Professional Documents
Culture Documents
Sabouni ElNaggar CJCE 8 2011
Sabouni ElNaggar CJCE 8 2011
net/publication/262965088
CITATIONS READS
6 4,289
2 authors:
Some of the authors of this publication are also working on these related projects:
Seismic performance evaluation of underground structure under liquefaction site View project
Investigation of Hybrid Foundation System for Offshore Wind Turbine View project
All content following this page was uploaded by Reem Sabouni on 27 August 2014.
Abstract: Concrete manholes are widely used in sanitary sewer and storm water systems in Canada. However, technical in-
formation regarding their structural aspects is limited. The main objective of this paper is to evaluate the effect of main pa-
rameters that impact the design of precast concrete manholes. A three-dimensional finite element model for circular precast
concrete manholes was developed using Plaxis 3D and was calibrated against the experimental results presented in an earlier
paper by the authors. The calibrated numerical model was used to analyze different configurations of concrete manholes and
to conduct a parametric study on the parameters that govern its design including: type of native soil around the manhole;
trench width (Tw); water table elevation (Wt); effect of manhole stage installation; and effect of soil compaction. The critical
conditions were identified based on the change in the pressure underneath the centre of the manhole base and the bending
moments within the manhole base. It was found that the trench width, stage installation of manhole, and filling soil compac-
tion had marginal effects on the total vertical pressure beneath the centre of the manhole base. The presence of the water ta-
ble at the top of the manhole resulted in the most critical contact pressure at the manhole base.
Key words: precast concrete manholes, Ontario standard truck load, three dimensional finite element, bending moments in
manhole base, strain gauges, pressure cells, soil structure interaction, water table and manhole trench width.
Résumé : Les trous d’homme en béton préfabriqué sont largement utilisés dans les réseaux d’égouts sanitaires et pluviaux
au Canada. Cependant, l’information technique concernant leurs aspects structuraux est limitée. L’objectif principal de cet
For personal use only.
article est d’évaluer l’effet des principaux paramètres touchant la conception des trous d’homme en béton préfabriqué. Un
modèle par éléments finis tridimensionnel pour les trous d’homme circulaires en béton préfabriqué a été développé en utili-
sant Plaxis 3D et étalonné en utilisant les résultats expérimentaux présentés dans un autre article. Le modèle numérique éta-
lonné a été utilisé pour analyser différentes configurations de trous d’homme en béton et pour réaliser une étude
paramétrique des paramètres qui régissent sa conception, dont: type de sol naturel autour du trou d’homme, la largeur de la
tranchée (Tw), l’élévation de la nappe phréatique (Wt), l’effet du stade d’installation du trou d’homme et l’effet de la com-
paction du sol. Les conditions critiques ont été identifiées en se basant sur le changement de pression sous le centre de la
base du trou d’homme et les moments de flexion dans la base du trou d’homme. La largeur de la tranchée, le stade d’instal-
lation du trou d’homme et la compaction du sol de remplissage n’avaient que des effets marginaux sur la pression verticale
totale sous le centre de la base du trou d’homme. La présence de la nappe phréatique au haut du trou d’homme a engendré
la pression de contact la plus importante à la base du trou d’homme.
Mots‐clés : trous d’homme en béton préfabriqué, charge de camion standard en Ontario, éléments finis tridimensionnels,
moments de flexion dans la base du trou d’homme, jauges de déformation, cellules de mesure des pressions, interaction sol-
structure, nappe phréatique, largeur de tranchée pour le trou d’homme.
[Traduit par la Rédaction]
Introduction garding the design loads and maximum allowed depth of pre-
cast concrete manholes is provided by the American
Literature on concrete sewer or storm water manholes is Concrete Pipe Association (ACPA 2008a). The association
scarce and concentrates on durability issues (Griffiths and also provided information on manhole floatation in the “De-
Ball 2000; Saricimen et al. 2003) or on the manhole perform- sign data 41” article (ACPA 2008b). To the best of the au-
ance as part of the overall sewer or storm water system (Bet- thors’ knowledge, no full-scale testing of concrete manholes
tez et al. 2001; Zhou et. al. 2004 and Downey 2004). under design loads was reported in the literature (Sabouni
Technical information regarding the structural aspects of this and El Naggar 2008). However, several studies were con-
type of manholes is limited. Brief technical information re- ducted on other types of manholes. For example, Petroff
Received 1 September 2009. Revision accepted 14 May 2011. Published at www.nrcresearchpress.com/cjce on 19 August 2011.
R. Sabouni. Alhosn University, Department of Civil Engineering, P.O. Box 38772, Abu Dhabi, United Arab Emirates.
M.H. El Naggar. Faculty of Engineering, Department of Civil and Environmental Engineering, The University of Western Ontario,
London, ON N6A 5B9, Canada.
Corresponding author: M.H. El Naggar (e-mail: helnaggar@eng.uwo.ca).
Written discussion of this article is welcomed and will be received by the Editor until 31 December 2011.
Can. J. Civ. Eng. 38: 909–920 (2011) doi:10.1139/L11-059 Published by NRC Research Press
910 Can. J. Civ. Eng. Vol. 38, 2011
(1994) presents a design methodology for the high density to be the model boundaries and were assigned the standard
polyethylene manholes. His design accounted for ring and di- boundary fixity.
rected loads from applied earth pressure, load from ground- The manhole base was modeled using the Plaxis 3D floor
water, and drag down of the surrounding soil. Hossain and element. The floor element was modeled as a 6-noded trian-
Lytton (1991) studied the response of flexible large diameter gular shell element with six degrees of freedom per node:
high density polyethelen plastic vertical shafts in landfills to three translational (ux, uy, and uz) and three rotational (fx, fy,
soil structure interaction. They carried out a comprehensive and fz) (Brinkgreve et al. 2007). The 1200 mm diameter
finite element analysis that included effect of incremental manhole model base was circular with diameter, D =
construction, creep of pipe, compaction, and landfill material. 1.219 m. The centre of the base was located at elevation
For personal use only.
This paper describes the numerical model and parameters zero (0.94 m from the base of the model) and 2.25 m from
used and the verification of the model using experimental the model boundary. The “1200 mm dia. manhole base” data
data. The numerical model is then used to investigate the ef- set (Table 1) was assigned to the floor elements. The
fect of rigid walls of the large-scale geotechnical testing fa- 1500 mm manhole model had a circular base with 1.524 m
cility (LSGTF) on the experimental results. Finally, a diameter. The base centre was located at elevation zero
comprehensive parametric study (involving the analysis of (1.92 m from the base of the model), 2.60 m in the x-direction
85 models) is conducted to evaluate the effects of different and 2.25 m in the z-direction. The “1500 mm dia. manhole
parameters that may influence the design of concrete man- base” data set (Table 1) was assigned to the floor elements.
holes including: type of native soil around the manhole, The floor (base) elements were assumed to remain linear
trench width (Tw), water table elevation (Wt), effect of man- elastic during loading, as evidenced from the small strains
hole stage installation, and effect of filling soil compaction. observed in the tested manhole floors during the experimen-
The critical conditions were identified based on the change tal phase.
in the soil pressure underneath its base and bending moments The monobase manhole risers were modeled using the
developed in the base. “Volume pile” option in Plaxis 3D. This pile option creates
a cylindrical tube pile composed of shell (wall) elements
Manhole models with optional interfaces at both shell sides. Interface elements
All assigned dimensions were taken as measured from the are composed of eight pairs of nodes. Each pair has identical
tested manholes setup. The elevation of the bottom of the coordinates, i.e., the element has zero thickness. Each node
manhole base was taken as the datum (zero elevation) in the has three translational degrees of freedom (ux, uy, and uz).
model. The detailed properties of the data sets are taken to The interface element allows for differential displacements
match the physical and mechanical properties of the LSGTF, between the node pairs to simulate slipping and gapping
manholes and soil bed as tested in the experimental program (Brinkgreve et al. 2007). For the 1200 mm diameter manhole
described in Sabouni and El Naggar (2011). The details of model, the pile inner diameter was D = 1.219 m. The mono-
the manhole model including the LSGTF, manhole compo- base and risers 1 to 4 heights were assigned their actual
nents, soil bed and interfaces, wheel footprint (loading plates) heights, i.e., 1.219 m, 1.219 m, 0.914 m, 0.610 m, and
and applied loads are provided below. 0.610 m, respectively. The monobase riser was connected to
The walls of the LSGTF are 4.5 m in width and 7.62 m in the manhole base and the risers were stacked on top of it.
height and were modeled using the Plaxis 3D wall (shell) el- The “1200 mm dia. manhole wall” data set (Table 1) was as-
ement. The wall element is 8-noded quadrilateral plate with signed to the wall elements representing the manhole mono-
six degrees of freedom per node: three translational (ux, uy, base and risers. For the 1500 mm diameter manhole model
and uz) and three rotational (fx, fy, and fz) (Brinkgreve et the pile inner diameter was specified as D = 1.524 m. The
al. 2007). The walls were assigned the LSGTF wall data set risers 1 to 3 heights were assigned their actual heights, i.e.,
with properties as presented in Table 1. The LSGTF base 1.21 m, 0.91 m, and 0.61 m, respectively. The first riser was
was assumed to be fixed and was assigned the standard connected to the manhole base and the other risers were
boundary fixity. The outer faces of the walls were assumed stacked on top of it. The “1500 mm dia. manhole wall” data
Table 2. Borehole 1200 and 1500 soil layer elevations and assigned soil and interface data
sets.
2 Grade A gravel
3 –0.98 –0.60 Concrete sand
4 –0.60 4.673 Grade A gravel
set (Table 1) was assigned to the wall elements representing material model and the drained material type were assigned
the manhole risers. The linear stiffness assigned to the wall for both soils used (concrete sand and grade A gravel). The
elements was justified as measured strains in the tested man- Mohr-Coulomb soil models in Plaxis 3D follows the elastic
hole were much less than the concrete cracking strain. perfectly plastic behaviour and the non associated flow
Due to the limitations of the program and the fact that the theory. The detailed assigned soil properties for both soil
variation of stresses in the tapered top area is of minor im- types such as the: unsaturated and saturated unit weight,
portance to the scope of the research, the tapered top for modulus of elasticity, Poisson’s ratio, cohesion, angle of in-
both manholes was taken as a cylindrical pipe similar to the ternal reaction, angle of dilatancy, and interface strength fac-
rest of the manhole with a 1.32 m height. The “Manhole ta- tor are shown in Table 3.
pered top” data set (Table 1) was assigned to this part of the To select the optimum mesh size that will provide reason-
model. The unit weight of this data set was assigned in a able accuracy with practical computational effort, several
manner that the weight of the modeled tapered top was equal mesh sizes were examined. Changing the mesh size from
to the actual weight of the tapered top and the soil resting on very coarse to very fine in the 1200 mm diameter manhole
it. For the 1500 mm diameter manhole the transition cone model changed the vertical displacements at the manhole
was modeled similar to the tapered top and had a height of base centre by about 20% and the vertical stresses underneath
0.61 m. the manhole base centre by less than 10%. On the other hand,
The soil bed was modeled using 15-node wedge elements. the refinement in the mesh size dramatically increased the
These elements are generated from the 6-node triangular computation time due to the large size of the three dimen-
elements in the 2D mesh. The wedge element is composed sional model. An optimized mesh size with refinement
of 6-node triangles in the horizontal direction and 8-node around the manhole perimeter where large stresses are ex-
quadrilaterals in the vertical direction. Soil elements have pected (Laman and Yildiz 2007) was selected with due con-
three translational degrees of freedom per node (ux, uy, and sideration for both accuracy and computing efficiency.
uz) (Brinkgreve et al. 2007). In Plaxis 3D, the soil profile is The manhole cover was modeled as a floor element cover-
defined in the model by assigning boreholes. One borehole ing the top of the inner diameter of the tapered top and was
was assigned to each model. Borehole 1200 was assigned to assigned the “Manhole cover” data set (Table 1). The loading
the 1200 mm diameter manhole models and Borehole 1500 plates were modeled as 0.65 m × 0.25 m floor elements.
was assigned to the 1500 mm diameter manhole models. They were also assigned the Manhole cover data set. The
The bottom of the manhole models was assigned zero eleva- loads applied to the manhole in the model replicated the ap-
tion. The hydrostatic water level was assigned at zero elevation plied loads during testing the manhole in the experimental
for the 1200 mm diameter manhole model and at –0.98 m program (described in Sabouni and El Naggar (2011). These
elevation (0.98 m below the manhole base) for the 1500 mm loads represent the critical loads from the standard Ontario
diameter manhole model (see Table 2). The Mohr-Coulomb truck. Six different load configurations as shown in Table 4
Fig. 1. Model view of different loading configurations 1200 mm diameter manhole: (a) no load, (b) 1PCLF, (c) 2PCLF, (d) 4PCLF,
(e) 4PDLF, and (f) 1PTLF and 1PXTLF.
For personal use only.
Fig. 2. Locations of instrumentation in the experimental setup: a) 1200 mm dia. nonreinforced manhole base strain gauges, (b) 1500 mm dia.
nonreinforced manhole base strain gauges, (c) 1200 mm dia. reinforced manhole pressure cells at 0.6 m beneath base, (d) 1200 mm dia.
nonreinforced manhole pressure cells at 0.6 m beneath base, and (e) 1500 mm dia. reinforced manhole pressure cells at 0.4 m beneath base.
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Western Ontario on 10/12/11
For personal use only.
and Fig. 1 were applied one at a time and the model response vated, one at a time, to model the load cases described
was analyzed. earlier. Each of the load construction stages started from the
The construction stages option was used to simulate the in- end of the last “installation” construction stage. The plastic
stallation process of the manhole in the soil pit and to apply calculation type and the program’s default calculation settings
various loading configurations to the model. In the first con- were used in performing the analyses.
struction stage, the soil underneath the manhole was acti-
vated. A construction stage was then added for installation Model verification using experimental results
of each manhole part, where the part and the surrounding
soil were activated. After completing the “installation” con- The soil pressure underneath the manhole base obtained
struction stages, five “load” construction stages were acti- from the analysis is compared with the values measured dur-
Table 5. Vertical pressure under 1200 mm diameter reinforced and nonreinforced manholes [kPa].
Nonreinforced manhole
Reinforced manhole H1 H1 H3
Pressure cell
name Model Exp. %Diff. Model Exp. %Diff. Model Exp. %Diff.
Before loading 139.5 104 26% 139.5 113 19% 129.6 84.6 35%
1PCL 150.7 105 30% 150.7 124 18% 140 88.4 37%
2PCL 162.4 110 32% 162.4 127 22% 145.1 89.1 39%
4PCL 158.4 111 30% 158.4 121 24% 146.1 91.4 37%
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Western Ontario on 10/12/11
4PDL 186.5 113 39% 186.5 139 25% 158.4 95.8 40%
1PTL 170.8 102 40% 170.8 138 19% 148.9 91.5 39%
1PXTL — — — 175.1 143 18% 151.4 92.5 39%
Note: Locations of pressure cells in the related experimental setup are shown in Fig. 2.
H1 H2 H3 H4
Pressure % % % %
cell name Model Exp. Diff. Model Exp. Diff. Model. Exp. Diff. Exp. Model Diff.
Before 129.3 176.0 –36% 132.9 155.2 –17% 136.0 136.7 0% 134.5 120.7 10%
loading
1PCL 138.5 179.8 –30% 142.6 159.5 –12% 145.7 141.6 3% 143.6 124.4 13%
2PCL 143.7 185.8 –29% 147.9 165.5 –12% 151.3 146.9 3% 148.8 131.3 12%
4PCL 146.3 196.9 –35% 150.3 171.7 –14% 153.9 155.2 –1% 152.1 137.2 10%
For personal use only.
4PDL 150.5 200.2 –33% 154.9 172.4 –11% 158.4 156.4 1% 155.3 137.6 11%
1PTL 147.7 205.2 –39% 152.0 177.1 –17% 155.5 160.6 –3% 152.5 137.9 10%
1PXTL 150.1 203.5 –36% 154.5 178.3 –15% 158.0 159.8 –1% 154.9 138.0 11%
Note: Locations of pressure cells in the related experimental setup are shown in Fig. 2.
ing the experimental program (see Fig. 2 for locations of the edges, which agreed with the experimental results. The
pressure cells in related experiments). Furthermore, the calcu- percentage differences between experimental and numerical
lated strains in the manhole base are compared with the ex- pressures ranged from 18% to 40% as shown in Table 5. On
perimental values at the same locations (see Fig. 2 for the other hand, the comparison between the calculated soil
locations of strain gauges in related experiments), and the pressure at 0.45 m under the 1500 mm diameter modeled
calculated maximum moments developed in the manhole manhole base and that of the tested manhole showed a per-
bases are compared to the pertinent base cracking moment. centage difference between the experimental and numerical
The following paragraphs will show the results of the com- pressure results ranged from –36% to 12% as shown in Ta-
parison. ble 6.
Table 8. Numerical and experimental strain in the 1500 mm diameter manhole base due to loading [strain × 10–6].
1PXTL 1.25 3.73 3.26 2.43 3.26 4.07 3.54 6.87 2.33 2.00 3.36 4.00
Note: Locations of strain gauges in the manhole base are shown in Fig. 2.
calculated tension strain due to loading in the manhole base Fig. 3. Pressure under manhole base: a) before loading, (b) 1PXTL,
was 8.58 × 10–6. The maximum overall calculated strain in and (c) 4PDL.
the manhole base (29.78 × 10–6) at the location of the strain
gauges was about 60% less than the base cracking strain. The
calculated strain due to loading (for fast loading cases) is
compared to the experimental strain due to loading for the
same loading cases at the same locations for the nonrein-
forced manhole specimen in Table 7. It should be taken into
consideration that the results due to loading shown in Table 7
do not represent the final state of tension or compression in
their location but demonstrate whether it is an increase or de-
crease in tension or compression from the before loading
strains condition in their location. The results demonstrate
For personal use only.
Table 9. Percentage difference of the maximum 1200 mm and 1500 mm diameter manhole models base bending moment from
the base cracking moment.
Fig. 4. Schematic diagram of the manhole model showing the parameters considered in the parametric study.
For personal use only.
the LSGTF strong walls had marginal effect on the pressure al. 1989). The experimental results ofan earlier work by Sab-
under the manhole base. ouni and El Naggar (2011) showed a similar behaviour where
the total loads at the same levels were found to be 175 kN
Manhole models results analysis and 377 kN for the 1200 mm and 1500 mm diameter man-
holes, respectively.
Pressure underneath the manhole bases
The average vertical soil pressure at 0.6 m and 0.4 m Moment in manhole bases
under the manhole base (levels of pressure cells in related ex- Table 9 shows the maximum bending moments of the base
periments) before loading were found to be 143.5 kN/m2 and of the 1200 mm diameter and 1500 mm diameter manholes.
130.5 kN/m2 for the 1200 mm and 1500 mm manholes.
The cracking moment (Mcr) for these manhole bases were
These pressures correspond to total vertical loads of 168 kN
found to be 16.3 kN·m/m and 62.4 kN·m/m for the
and 332 kN acting on the 1200 mm and 1500 mm manhole
base area, respectively. These loads are greater than the 1200 mm and 1500 mm diameter manholes, respectively, as
weight of manhole and soil to the specified depth, which calculated by (CSA 2004, 2006):
means manholes are carrying 52 kN and 192 kN extra loads.
Ig fcr
This could be due to additional load from surrounding soil ½1 Mcr ¼
transmitted to the manholes walls through friction (Tadros et yt
Table 10. Properties of soil materials used in the finite element models.
Fig. 5. Effect of trench size on total vertical pressure under Fig. 6. Effect of water table on total vertical pressure under
1200 mm diameter and 5.89 m long manhole base centre: (a) before 1200 mm diameter and 5.89 m long manhole base centre with 0.6 m
loading and (b) 1PXTL applied. trench size.
For personal use only.
pffiffiffiffi
½3a fcr ¼ 0:6l fc0
8 9
>
> 1:00 rc 2150 kg=m3 >
>
< =
3 3
½3b l ¼ 0:85 1850 kg=m < rc < 2150 kg=m
>
> >
>
: 0:75 rc 1850 kg=m3 ;
Table 12. Effect of modeling construction stages on soil pressure under manhole base
centre.
Table 13. Effect of compaction on total pressure under manhole base centre.
concrete sand
Sand–clay 115.3 122.2 5.98
Clay–sand 91.7 92.3 0.65
The finite element models calibrated against the experi- ble 11. Several finite element models were analyzed for each
mental results were slightly modified for the purpose of the soil configuration, changing the trench size and the water ta-
parametric study (Fig. 4) to render it representative of in situ ble level. Each manhole model was analyzed for two cases:
conditions. For example, the walls representing the large- no load applied, and the 1PXTL applied load. Figures 5 and
scale geotechnical testing facility (LSGTF) were removed 6 show that the largest total vertical pressure underneath the
and the boundaries of the model were placed at 6.0 m away manhole base centre occurred in sand–sand soil models. It is
from the manhole walls, and 6.0 m away from the manhole also noted that pressure values for different soil conditions
base, i.e., more than six times the radius of the manhole are bounded by the values of the clay–clay and sand–sand
(Zhao and Wang 2008). In addition, a trench was introduced soil model.
around the modeled manholes and the bedding under the
manhole was reduced to the minimum (0.15 m) required by Effect of trench width (Tw)
the Ontario provincial standard specification (OPSS516) The trench width, Tw, is the width of grade A gravel back-
(MTO and MEA 2005). Both the trench filling around the fill between the manhole riser and native soil as shown in
manhole and the bedding under the manhole were taken as Fig. 4. Three values were considered, Tw = 0.3 m, 0.6 m,
grade A gravel (grade A gravel soil data set Table 3). This and 1.64 m (as used in the experimental program). Each
soil was chosen based on the requirements of the MTO and width was considered with the five soil configurations and
MEA (2003, 2008). Three different native (in situ) soil types for water table at the base level and at the manhole top and
were considered: medium dense sand, medium to stiff clay, the analysis was performed for both no loading and the
and very dense sand (see Table 10 for properties). The 1PXTL loading case. The results shown in Fig. 5 indicate
Mohr-Coulomb material model was used for all three types that the trench size had a slight effect on the total vertical
of soils. The first two materials represent in situ cohesionless pressure under the centre of the manhole. For example, as
and cohesive soils; whereas, the third represents the case of a the trench size increased from 0.3 m to 1.64 m, the pressure
stronger soil on the response of the modeled manholes (the underneath the centre of the manhole varied by ±8.5%, con-
sandy soils represent two different soils). firming that the LSGTF had minor effect on soil pressure
from a designer point of view.
Effect of type of native soil around manhole
Three types of soils, with five different combinations of Effect of water table elevation
soils around the risers (outside the installation trench) and Three water table levels were considered: 6 m below man-
under the manhole base (under the bedding soil) were con- hole base (dry model), elevation of manhole base, and top of
sidered in the preliminary parametric study as shown in Ta- the manhole (submerged model). Five soil configurations
were considered, with Tw = 0.6 and the models were ana- soil underneath the manholes were evaluated in a parametric
lyzed for both no loading and the 1PXTL loading case. The study on a variety of manhole site conditions to identify the
total vertical pressure beneath the centre of the manhole base critical factors affecting the manhole response.
was almost equal for the cases of water table at 6 m below The results showed that the maximum base moment for the
and at the manhole base, and it slightly increased for water 1200 mm diameter manhole model for all loading cases was
table at the manhole top (from 3% to 13.5%) as shown in 65% less than the cracking moment. For the 1500 mm diam-
Fig. 6. eter manhole model base, the maximum moment for all load-
ing cases was 81% less than the cracking moment. These
Effect of the model staged installation results indicated that the 1200 mm and 1500 mm diameter
The effect of the manhole staged installation on the soil circular precast concrete manholes’ base designs were overly
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Western Ontario on 10/12/11
Table 12. The results showed that for manholes installed in The authors would like to express their sincere thanks to
sand, the staged construction slightly decreased the pressure the Ontario Concrete Pipe Association and NSERC for sup-
beneath the centre of the manhole base. On the other hand, porting this research. Thanks are also extended to Con Cast
the pressure increased by up to 6.4% and 1.6% for manholes Pipe, Hanson Pipe and M-Con for providing us with the
in clay and concrete sand, respectively. tested manhole samples.
high density polyethylene plastic pipes as vertical shafts in manholes. In Buried Plastic Pipe Technology, Vol. 2. (ASTM STP
landfills. Journal of Testing and Evaluation, 19(6): 475–484. 1222). Edited by D. Eckstein. pp. 52–65.
doi:10.1520/JTE12611J. Sabouni, R., and El Naggar, M.H. 2008. Full Scale Testing of
Ingold, T.S. 1979. Retaining wall performance during backfilling. 1200 mm Diameter Precast Concrete Manhole. In Proceedings of
Journal of the Geotechnical Engineering Division, 105(GT5): 2nd Canadian Conference on Effective Design of Structures,
613–626. Hamilton, Ontario, Canada, 20–23 May 2008.
Laman, M., and Yildiz, A. 2007. Numerical studies of ring Sabouni, R., and El Naggar, M.H. 2011. Circular precast concrete
foundations on geogrid-reinforced sand. Geosynthetics Interna- manholes: experimental investigation. Canadian Journal of Civil
tional, 14(2): 52–64. doi:10.1680/gein.2007.14.2.52. Engineering, 38(3): 319–330. doi:10.1139/L10-135.
Ministry of Transportation of Ontario (MTO) and Municipal Saricimen, H., Shameem, M., Barry, M.S., Ibrahim, M., and Abbasi,
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Western Ontario on 10/12/11
Engineers Association. (MEA). 2003. Ontario Provincial Standard T.A. 2003. Durability of proprietary cementitious materials for use
Specifications OPSS 1010, Material specification for aggregates- in wastewater transport systems. Cement and Concrete Compo-
base, subbase, select subgrade, and backfill material. Ministry of sites, 25(4–5): 421–427. doi:10.1016/S0958-9465(02)00082-3.
Transportation of Ontario, and Municipal Engineers Association, Seed, R.B., and Duncan, J.M. 1986. FE analysis: Compaction-
Ontario, Canada. induced stresses and deformations. Journal of Geotechnical
Ministry of Transportation of Ontario (MTO) and Municipal Engineering, 112(1): 23–43. doi:10.1061/(ASCE)0733-9410
Engineers Association. (MEA). 2005. Ontario Provincial Standard (1986)112:1(23).
Specifications OPSS 516, Construction specification for excavat- Tadros, M.K., Benak, J.V., and Gilliland, M.K. 1989. Soil Pressure on
ing, backfilling, and compacting maintenance hole, catch basins, box culverts. American Concrete Institute Structural Journal, 86(4):
ditch inlets and valve chambers. Ministry of Transportation of 439–450.
Ontario, and Municipal Engineers Association, Ontario, Canada. Zhao, L., and Wang, J.H. 2008. Vertical bearing capacity for ring
Ministry of Transportation of Ontario (MTO) and Municipal footings. Computers and Geotechnics, 35(2): 292–304. doi:10.
Engineers Association. (MEA). 2008. Ontario Provincial Standard 1016/j.compgeo.2007.05.005.
Specifications OPSS 514, Construction specification for trenching, Zhou, F., Hicks, F., and Steffler, P. 2004. Analysis of effects of air
backfilling, and compacting. Ministry of Transportation of pocket on hydraulic failure of urban drainage infrastructure.
Ontario, and Municipal Engineers Association, Ontario, Canada. Canadian Journal of Civil Engineering, 31(1): 86–94. doi:10.1139/
Petroff, L.J. 1994. Design methodology for high density polyethylene l03-077.
For personal use only.