Professional Documents
Culture Documents
DOD-MST-INS-004, MST For Insta. of Tubes, Pipes & Pressure Testing.-Rev.0
DOD-MST-INS-004, MST For Insta. of Tubes, Pipes & Pressure Testing.-Rev.0
METHOD STATEMENT
FOR
INSTALLATION OF IMPULSE LINE, AIR TUBING
AND PRESSURE TESTING
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 PROCCEDURE
7.0 DOCUMENTATION
The purpose of this Method Statement is to accomplish the Installation of Impulse line, Air
Tubing and pressure testing of Process and Field instrument in accordance with
Project Specifications, Codes and Standards
2.0 SCOPE
This scope covers Installation of Impulse line, Air Tubing and pressure testing of
Process and Field instruments, within subcontractor’s scope of work for RasGas
Onshore Expansion Project, Phase-2.
3.0 REFERENCES
5 RESPONSIBILITIES
5.2 E&I MANAGER / DEPUTY E&I MANAGER: Shall be responsible for the
implementation of this Method Statement and ensure the required HSE and Quality
standard, practices and procedures are maintained at each stage of the instrumentation
works.
5.3 SENIOR INST ENGINEER: Shall be responsible for the implementation of this Method
Statement and correct working techniques and shall ensure that the instrumentation works
are carried out as per approved IFC drawings, Project Specifications & Standards. He shall
be responsible for overall site supervision and work execution with strict adherence to this
method statement and required HSE & Quality standards, practices and procedures at site.
He shall arrange for necessary inspection & documentation.
5.4 INST SITE- ENGINEER / SUPERINTENDENT: Shall be responsible for the execution of
instrumentation works as per approved IFC drawings, Project Specification & Standards. He
shall be responsible for supervision of execution works with strict adherence to this method
statement and required HSE & Quality practices and procedures at site. He shall be
responsible to raise RFI for the works to be inspected and attend punch- points as required.
5.5 INSTRUMENT FOREMAN: Shall be responsible for the execution of the instrumentation
work as per approved IFC drawings ,specifications & standards, method statement and
responsible for implementation of required HSE and Quality Standards at site.
6 ERECTION PROCEDURE
6.1 Safety
6.1.1 All equipment and accessories shall be verified and of adequate capacity according
to HSE requirements. Refer JSA No.: DOD-MST-INS-004
6.1.2 All personnel involved in Installation of field Instruments shall be informed of hazards
and will adopt preventive measures while undertaking subject instrumentation works.
6.1.3 All personnel must use their Safety Equipments and Personnel Protective Equipments
(PPE).
6.1.4 Tool Box meeting shall be held daily, prior to start of the work
6.2 MATERIALS
All Materials shall be supplied by M/s CTJV based on the M/s RasGas Standard,
and Project purchase documents & approved manufacturer’s specification.
All materials purchased by Dodsal will be approved before usage by
CTJV vía “MAR” (Material Approval Request) form no: DOD-RGX-F037
6.4.1 Upon receipt at the storage and handling area, the impulse line and air tubing
accessories shall be inspected by material QC inspector and recorded in the
MIR (Material Receipt Inspection Report) Form No: DOD-RGX-F051. And if
there is any mechanical damage / missing accessories, they shall be recorded
on the OSDR (Overage /Shortage/Damage Report) form no: DOD-RGX-F049
respectively.
6.4.2 Prior to start of Impulse Line installation, it is a must to identify all necessary
tools needed. All lifting harness and safety harness shall be updated. Obtain
the required work permits and safety clearances.
6.4.3 Cordon-off the area covered by the scope of working. Safety sign stating
“Impulse line work in progress” and “Do not enter “.will be posted in all
corner and side visible to anyone.
6.4.4 Physical damage shall be checked and the material traceability shall be
6.4.5 All impulse points for flow and pressure measurement shall be fitted with isolation
valves mounted on the fluid pipeline.
6.4.6 In order to prevent impulse tubing from being plugged at the drain or stagnated by
gas, the piping shall have gradient of 1/10 (minimum 1/25)
6.4.7 In liquid impulse pipe, air bleeder valves should be installed at the highest part and
drain valves should be installed at the lowest parts. In gas impulse pipe, drain valves
should be installed at the lowest part and also in the vicinity of the instruments.
6.4.9 Instrument Impulse line shall be kept as short as possible and the number of
joints shall be kept to a minimum. For impulse line, supports shall be
provided for every 1 meter Interval.
6.4.10 Prior to installation, the material shall be checked against the material
schedule to ensure it is to the correct specification and pressure rating.
6.4.11 Pipe bender’s shall be used for bending pipes which shall be free from kinks or
flats
6.4.12 The Impulse line / tubing shall be inspected and particular attention shall be
paid to the following:
Section of pipes shall be cut square, have the ends reamed and be free from burr or
grease.
Impulse lines shall slope towards or away from the tapping point as applicable. The
minimum slope shall be 1 in 12 or as specified in the installation drawing.
Where threaded fittings are used thread forms are compatible and approved sealant
to be used.
For longer lengths the tubing shall be supported approximately one-meter intervals.
Non-conductive space material shall be applied to isolate tubing from the support.
Impulse lines shall be grouped closely together.
Where applicable vent and drain ports are installed as per the standard installation
drawings.
Vent and drains are installed at the highest and lowest points of the piping
arrangement.
Long piping/tubing runs which have intermediate union connections shall have tubing
off-sets to facilitate connection and disconnection.
Sufficient access shall be maintained to minimize deleterious effects from hot or cold
surfaces, condensate and etc.
All tubing fittings and components in any tubing assembly shall be Swagelok as per
Project Specification RG6-S-00-1370-010,
6.5.1 The Instrument headers and sub-headers shall be installed as per the approved
instrument hook-up and air supply layout.
6.5.2 Prior to installation, the material shall be checked against the material schedule to
ensure it is correct specification and pressure testing.
6.5.3 Short lengths of flexible armored tubing may be used on places, where sufficient movement
is not available in standard tube. Air flow shall not be restricted through fittings.
6.5.4 Tubing which run together, shall be installed vertically one above the other. More than three
runs shall be installed on tray. Any joints if necessary , shall be staggered.
6.5.5 The tubing runs should not exceed 100 m (300 ft.). Volume boosters may be used to give the
required response provided other control characteristics are not down graded.
6.5.6 The pipe line shall be thoroughly cleared before installation of equipment. When the pipe line
is flushed, the equipment shall be replaced by a dummy pipe.
6.5.7 Where a plastic sheath is used, the sheath shall continuously cover the tube to the seal
within a fitting.
6.5.8 Teflon tape shall not be used downstream of the filter regulator.
6.5.9 Air supply tubing shall be 6mm O.D for transmitter and receiver applications and 10 mm O.D
for controller and control valve installations as per standard drawings and specifications.
6.5.10 Piping downstream of instrument isolating valves shall be installed direct or with a “Swan
Neck “down to the filter regulator.
6.5.11 Pneumatic tubing should be run away from hot environments and potential fire risk areas
and should be located away from places where it may be subjected to mechanical damage ,
split liquids or corrosive gases. Tubing should be run so that it does not interfere with access
to or removal of other equipments.
6.5.13 The piping and tubing shall be inspected and particular attention paid to the
following:
All main and sub-headers shall be sloped (minimum 1:12 or as specified in the installation
drawings) and provided with low point drains.
All header and supply take-offs shall be connected to the top of mains or sub-header
Instrument air piping shall not be pocketed (i.e. shall not contain U-sections)
Instrument air piping shall not be installed underground (Without Ras Gas permission)
From main instrument air header to the instrument air manifold NPS 1” or ¾” pipe shall be
installed.
One NPS ½” spare valve shall be provided on each instrument air manifold.
Single core tubes shall be supported and protected by tube tray. The instrument air
manifold shall be provided 6 or 12 points valve with drain valve.
TAG plate showing instrument TAG No. to be installed at instrument air manifold.
Instrument Air manifold may be preferably installed near instrument junction box. Air
tubing way to be commonly used with cable way.1” valve shall be installed by piping
at every 6 meters on main instrument air header.
Air supply and signal transmission lines shall be routed to minimize exposure to
accidental
impact damage.
6.5.14 Prior to testing, the instrument air tubing connected to instrument shall be
disconnected and the air supply sub-header must be blown-down to ensure no
debris or water is present as per MST: DOD-MST-INS-004
6.5.15 Pressurize the sub-header using dried filtered Air or Nitrogen with test gauge at the
end and isolate, held for 3 minutes. The pressure shall not fall.
6.6.1 Prior to start of leak testing job, it is a must to identify all necessary tools
needed. All calibration stickers and certificate for shackle, lifting harness and
safety harness shall be updated
6.6.3 Redundant evaluation and verification made for the PID and datasheet of the
instrument. Ensure that all the impulse line / tubing is completed as per hook-up.
6.6.4 Cordoned the area covered by the scope of testing. Safety sign stating “Pressure Testing is
On Going “, and “Do not Enter“ will be posted in all corner and side visible to anyone
6.6.6 All instruments impulse line shall be pressure tested using Nitrogen.
6.6.7 Prior to testing, the instrument shall be disconnected and the impulse piping blown through
using compressed air to ensure no debris is present.
6.6.8 The Nitrogen Cylinder, complete with regulator and test gauge, shall be connected to a
drain or vent port and the impulse loop evacuated of air.The pressure gauge should be
ranged such that the test pressure indicates within 40 to 80% of the calibrated range.
The calibrated test pressure gauge shall be used.
6.6.9 The impulse line/ tubing shall be pressurized to a range of 110% of the maximum design
pressure. All the equalizing manifold valves shall be kept in open position at the time of
testing.
The applied pressure should not exceed the allowable maximum pressure range of
instrument and to specified pressure range at instrument data sheet.
Apply soap solution or other leak determining solution through unions, Tees, valves or
nipples to identify whether the system has leak or not. Preparation of tapping point list.
The Instrument Impulse line / tubing shall be isolated from the pressure source and held for
3 minutes. The pressure in the system shall not fall.
Perform a soap test at the compression fittings and, if no leakage is found continue
increasing to full test pressure.
In the presence of leak slowly close the valve and drain the air inside the
line before proceeding to tightening loose bolts or part of the fittings.
If leakage is found, the leakage point shall be identified using the soap water solution
snooping at the joints and the joints shall be repaired and tested again till the joints are
away from leak.
Check for any leakage again, if leak is observed, that joint shall be isolated
and right marking has to be given. For the rest of testing, if found leaks, this
has to be sealed and testing has to continue until the desired result is obtained.
After completion of the test, the impulse line / tubing shall be blown through and dried using
compressed air. Pressure testing records shall be recorded on the form no: DOD-RGX-
F421
6.7 Certification:
6.7.1 After successful completion of each test, the instrument shall be marked with a
colored label bearing the date of the test and the initials of the witnessing party.
6.8.3 Pipe and Pipe fittings like, Ferrules and accessories shall be checked.
6.8.10 Yellow color Sticker shall be fixed after Acceptance of Pressure Testing.
7 DOCUMENTATION