Abstract of Quantities

sr. # Description no Length Width Height Quantity unit remarks

R.c.c. work 1:2:4 excludig


steel and its bending but length of
including centering and beam = clear
shuttering and binding of span
01- bars +2bearings
T-Beam ribs 3 6.9 0.35 0.75 5.43375 cu.m
Fillets 6 6.9 0.5*.15*.15 0.466 cu.m
deck slab 1 6.9 7.7 0.2 10.626 cu.m
railing posts 12 0.15 0.15 1.2 0.324 cu.m
kerbs 2 6.9 0.35 0.2 0.966 cu.m
Total 17.81575 cu.m
2- R.C.C. 1:2:4 in wearing coa 1 6.9 7 0.1 4.83 cu.m
40 mm diamater G.I. pipes
3- in railing 8 6.9 55.2 R.m
Steel reinforcement bars
4- including binding
Beam @ 2.5 % 3 4.502465625 13.507397 q 78.5 q/cu.m
Slab @ 1% 8.34141 8.34141 q
railing posts @ 1 % 0.25434 0.25434 q
Total 22.103147 q

Abstract of Cost
Sr.# Item of Work Quantunit Rate Per Amount

R.c.c. work 1:2:4 excludig


steel and its bending but
including centering and
shuttering and binding of
1- bars 18 cu.m 675 cu.m 12025.631 PRS
2- C.C. 1:2:4 in wearing Coat 4.83 cu.m 450 cu.m 2173.5 PRS
40 mm diamater G.I. pipes
3- in railing 55.2 R.m 25 Rm. 1380 PRS
Steel reinforcement bars
4- including binding 22 q 515 q 11383.121 PRS
Total 26962.252 PRS
5 % contingencies 5% 1348.1126 PRS

Grand Ttoal 28310 PRS