I. Project Summary
II. Rationale
The Local Government Unit of Bantay, Ilocos Sur in coordination with the
Municipal Social Welfare and Development Office and Municipal Environment and Natural
Resources Office, would like to conduct a Tree Planting Program, Drainage Canal and
Community Cleaning through Cash for Work. Hence, this proposal.
The purpose of the activity is to help indigent families to solve their immediate
problems. And the main goal of this program is to provide financial assistance to the indigent
families in order for them to have a time to buy such as basic needs. On the other hand, as
part of that said program, the Barangay Health Worker initiated the project “Cash for Work”
for Tree Planting Program, Drainage Canal and Community Cleaning. The beneficiaries
target two (2) weeks to ensure the successful implementation of the project.
The program will be in form of Tree Planting Program, Drainage Canal and
Community Cleaning. The program will run for two (2) weeks. The program will be
monitored by the Municipal Social Welfare and Development Office from the start until the
conduct of the program be fully executed.
And the main objectives of this program are to provide temporary employment to
farm workers/laborers and especially those families under the low income earners category or
indigent families and to encourage community preparation in implementing a community
defined project.
IV. Project Components
Drainage Canal To clean the canal and to LGU and MSWD of Bantay
prevent floods
Community Cleaning To keep environment clean LGU and MSWD of Bantay
V. Budgetary Requirement/s
Particulars Unit Cost (in Php) Quantity Total Cost (in Php)
Financial Assistance Php 5,000.00 20 Php 100, 000.00
Tools (set) Php 5, 000.00 5 Php 25, 000.00
Fertilizers 50/kg 30 Php 1,500.00
Seeds/plants 100 235 Php 23, 500.00
VI. Recommendation
The proposed project amounting to Php 150,000.00 initiated by the MSWD and LGU
Bantay is hereby recommended for approval.
JACQUELYN A. PAA
Recommending Approval:
Activities Jan.03 Jan.1 Jan.17 Jan.24 Jan.31 Feb.07 Feb.14 Feb.21 Feb.28 Mar.07 Mar.14
0
1 Social
Preparation
Activities
2 Proposal
Preparation
3 Accessing of
funding
support
4 Implementatio
n phase
5 Monitoring and
evaluation