The report summarizes the progress on a drainage project in Sto. Nino, Hagonoy, Bulacan. As of August 28, 2022, 55.6% of the total project has been completed, including 74% of drainage flooring, 72% of drainage siding and fixed covers, and 60% of movable covers, while 0% of PCCP has been done.
The report summarizes the progress on a drainage project in Sto. Nino, Hagonoy, Bulacan. As of August 28, 2022, 55.6% of the total project has been completed, including 74% of drainage flooring, 72% of drainage siding and fixed covers, and 60% of movable covers, while 0% of PCCP has been done.
The report summarizes the progress on a drainage project in Sto. Nino, Hagonoy, Bulacan. As of August 28, 2022, 55.6% of the total project has been completed, including 74% of drainage flooring, 72% of drainage siding and fixed covers, and 60% of movable covers, while 0% of PCCP has been done.