ACCOMPLISHMENT REPORT

AS OF AUGUST 28, 2022

1. STO.NINO, HAGONOY, BULACAN


TOTAL LENGTH: 1,402.26m

ITEM % IN PROJECT ACTUAL % OVERALL %

DRAINAGE FLOORING 20% 74% 14.80%


(1,042.9m)
DRAINAGE SIDING 20% 72% 14.40%
(1,006.33m)
DRAINAGE FIXED 20% 72% 14.40%
COVER
(1,006.33m)
DRAINAGE MOVABLE 20% 60% 12.00%
COVER
(836.24m)
PCCP 20% 0% 0

TOTAL 100% 55.60%

PROGRESS REPORT AS OF THIS DATE: