Installation and Pressure Testing of Clean Agent System FM200
Installation and Pressure Testing of Clean Agent System FM200
Document
Date of issue 02-Sep-2022 Dondon Tinimbang
Prepared By
As per project
Proposed start date TBA Duration of task
Requirement
Contents
Section A Register of Revisions Page 3
Section B Scope of Works to be undertaken Page 4
Section C Location of the Project Page 4
Section D Location of the Works to be Undertaken with the Project Page 5
Section E Site Access/Egress and Access to the Work Zone Page 6
Section F Emergency Contacts Details and Procedures Page 7
Section G McLaren Site Specific HSE Safety Induction Page 8
Section H Welfare facilities Page 8
Section I Personal Protective Equipment Page 8
Section J Plant/Equipment and tools to be Used Page 9
Section K Materials To be used Page 9
Section L Temporary Works Page 10
Section M Inspection and Test Regime Page 10
Section N Communication/Toolbox Talks/Training Requirements Page 10
Section O Works Permits Page 11
Section P Environmental and Waste Management Page 11
Section Q Programme for the Works Page 12
Section R Housekeeping and Storage Page 12
Section S Working at Height Page 12
Section T Occupational Health Page 12
Section U Sequence of Works/Activities Page 13
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets
Appendix D Risk Assessments
Appendix E Technical Information
Appendix F Inspection and Test Plans
Appendix G Third Party competency/certifications
Appendix H Installation Checklist and Test Report
Rev. No Date Reason for Amendment Amended By Signature Has this amendment been
(Name) briefed to the operatives
involved and have the
operatives signed the register?
00 02-09-2022 Issued for Approval
This method statement has been prepared in conjunction with the following documents;
Existing Services
As per current information, there are no services within the site boundaries.
A full survey will be undertaken to confirm this including an underground service scan and trial
trenches hand excavated in various locations around the project to locate any services running into, or
close to the plot.
A permit to dig must be obtained from McLaren prior to any excavations commencing.
MS for Installation and Pressure Testing of Clean Agent Fire DX031-MCL-ZZ-ZZ-MS-F-
Title: Ref. No:
Suppression System FM200 SPRN-0004
Project: DX3.1 Data Centre Dubai Production City Rev. No: P01
Prepared By: Dondon Tinimbang Approved By: Vivek Allen Quadros Rev. Date:
Ground level
Level 1
Section E- Site Access/Egress and Access to the Work Zone
MS for Installation and Pressure Testing of Clean Agent Fire DX031-MCL-ZZ-ZZ-MS-F-
Title: Ref. No:
Suppression System FM200 SPRN-0004
Project: DX3.1 Data Centre Dubai Production City Rev. No: P01
Prepared By: Dondon Tinimbang Approved By: Vivek Allen Quadros Rev. Date:
The following staff from McLaren will be on site during the execution of the works and will be responsible for
managing the works.
Name Position Company Contact Details
Fergus O’Boyle Project Director McLaren 050 922 4337
Vivek Allen Quadros Project Manager McLaren 050 4330423
Edwin Rebello Snr Site Manager McLaren 0559926208
Sukhjinder Singh Senior HSE Officer McLaren 055 658 0651
Lester Ramos QA/QC Engineer McLaren 0561383961
Robert Heard MEP Manager McLaren 0503744801
Mark Summers Senior Project Manager JJJV 0564147305
Michael Enright HSE Manager JJJV 0563390767
Muthiah Palaninayagam MEP Construction Manager JJJV 056 408 5895
Joel Betreen Senior HSE Officer JJJV 0559657829
Dondon Tinimbang QA/QC Mechanical Engineer JJJV 0509098726
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly
Point, which is indicated on the site logistics drawing, as indicated by the symbol below. A roll call will be taken,
and registers checked to ensure that everyone is accounted for. No one will be allowed to leave the assembly
point until the Emergency Response Controller confirms that it is safe to do so.
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available within the
First Aid Room and in the Main Office Reception.
On completion of the HSE induction, those involved in this activity will be briefed on the contents of the MSRA
by their respective Site Engineer or Supervisor. They will then be required a sign a MSRA Briefing Register
(SAF019 UAE) confirming that they have been briefed and that they fully understand the MSRA and what is
expected from them during the execution of the works.
Any operative who will be operating any plant or equipment will be required to produce a copy of their Dubai/
Abu Dhabi Municipality/EIAC approved competency certificate/card and proof of health to enable McLaren to
issue them with the Plant Operators Authorisation (SAF023 UAE).
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.
Section J- Plant and Equipment to be Used
It is anticipated that the following Plant and Equipment will be used during the execution of the works; other
items will also be identified on the schedule below.
*Note: All relevant competency certificates to be submitted to HSE Manager/Eng./Advisor prior to start of any
activity.
During this meeting, all those with specific responsibilities for implementation of the ITP and completing the
Work Inspection Sheets will have their roles and responsibilities briefed to them and their names added to the
ITP process flow chart.
The QAQC Engineer will verify that process is fully complied with.
Section N- Communication/Toolbox Talks/Training Requirements:
Before starting any activity, a Point of Work Risk Assessment will be carried out by the Site Engineer/ Supervisor
to ensure all risk and controls have been identified, this will be followed by a task briefing carried out in the
language of the team. All members of the team must sign the briefing sheet to confirm that they have
understood the task requirements.
During the Preparation of this MSRA the following training for the staff and operatives has been identified.
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed (Date)
1 3rd party training for operative of plant Yes, Certificates to be provided TBC
and equipment during induction.
2 First aider training Yes -
3 Power Tools Yes -
4 Banksmen/ Flagmen No, training to be provided prior TBC
to commencement of activity
5 Work at height / Scaffold No, training to be provided prior to -
commencement of activity
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Section O- Works Permits
MS for Installation and Pressure Testing of Clean Agent Fire DX031-MCL-ZZ-ZZ-MS-F-
Title: Ref. No:
Suppression System FM200 SPRN-0004
Project: DX3.1 Data Centre Dubai Production City Rev. No: P01
Prepared By: Dondon Tinimbang Approved By: Vivek Allen Quadros Rev. Date:
Item Description of the Work Permit Permit Issued by Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with scaffold McLaren
8 Permit to Work at Height McLaren
9 Permit to Work – Electrical above 110V McLaren
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Pressure Testing McLaren
14 Other Permit
Any other permits if required to be added
1. Metal
2. Plastic
3. General
4. Concrete
5. Food waste
6. Hazardous
7. Wood Waste
Due to the nature of the works and the current site conditions, water shall be sprayed onto dirt/sand roads to
minimize dust pollution.
Where any plant is used, drip trays shall be placed underneath to catch any spilled oils or fuels. Oils and fuels
will be managed in accordance with the MSDS and the site Waste Management Plan.
All hazardous liquids must store in suitable, labelled containers with secondary containment to prevent ground
and water contamination.
Emergency spills kits must be available where any hazardous material is used.
Combustible materials will be carefully managed and monitored to reduce the risk of fire.
Item Description Preventative Measures, (see also within the Risk Assessments)
1 Safety Critical Roles Anyone identified as safety critical (i.e. Operators, riggers,
scaffolders, banksmen etc.) must have a medical check-up before
starting work
2 Bad Back/sprain due to A manual handing assessment will be carried out for all activities and
improper Manual handling all Operatives will receive Manual Handling training
3 Hand/Arm Vibration Exposure Action Values (EAVs) will be calculated for all vibration
activities. Where required, job rotation will be put in place and
recorded
4 Construction dust Roads shall be watered to minimise dust and housekeeping to be
carried out regularly.
RPE shall be provided for those at risk from hazardous dust
5 Noise Noise values will be monitored. Where required, job rotation will be
put in place and recorded. Where it is not possible to control noise,
PPE will be provided
6 Sun & Heat Drinking water and electrolyte additives will be provided.
Clothing shall cover legs and arms, gloves will be worn.
Summer Working Plans
7 Skin PPE shall be provided as required by MSDS
Section U- Sequence of Works for Installation and Pressure Testing of Clean Agent Fire Suppression
Prior to start the installation at site, the following pre-installation task are essential.
1. Supervising Engineer will confirm that all necessary documentations are in-place to proceed and
identifies if there are any special requirements needed to undertake the work. If everything is
acceptable to proceed, the Supervising Engineer will issue an instruction to carry out the work.
2. Any works in confined spaces (where required) will be subjected to a risk assessment and a permit will
be requested prior to the commencement of any works.
3. All safety work permits must be obtained prior to commencement of work and all workers must be HSE
inducted.
4. All material shall be stored in a dedicated area near workplace allocated by main contractor & handled
by skilled labours.
5. Ensure that all materials to be used and equipment to be installed are checked by the Site Engineer /
QC against equipment data sheets and approved drawings. Materials should be inspected and
approved by the Consultant before being used.
6. The latest revision of the Approved shop Drawings should be available at the installation area.
7. The Site Engineer / Supervisor to orient and familiarize the workers involved in the installation
procedures and details, acceptance criteria and safety requirements relevant
8. All workers must wear PPEs and have work permits with detailed activities signed by the person in-
charge, prior to starting the works.
9. Works must be coordinated with other MEP services and civil team prior to commencement of any
installation work at site.
2. Install the correct die head with threading teeth on the threading machine for the corresponding pipe
size.
3. Insert the end of the pipe to be threaded in-between the die head and tighten the chuck to hold the
pipes properly.
4. Support the other end of the pipe using the pipe support temporary stand.
5. Start the machine and engage the die head in to threading position.
6. Thread the pipe until the required length of the thread is achieved.
8. Drain the residual threading oil from the pipe into the oil tray of the threading machine.
3. Install the correct die on the Grooving machine for the corresponding pipe size.
4. Insert the end of the pipe to be grooved in-between the groove dies.
5. Support the other end of the pipe using the pipe stand.
6. Start the machine and at the same time apply pressure on the pipe toward the machine so that the
pipe does not slip out of the groove die.
7. Groove the pipe until the required depth of the groove is achieved.
Pipe Installation
2. Pipework for FM200 discharge nozzles shall be delivered to site and stored in the designated laydown
area.
3. Where almost all pipework will be fabricated as required in NAFFCO workshop, however there will still
be a requirement for works on site.
4. Pipe will be grooved and threaded therefore minimum amount of hot works is required.
5. Brackets will be manufactured out of Unistrut or C-channel and threaded rods and installed on site at
height using MEWP/Scaffolding/Ladders. Where required.
6. Pipe hangers will be used to hold pipework into position when installed.
8. Operatives will place pipework on stands and carry out preparation work of grooving and threading
pipework.
9. Operative will cut pipework to size where required using cold cutting if possible or angle grinder/chop
saw cutter. Hot works permit in place for use of angle grinder/chop saw cutter, Fire extinguishers and
fire blankets.
10. Operatives to ensure they are always wearing correct PPE i.e., standard site PPE with visor when using
grinder.
11. Once brackets are in position operatives will begin installing pipework as per approved drawings
routes.
12. Pipework will be lifted into position at height using MEWP or scaffolding or pipe lifter.
13. Once pipework is raised to correct height operatives will then place pipework into brackets and secure
into position in brackets.
14. The above process will be repeated until all pipework is in position.
15. All Pipework passing through walls/Slabs should have sleeves. ( sleeves under MEP contractor)
Coupling Installation
1. Groove the pipe ends according to the manufacturer’s specification, project specification and
consultant’s approval.
2. Pipe must be free from indentations, projections or roll marks on exterior from the ends to the groove,
to assure a leak tight seat for the gasket.
3. Place gasket over pipe ends, being sure gasket lip does not overhang pipe end.
4. Align and bring 2 pipe ends together and slide gasket into position centred between the grooves on
each pipe. No portion of the gasket should extend into the groove on either pipe.
5. Loosely assemble all segments leaving one nut and bolt off to allow for “swing-over” feature.
6. With 1 nut and 1 bolt removed, use the “swing-over” feature to position housings over gasket and into
the grooves on both pipes.
7. Insert the remaining bolt to allow easy tightening of the nut. Be sure track head engages into housing
recess.
8. Tighten nuts alternately and equally maintaining metal-to-metal contact at the angle bolt pads.
1. Identify the actual location of the hanger based on the approved shop drawing. Mark the position for
2. Check the hanger size to confirm the depth of the hole to be drilled based on approved shop drawings
3. Check the hanger size to select the right drill bit. Then drill the hole according to the manufacturer’s
7. Drop-in Anchors shall not be used in hollow blocks and the surface to be checked prior to installation.
8. All the supports shall be taken from the structural members or beams
10. Identify the actual location of the cleats to be installed and do the marking for hanged point
11. Drill hole according to the size of bolt on the marked position.
c. Install the required pipe hanger based on shop drawing and pipe size.
1. Identify the actual location of the hanger based on the approved shop drawing. Mark the position for
2. Select the hanger based on the pipe size. Install the hanger rod to the angle piece.
4. Tighten the bolts and nut that hold the hanger rod and hanger evenly.
1. Painting Materials to be used on piping system should be as per approved Material submittal.
2. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are
between 10 and 35 deg C.
3. Do not apply paints in rain, fog, or mist; when relative humidity exceeds 85 percent; at temperatures
less than 3 deg C above the dew point; or to damp or wet surfaces.
4. Verify suitability of substrates, including surface conditions and compatibility, with finishes and
primers.
5. Proceed with coating application only after unsatisfactory conditions have been corrected.
7. Use applicators and techniques suited for paint and substrate indicated.
8. Allow primer paint to dry for some hours prior to proceed with the first coat.
11. Jotun Top Coat RED – 40 – 60 microns, Total = 150 - 180 microns.
12. After completing paint application, clean spattered surfaces. Remove spattered paints by washing,
scraping, or other methods. Do not scratch or damage adjacent finished surfaces.
13. Protect work of other trades against damage from paint application.
14. At completion of construction activities of other trades, touch up and restore damaged or defaced
painted surfaces.
1. Study the drawings carefully and install the pipes as per approved shop drawings.
2. Layout of pipe support location is based on the approved drawings and shall be used chalk line to
3. Measure location of supports and drill concrete slab and fix anchor bolt, threaded rods, and adjustable
hangers.
4. Clean the pipe internally after threading to remove burrs and foreign materials.
6. Clean agent containers and other accessories shall be installed as per the approved drawings and as per
manufacturer's recommendation.
7. Verify that the pressure gauge of cylinder is within the green range to ensure the gas filling
measurement.
8. Check the identification sticker available on the cylinder to cross check the gas quantity with approved
9. The location FM200 cylinder shall not obstruct the emergency escape route and means of egress.
10. Position the cylinder vertically on the plinth provided by Main Contractor and secure it firmly to the
wall.
12. After installation of cylinders fix the manifold. Main and reserve cylinders arrangement should be
properly arranged.
14. Seal all the openings with the fire stop materials to avoid gas leaking from the room.
Nozzle Installation
1. All Nozzles will be installed according to the approved shop drawings and NFPA standards.
2. Check for the proper model, style, orifice size and temperature rating prior to installation.
1. Check if the piping is installed as per approved shop drawing and installation is approved.
2. All the nozzle plugs need to be closed before starting the pneumatic pressure testing.
5. First pressure the pipe with air for 40 psi than observe for 10 Mins.
6. During this 10 Mins if pressure drop is less than 20% of initial pressure then Pneumatic Testing is pass.
7. If the pressure drop is more than 20% of initial pressure than apply soap solution in pipes joints to
8. Rectify the leak, then redo the Pressure testing until we get the desired result.
2. At each discharge nozzle, tie a piece of ribbon, so that it can flutter when the air is passing through the
nozzle, providing a visual indication.
3. Ensure temporary hoses are connected at the cylinder/air compressor and connected to the system to
be tested.
4. Once ready open the valve on the cylinder/air compressor to allow air slowly flow through the
pipework system.
5. As the air passes through the system the ribbon tied to the discharge heads should flutter, proving the
flow is continuous and that all system valves are in the correct direction.
7. Disconnect the temporary hoses and remove the ribbons from the discharge nozzles.
1. Prior to installation check the size of the cable as per approved submittal and shop drawings.
2. All wiring circuits are installed as per manufacturers and contractor recommendation.
3. Install G.I conduits as per the required site routing and pull the cable using pulling spring.
5. Identify the cables are with tags and terminates cables with ferrules.
6. Manual release unit is accessible always even fire condition. Locate all devices so that it will not be
subjected to damage.
8. Minor changes to piping works and supports layout as per actual condition at site, may be allowed,
9. Panel, Bells, Detector, Remote indicator, Identification label, warning signs were installed as per the
10. Check the required power supply 220 V single phase available to the panel and battery is charged to
11. Check the required provision is available in the panel for interfacing with the main fire alarm panel.
12. Check that EOL resistors are installed for fixed devices.
15. Fix the electromagnet release devices in Master cylinder. This Electromagnet release device will be
fixed in master cylinder during the time of handing over of the system.
16. Check the control panel and electromagnet release devices are interfaced properly and tested prior to
17. Fire & Fault signal should be interface with Main FACP. (Scope by Fire Alarm Contractor)
2. Install the Manual call points as per the approved shop drawings.
3. Manual call points to be installed @ wall with 1.2M from finish floor.
6. Set the address number and mark in the shop drawings for commissioning and inspection purpose.
1. Install the smoke detectors base as per the approved shop drawings.
2. Install the smoke detector inside the trench as per regulation either top of the soffit level or mid of the
5. Set the address number, install the detectors, and mark address numbers in the shop drawings for
1. Install the strobe light / horn strobe as per the approved shop drawings.
2. Strobe Light / horn strobe to be installed @ wall with 2.3M from finish floor level.
1. Check the panel and remove all internal components before installing the back box of control panel if
2. Install the back box of the panel at the height of 1800mm from finish floor level to the top of the panel.
3. Check the installation and alignment of the panel, clean inside the control panel. Pull all cable to panel
4. The mock up installation to be carried out for the panel installation to get the consultant approval prior
5. Check all continuity of all loop or circuit & Fix all internal cards & parts etc.
6. Complete the cable terminations (except power supply and battery connection) Check the battery and
its terminals.
7. Ensure the terminations inside control panel are completed as per approved.
8. Complete the third-party connection with Building fire Alarm System with label. Volt free contact will
be provided to control the Motorized damper/ Access doors. (Cable needs to pull to panel by MEP
Contractor)
9. Make the system ready for commissioning & inform the commission engineer to start the programming
APPENDIX A
Site Logistics Plan
APPENDIX B
CRISIS PLAN
APPENDIX C
(To be Submitted)
APPENDIX- D
RISK ASSESSMENT
APPENDIX-E
TECHNICAL INFORMATION
(To be Submitted)
APPENDIX-F
APPENDIX-G
(To be Submitted)
APPENDIX-H