The work schedule outlines the tasks and timelines for construction of an Earth Enclave project in March 2023. Key activities include RCC core wall construction from February 14 to March 31 including rehabilitation of the club house and sale building, with concrete pouring in multiple levels. Structural steel erection is scheduled from February 25 to April 2 along with deck sheet work. Floor slab work is planned from February 22 to March 31 for various levels including column and beam work and concrete pouring.
The work schedule outlines the tasks and timelines for construction of an Earth Enclave project in March 2023. Key activities include RCC core wall construction from February 14 to March 31 including rehabilitation of the club house and sale building, with concrete pouring in multiple levels. Structural steel erection is scheduled from February 25 to April 2 along with deck sheet work. Floor slab work is planned from February 22 to March 31 for various levels including column and beam work and concrete pouring.
The work schedule outlines the tasks and timelines for construction of an Earth Enclave project in March 2023. Key activities include RCC core wall construction from February 14 to March 31 including rehabilitation of the club house and sale building, with concrete pouring in multiple levels. Structural steel erection is scheduled from February 25 to April 2 along with deck sheet work. Floor slab work is planned from February 22 to March 31 for various levels including column and beam work and concrete pouring.
The work schedule outlines the tasks and timelines for construction of an Earth Enclave project in March 2023. Key activities include RCC core wall construction from February 14 to March 31 including rehabilitation of the club house and sale building, with concrete pouring in multiple levels. Structural steel erection is scheduled from February 25 to April 2 along with deck sheet work. Floor slab work is planned from February 22 to March 31 for various levels including column and beam work and concrete pouring.
EARTH ENCLAVE 49.75 days Tue 14-02-23 Tue 04-04-23 RCC CORE WALL 45.88 days Tue 14-02-23 Fri 31-03-23 REHAB BUILDING 9 days Wed 01-03-23 Fri 10-03-23 Club House Floor to 8th Floor 9 days Wed 01-03-23 Fri 10-03-23 Reinforcement Work 3 days Wed 01-03-23 Sat 04-03-23 Lifting of Internal Platform 2 days Sat 04-03-23 Mon 06-03-23 Fixing of Embedded Plate 1 day Mon 06-03-23 Tue 07-03-23 Fixing of Shuttering 2 days Tue 07-03-23 Thu 09-03-23 Concreting Work 1 day Thu 09-03-23 Fri 10-03-23 SALE BUILDING 45.88 days Tue 14-02-23 Fri 31-03-23 From +26.775 Lvl to +30.450 Lvl. 14 days Tue 14-02-23 Mon 27-02-23 Deshuttering Work 2 days Tue 14-02-23 Thu 16-02-23 Reinforcement Work 7 days Wed 15-02-23 Wed 22-02-23 Lifting of Platform 2 days Tue 21-02-23 Thu 23-02-23 Fixing of Embedded Plate 1 day Mon 20-02-23 Tue 21-02-23 Fixing of Shuttering 5 days Tue 21-02-23 Sun 26-02-23 Concreting Work 1 day Mon 27-02-23 Mon 27-02-23 From +30.450 Lvl to +34.125 Lvl. 12 days Tue 28-02-23 Sat 11-03-23 Deshuttering Work 1 day Tue 28-02-23 Tue 28-02-23 Reinforcement Work 5 days Tue 28-02-23 Sat 04-03-23 Lifting of Platform 1 day Sun 05-03-23 Sun 05-03-23 Fixing of Embedded Plate 1 day Sun 05-03-23 Sun 05-03-23 Fixing of Shuttering 5 days Mon 06-03-23 Fri 10-03-23 Concreting Work 1 day Sat 11-03-23 Sat 11-03-23 From +34.125 Lvl to +37.800 Lvl. 10 days Sun 12-03-23 Tue 21-03-23 Deshuttering Work 1 day Sun 12-03-23 Sun 12-03-23 Reinforcement Work 4 days Sun 12-03-23 Wed 15-03-23 Lifting of Platform 1 day Thu 16-03-23 Thu 16-03-23 Fixing of Embedded Plate 1 day Thu 16-03-23 Thu 16-03-23 Fixing of Shuttering 4 days Fri 17-03-23 Mon 20-03-23 Concreting Work 1 day Tue 21-03-23 Tue 21-03-23 From +37.800 Lvl to +41.475 Lvl. 10 days Wed 22-03-23 Fri 31-03-23 Deshuttering Work 1 day Wed 22-03-23 Wed 22-03-23 Reinforcement Work 4 days Wed 22-03-23 Sat 25-03-23 Lifting of Platform 1 day Sun 26-03-23 Sun 26-03-23 Fixing of Embedded Plate 1 day Sun 26-03-23 Sun 26-03-23 Fixing of Shuttering 4 days Mon 27-03-23 Thu 30-03-23 Concreting Work 1 day Fri 31-03-23 Fri 31-03-23 STRUCTURAL STEEL WORK 37 days Sat 25-02-23 Sun 02-04-23 STEEL MEMBER ERRECTION 34 days Sat 25-02-23 Thu 30-03-23 GF to 1st Floor 9 days Sat 25-02-23 Sun 05-03-23 1st Floor to P-1 Level 5 days Wed 01-03-23 Sun 05-03-23 P-1 Level to P-2 Level 8 days Thu 02-03-23 Thu 09-03-23 P-2 Level to P-3 Level 12 days Mon 27-02-23 Fri 10-03-23 P-3 Level to P-4 Level 29.88 days Mon 06-03-23 Tue 04-04-23 P-4 Level to P-5 Level 10 days Sat 11-03-23 Mon 20-03-23 P-5 Level to P-6 Level 10 days Tue 21-03-23 Thu 30-03-23 DECK SHEET WORK 27 days Mon 06-03-23 Sun 02-04-23 1st Floor Lvel 2 days Mon 06-03-23 Wed 08-03-23 P-1 Level 2 days Wed 08-03-23 Fri 10-03-23 P-2 Level 3 days Fri 10-03-23 Mon 13-03-23 P-3 Level 5 days Mon 13-03-23 Sat 18-03-23 P-4 Level 6 days Wed 15-03-23 Tue 21-03-23 P-5 Level 6 days Tue 21-03-23 Mon 27-03-23 P-6 Level 6 days Mon 27-03-23 Sun 02-04-23 FLOOR SLAB WORK 38 days Wed 22-02-23 Fri 31-03-23 1st Floor Level Balance Part 13 days Sat 25-02-23 Thu 09-03-23 Column Reinforcement Work GF to 1st Floor 3 days Sat 25-02-23 Mon 27-02-23 Column Shuttering Work GF to 1st Floor 2 days Mon 27-02-23 Tue 28-02-23 Column Concrete Work GF to 1st Floor 2 days Tue 28-02-23 Wed 01-03-23 External Pheripherial Beam Bottom Fixing 5 days Thu 02-03-23 Mon 06-03-23 External Pheripherial Beam Reinforcement Work 4 days Sat 04-03-23 Tue 07-03-23 External Pheripherial Beam Shuttering Work 3 days Mon 06-03-23 Wed 08-03-23 Slab Reinforcement Work 1 day Wed 08-03-23 Wed 08-03-23 Slab Concrete Work 1 day Thu 09-03-23 Thu 09-03-23 P-1 Level Balance Part 20 days Tue 28-02-23 Sun 19-03-23 Column Reinforcement Work 1st Floor to P-1 Level 11 days Tue 28-02-23 Fri 10-03-23 Column Shuttering Work 1st Floor to P-1 Level 11 days Wed 01-03-23 Sat 11-03-23 Column Concrete Work 1st Floor to P-1 Level 10 days Thu 02-03-23 Sat 11-03-23 External Pheripherial Beam Bottom Fixing 4 days Sun 12-03-23 Wed 15-03-23 External Pheripherial Beam Reinforcement Work 4 days Mon 13-03-23 Thu 16-03-23 External Pheripherial Beam Shuttering Work 3 days Wed 15-03-23 Fri 17-03-23 Slab Reinforcement Work 3 days Thu 16-03-23 Sat 18-03-23 Slab Concrete Work 3 days Fri 17-03-23 Sun 19-03-23 P-2 Level 29 days Wed 22-02-23 Wed 22-03-23 Column Reinforcement Work P-1 to P-2 Level 26 days Wed 22-02-23 Sun 19-03-23 Column Shuttering Work P-1 to P-2 Level 25 days Fri 24-02-23 Mon 20-03-23 Column Concrete Work P-1 to P-2 Level 25 days Fri 24-02-23 Mon 20-03-23 External Pheripherial Beam Bottom Fixing 21 days Wed 01-03-23 Tue 21-03-23 External Pheripherial Beam Reinforcement Work 18 days Fri 03-03-23 Mon 20-03-23 External Pheripherial Beam Shuttering Work 17 days Sun 05-03-23 Tue 21-03-23 Slab Shuttering Work 13 days Sun 26-02-23 Fri 10-03-23 Slab Reinforcement Work 21 days Wed 01-03-23 Tue 21-03-23 Slab Concrete Work 16 days Tue 07-03-23 Wed 22-03-23 P-3 Level 19 days Thu 09-03-23 Mon 27-03-23 Column Reinforcement Work P-2 to P-3 Level 15 days Thu 09-03-23 Thu 23-03-23 Column Shuttering Work P-2 to P-3 Level 15 days Fri 10-03-23 Fri 24-03-23 Column Concrete Work P-2 to P-3 Level 15 days Sat 11-03-23 Sat 25-03-23 External Pheripherial Beam Bottom Fixing 14 days Mon 13-03-23 Sun 26-03-23 External Pheripherial Beam Reinforcement Work 14 days Tue 14-03-23 Mon 27-03-23 External Pheripherial Beam Shuttering Work 10 days Sat 18-03-23 Mon 27-03-23 Slab Shuttering Work 10 days Sat 11-03-23 Mon 20-03-23 Slab Reinforcement Work 15 days Mon 13-03-23 Mon 27-03-23 Slab Concrete Work 10 days Sat 18-03-23 Mon 27-03-23 P-4 Level 13 days Sun 19-03-23 Fri 31-03-23 Column Reinforcement Work P-3 to P-4 Level 10 days Sun 19-03-23 Tue 28-03-23 Column Shuttering Work P-3 to P-4 Level 9 days Mon 20-03-23 Tue 28-03-23 Column Concrete Work P-3 to P-4 Level 9 days Mon 20-03-23 Tue 28-03-23 External Pheripherial Beam Bottom Fixing 9 days Tue 21-03-23 Wed 29-03-23 External Pheripherial Beam Reinforcement Work 8 days Wed 22-03-23 Wed 29-03-23 External Pheripherial Beam Shuttering Work 8 days Thu 23-03-23 Thu 30-03-23 Slab Shuttering Work 8 days Wed 22-03-23 Wed 29-03-23 Slab Reinforcement Work 8 days Fri 24-03-23 Fri 31-03-23 Slab Concrete Work 5 days Mon 27-03-23 Fri 31-03-23 REHAB CORE STAIRCASE AND LOBBY WORK 16 days Mon 20-02-23 Tue 07-03-23 P-4 Level 8 days Mon 20-02-23 Tue 28-02-23 Shuttering Work 4 days Mon 20-02-23 Fri 24-02-23 Reinforcement Work 3 days Fri 24-02-23 Mon 27-02-23 Concrete Work 1 day Mon 27-02-23 Tue 28-02-23 P-5 Level 7 days Wed 01-03-23 Tue 07-03-23 Shuttering Work 3 days Wed 01-03-23 Fri 03-03-23 Reinforcement Work 3 days Sat 04-03-23 Mon 06-03-23 Concrete Work 1 day Tue 07-03-23 Tue 07-03-23 SALE CORE LOBBY AND STAIRCASE WORK 36.88 days Thu 23-02-23 Fri 31-03-23 P-3 Level 10 days Thu 23-02-23 Sun 05-03-23 Shuttering Work 4 days Thu 23-02-23 Mon 27-02-23 Reinforcement Work 5 days Mon 27-02-23 Sat 04-03-23 Concrete Work 0.13 days Sun 05-03-23 Sun 05-03-23 P-4 Level 10 days Sun 05-03-23 Wed 15-03-23 Shuttering Work 4 days Sun 05-03-23 Thu 09-03-23 Reinforcement Work 5 days Thu 09-03-23 Tue 14-03-23 Concrete Work 1 day Tue 14-03-23 Wed 15-03-23 P-5 Level 8 days Thu 16-03-23 Thu 23-03-23 Shuttering Work 3 days Thu 16-03-23 Sat 18-03-23 Reinforcement Work 4 days Sun 19-03-23 Wed 22-03-23 Concrete Work 1 day Thu 23-03-23 Thu 23-03-23 P-6 Level 8 days Fri 24-03-23 Fri 31-03-23 Shuttering Work 3 days Fri 24-03-23 Sun 26-03-23 Reinforcement Work 4 days Mon 27-03-23 Thu 30-03-23 Concrete Work 1 day? Fri 31-03-23 Fri 31-03-23 U.G. TANK WORK 34 days Sat 25-02-23 Thu 30-03-23 U.G. TANK WALL WORK 34 days Sat 25-02-23 Thu 30-03-23 Fire Fighting Water Tank No. 3 7 days Sat 25-02-23 Fri 03-03-23 Fire Fighting Water Tank No. 1 7 days Sat 04-03-23 Fri 10-03-23 Domestic Water Tank for A-Wing Tower 5 days Sat 11-03-23 Wed 15-03-23 Domestic Water Tank for B-Wing Tower 5 days Thu 16-03-23 Mon 20-03-23 Rain Water Harvesting Tank 5 days Tue 21-03-23 Sat 25-03-23 Flush Water Tank for A-Wing Tower 5 days Sun 26-03-23 Thu 30-03-23 U.G. TANK SLAB WORK 30 days Wed 01-03-23 Thu 30-03-23 Fire Fighting Water Tank No. 2 10 days Wed 01-03-23 Fri 10-03-23 Fire Fighting Water Tank No. 3 10 days Sat 11-03-23 Mon 20-03-23 Fire Fighting Water Tank No. 1 10 days Tue 21-03-23 Thu 30-03-23