is one of the key factors that controls the productivity and operating
cost of excavation equipment. In addition, the efficiency of the haulage fleet is also
influenced indirectly by “diggability” of the muckpile. During the detonator analysis, an
O&K RH 200 hydraulic excavator was used to excavate the blasts. The truck fleet
consisted primarily of Komatsu 930E haul trucks with an average load of 330 tons.
The electronic delays add approximately 6.5% per ton to the drilling and blasting costs.
If the total excavation and haulage costs can be reduced by more than 6.5 percent, the
resultant savings will offset the additional cost of the detonators.
EXCAVATORPRODUCTIVITYTESTSETUP
A video camera was used to record the productivity of the excavator in the electronic and
pyrotechnic blasts. The videos were then analyzed using the ProDig shovel analysis
software.
The truck loading time for the electronic blast was 18 percent less than the pyrotechnic
blast. However, some of this advantage was not dig related (operational delays etc.). A
better indicator of the diggability of the two blasts was shown by the “pure productivity”
rate (tons per hour). This rate is based on the time interval between when the first bucket
is dumped into the truck until the truck is released. The electronic blast produced a pure
productivity rate that was approximately 11 percent greater than the pyrotechnic blast.
It appears from this analysis that all elements of the pyrotechnic blast’s excavation cycles
were slower. This could indicate that the pyrotechnic blast’s operator was not as skilled
or that the excavator was not running as well. However, hard digging was noted during
the analysis of several loading cycles in the pyrotechnic blast.
The average electronic blast dig cycle was 4 percent less than the average pyrotechnic
blast dig cycle. It should be noted that this analysis does not take into account how full
the bucket was. In fact, up to nine buckets (instead of 5 to 6) were required to load one of
the trucks from the pyrotechnic blast. These partially tilled buckets took less time to till.
It was also noted that the dig cycle trend over time was more consistent during the
excavation of the electronic blast
DILUTION CONTROL
CONSIDERATIONS
The efficiency of Barrick’s ore recovery processes is directly influenced by the
geological nature of the ore. Currently, the operation uses 18 routing schemes (14 for ore
and 4 for waste) to maximize recovery and in turn, profits. Higher grade ores are
typically processed first while low grade ore is stockpiled for processing at a later date.
Often the dilution caused by blasting simply defers the return on investment to a later
date. However, in some cases blast induced dilution can have a detrimental effect on the
efficiency of the recovery processes (for example, preg robbing material processed by the
autoclave or mixing of distinct ore/waste boundaries).
Typically, the post blast ore boundaries are staked based on the assumption that no blast
movement has occurred. Unfortunately, most conventional timing configurations mix the
material types together and can move the entire rockmass in an unpredictable fashion.
This uncontrolled movement leads to the inaccurate placement of ore boundary stakes.
The accuracy and flexibility of the electronic delays allows blasts to be designed to limit
ore dilution. In many cases, the different material types in a blast can be separated into
DILUTIONCONTROLEVALUATION
The performance of the ore recovery enhancement blast was dramatic. There were four
distinct muckpiles produced and, as expected, there was one timing sequence that
performed better than the others. The best performing sequence occurred in the region of
pile 1 shown in figures 15 and 16. The delay sequence used to produce pile 1 is shown in
figure 17.The height of pile 1 was over 20 feet above the original surface of the blast as
shown in figure 18. The blast also produced a well defined seperation along the NW
material boundary as shown in figure 19.
Some oversize was noted in the northwest portion of the blast. This oversize was due to a
change in and the use of longer delay times (41 ms) between rows.
DILUTIONCONTROLECONOMICRAMIFICATIONS
The delay configuration used for the ore recovery enhancement blast would not have
been possible with pyrotechnic delays. The practically unlimited range of firing times
provided by the electronic delays allows timing configurations to be developed to
precisely control muckpile movement and dramatically reduce dilution. The economic
benefits of this control in terms of increased efficiency and recovery is probably several
times greater than the additional costs of the detonators.
If the productivity of the milling and roasting operations is increased by 0.15 percent the
additional costs of the detonators will be offset by the savings generated by the increased
production.
If the value of the additional gold produced is added to the equation the break-even point
is around 0.05%.
The additional cost of the electronic caps can be offset by very small increases in the
efficiency of the ore processing and recovery operations. An in-depth evaluation of the
actual economic benefits is being pursued based on the magnitude of potential savings.
Extensive research has been conducted onsite to develop the best timing configuration to
limit vibrations at the oxygen plants. The frequency content of the blast vibrations was
found to be an important factor that influenced the response of the equipment in the plant.
Specialized timing configurations were developed to control the frequency content of the
blast vibrations. Since the available pyrotechnic delay times are limited, a configuration
was adopted based on the available delays as opposed to optimum design. In addition,
the scatter in the tiring times of the pyrotechnic delays prevented consistent frequency
modification and vibration control.
Excessive blast vibrations have been shown to cause damage to slope stability at other
operations. While ground vibration has not been shown to be the specific cause of slope
failures at Barrick’s Goldstrike operation it is still an important concern.
VIBFUTIONCONTROLTESTSETUP
The initial scope of the project included studying the influence of accurate timing on
vibration control. A typical waste blast was detonated using electronic delays and the
vibration control timing configuration of 59 ms down the control row and 17 ms between
holes on the echelon.
Two separate blastholes were tired independently of the blast to generate a vibration
“signature” for future timing analysis.
The blast vibrations were monitored with a digital seismograph about 1200 feet away at a
point between the blast site and the new oxygen plant.
Tests were also conducted to determine the influence of short delay intervals on vibration
amplitude and frequency. However, the results of these tests were inconclusive.
VIBRATIONCONTROLTESTRESULTS
The timing configuration was effective for the first 500 ms of the blast. Some of the
blast’s low frequency energy was shifted to around 20 hz. Unfortunately it was not
possible to evaluate a similar timing configuration with pyrotechnic delays during the
study.
The accuracy and full range of delay intervals provided by the electronic delays makes
them much more suitable for consistent vibration control. Additional tests are required to
quantify the benefits specifically for the Goldstrike operation.
Several methods were used to evaluate the performance of the blasts. The methods
included image analysis of the run of mine ore, plant evaluation using PI data, and plant
evaluation using circuit survey.
The results indicated that ore from blasting with electronic detonators was finer and the
mill throughput was greater compared to ore from the pyrotechnic detonators.
SmarY
Recent advances in electronic detonator technology have resulted in systems that are now
ready for widespread use by the mining and quarrying industry. The main features that
are unique to electronic detonators are:
l tiring time accuracy to within one tenth of one millisecond of the designed
time
l a full range of firing times (1 to 4000 ms in one ms intervals)
This accuracy and flexibility allows the blast designer to develop timing configurations
that are not possible with conventional pyrotechnic delay units. As a result, the blasts can
be designed to maximize fragmentation, control ore dilution and limit vibration levels.
The main thrust of this study was to quantify the benefits of the use of electronic
detonators to the downstream excavation, crushing and ore processing operations.
The rock fragmentation produced by the use of the electronic detonators was quantified
using digital image analysis. Ninety percent of the blast fragmentation produced by the
use of the electronic detonators was less than 4 inches (a reduction of over 44 percent
over a similar blast with pyrotechnic detonators). One benefit of this decrease was
reflected by the improved performance of the excavator. An increase in productivity of
6.5 percent is required to offset the additional costs associated with the use of electronic
detonators. The average “pure productivity” rate of the excavator was 11 percent higher
while excavating the electronic detonator blast.
The crushing and milling circuits are optimized when blasting produces the proper
fragment size distribution and when the explosive energy creates micro-fractures that
increase friability. The material from the initial test blasts was stockpiled and fed directly
into the crusher. This allowed the benefit to the crusher and milling operations to be
quantified.
One of the main advantages of the electronic detonators is the wide range of available
delay times. With this flexibility, the ore blasts can be designed to limit dilution by
separating the various ore types into distinct piles. A test blast was conducted that
successfully proved this concept. The Goldstrike property currently has 14 different ore
routing schemes to maximize the efficiency of the roaster and autoclave processes. The
A total of six hundred electronic detonators were used during the study. No attempt was
made to optimize the performance of the current blast designs. However, the test blasts
still produced excellent fragmentation and demonstrated unique dilution control
characteristics. The positive test results warrant a larger scale, longer-term evaluation.
This evaluation will be conducted in a manner that allows the benefits of the increased
fragmentation to be quantified in terms of excavator, crusher and mill productivity. The
influence of dilution control on the efficiency of the roaster and autoclave will also be
quantified during the evaluation.
The initial findings of this study indicate that the use of electronic delays will benefit the
excavation, hauling and crushing operations at Barrick’s Goldstrike operation. In
addition, there is a strong probability that the proper use of electronic delays will increase
the efficiency of the ore recovery operations. This increase could potentially provide a
much greater economic benefit than has been determined to date. The electronic
detonators will be further evaluated to quantify the benefits of increased fragmentation
and dilution control on the efficiency of the gold recovery processes.
Pile ‘1
0 0 0 0
37 15 15 37
0 0 0 0
35 1 1 35
0 0 0 0
37 15 15 37
0 0 0 0
39 37 37 39