Volume 1 Tender & Contract Conditions
Volume 1 Tender & Contract Conditions
Contract Documents
Volume 1
Tender and Contract Conditions
December 2022
Employer: Contractor:
Sewerage and Recycled Water Nael Construction and
Projects Department Contracting LLC.
P.O. Box 67, Dubai, UAE P.O. Box 29703, Dubai, UAE
Tel: 04-8815555 Tel: 04-3599940
Fax: 04-2246666 Fax: 04-3599941
Consultant
Khatib & Alami (CEC) l P.O. Box 5091 l Dubai l Tel: 04-4252222l Fax: 04-4252233
__________________________________________________________________________________
PROJECT: DS 196/2
NADD AL SHIBA 3rd SEWERAGE AND STORMWATER SYSTEM
CONTRACT DOCUMENTS
GENERAL INDEX
General Index
-i-
اﻟﻤﺤﺘﻮ ﻳﺎت
CONTENT
Content
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
BRIEF SCOPE OF WORKS
BRIEF SCOPE OF WORKS:
The project Nadd Al Shiba 3rd Sewerage And Storm water System covers an approximate area of
340 ha. The project Nadd Al Shiba 3rd Sewerage And Storm water System project serves the
communities of 616. The communities comprise of different land uses like residential, commercial
and other public facilities.
The gravity storm network designed to serve Nadd Al Shiba development, Al Manama road and a
small area of Al Warsan 2&3 during the storm event, this network is the downstream of
International City and Al Warsan 2&3, the main line of the drainage system proposed in Al
Manama Road will operate as an evacuation line to evacuate the existing International city pond
and the proposed ponds in Al Wasran 2&3 areas in the off-peak storm event. The Length of the
proposed main gravity network is almost 30.70 km and the diameter ranging from 250 mm to
1500mm (excluding Gully connection Pipe Length).
The scope of work under Dubai Municipality (DM) does not include the gullies, however tapping
lines from the manholes / land drain pipes have been provided, the gullies installation will be along
with the road contract.
Construction of the proposed Nadd Al Shiba Storm Water Pump Station (near the existing
Pumping station DB-21)
Construct SWD Pump station near the existing pumping station DB-21 including all Civil & Electro-
Mechanical work with associated works complete as shown on drawings, specification and
standards; including (but not limited to) the following:
Pump station capacity of 3,600 lps with pump configuration of 3 no. duty & 1no. assist pump.
The above scope of WORKS shall include supply, installation, temporary WORKS and all necessary
testing, commissioning, interfacing with other Contracts and handing over on successful completion of
the WORKS.
Note:- Please be noted that the quantities mentioned above are indicative only. The Tenderer to refer
the BOQ and Drawings for the relevant quantities.
PART- A
INSTRUCTIONS TO TENDERERS
1. General عام.1
One set of the following Tender Documents is :تتضمن وثائق العطاء ما يلي
issued for tendering: المناقصة وشروط العقد:المجلد األول
Volume 1 Tender and Contract Conditions
المواصفات:المجلد الثاني
Volume 2 Specifications
Volume 3 Bills of Quantities جداول الكميات:المجلد الثالث
Volume 4 Drawings المخططات:المجلد الرابع
Volume 5 Soil Investigation Report تقرير فحوصات التربة:المجلد الخامس
الغموض والتباين.4
4. Doubt and Obscurities
Should there be any doubt or obscurity in the في حال وجود أي غموض أو تباين في وثائق العطاء أو إلى
meaning of any of the tender documents or as to أي شيء ينبغي القيام به أو عدم القيام به أو إلى أ ية
anything to be done or not to be done or as to any
فينبغي على المناقص إرسال،مسألة أو شيء آخر
other matter or thing, the Tenderer must set forth
استفساراته خطيا إلى المهندس في موعد ال يقل عن
such doubt or obscurity in writing and submit the
same to the Engineer not later than Ten (10) ،) عشرة أيام من الموعد المحدد لتقديم المناقصة10(
days before the date stipulated for the delivery of وسيرد خطيا (كتابيا) على االستفسارات والشروحات
Tenders. The replies to such written queries, the
والتوضيحات وتقديم نسخ من الوثائق أو المخططات
explanations and clarifications given and copies of
documents or drawings shown at meetings will be
من خالل إشعار يصدر إلى جميع المناقصين في موعد ال
distributed as Notices to Tenderers to all ) خمسة أيام من الموعد المحدد لتقديم5( يقل عن
Tenderers not later than Five (5) days before the .المناقصة
date stipulated for delivery of Tenders. No
Instructions to Tenderers (CESMM – RM-Cons.)
ECS March 2022,
A2
OPEN DATA / بيانات مفتوحة
instruction, clarification or other information given إن أي تعليمات أو توضيحات أو معلومات أخرى تعطى
verbally by the Engineer or any of his assistants at
شفويا من المهندس أو أي من مساعديه في أي اجتماع
any meeting or discussions held in terms of this
أو مناقشات ال تعتبر ملزمة أو تؤخذ باالعتبار في إعداد
clause shall be binding or taken into account in
preparing and evaluating Tenders unless and until وتقييم المناقصات ما لم تؤكد خطيا من المهندس
such instruction, clarification or information is .وترسل لجميع المناقصين
confirmed in writing by the Engineer to all
كما أن أي إجراء بصدد توضيح وتفسير وثائق العطاء ال
Tenderers. In no case will any procedure in
يعطي المناقصين الحق في المطالبة بتمديد الموعد
connection with clarification and interpretation of
tender documents give the right to Tenderers to .المحدد لتقديم المناقصات
claim an extension of the time set for submitting ال يجوز للمهندس الرد على أي استفسار يرد بعد الوقت
Tenders. The Engineer shall not reply to any
المحدد وال يخول ذلك المناقص إجراء أي تحفظات أو
query submitted after the stipulated time and this
تغييرات أو إيضاحات بشأن مناقصته.
will not entitle the Tenderer to make any
qualifications, changes or clarifications to his
tender.
الكميات.5
5. Quantities
كميات األشغال التي ستنفذ بموجب هذا العقد وردت في
The quantities of the Works to be carried out
under this Contract are given in the Tender وثائق المناقصة ومقاسه وفقا لطريقة القياس القياسية
Documents, and measured in accordance with Civil )للهندسة المدنية (الطبعة الثالثة
Engineering Standard Method of Measurement
Civil Engineering Standard Method of
(3rd Edition) amended to suit local DM practices
Measurement (3rd Edition)
and procedures.
.والتي عدلت لتتوافق مع ممارسات وإجراءات بلدية دبي
6. Pricing التسعير.6
The rates and prices set down by the Tenderer
تعتبر أسعار البنود وأسعار الوحدة التي يحددها
against the items in the Tender Documents are to
المناقص مقابل البنود الواردة في المناقصة هي إلنجاز
be for the full inclusive value of the finished work
األشغال على أ كمل وجه طبقا للمواصفات وشاملة
described there under and shall include for profit .لألرباح والمسؤوليات والواجبات بموجب أحكام العقد
and all obligations and liabilities of every kind
arising under the Contract. وإذا،يجب تسعير جميع البنود الواردة في وثائق العطاء
Each item in the Tender Documents is to be priced.
يعتبر ألحد سعرا العرض مقدِّم يحدِّد لم،ممتنِعا البنود
Where a bidder fails to price an item, he will be
the Price Analysis Schedule included in the وأن عدم ا كتمال هذه الجداول قد،الواردة في العطاء
document. The tender may be rejected, if this
يؤدي إلى رفض المناقصة ومصادرة ضمان المناقصة
schedule is incomplete and the Tender Bond may
be confiscated. .)(التأمين االبتدائي
7. Fixed Price
السعر ثابت.7
The Tenderer should note that this Tender is a
Fixed Price Tender and he is to include for all على المناقص أن يأخذ باالعتبار بأن هذه المناقصة هي
8. Qualifications التحفظات.8
The Tender must be submitted solely on the basis
يجب تقديم المناقصة وفقا لوثائق العطاء فقط وأن
of the tender documents and shall be free of any
و يجوز،في للمشارِك تكون خالية من أي تحفظات
qualifications.
A participant may submit more than one Tender
للمناقصة عرض من أ كثر يقدِّم أن المناقصة،الواحدة
for the same public tender, provided that each ِل بشكل عرض كل أن يقدِّم على
ّ وبمجموعة مستق
المناقصات البديلة.9
9. Alternative Tenders
سينظر في المناقصات البديلة التي تقدم وفقا لمواصفات
Alternative Tenders based on specifications other
than those in the tender documents will be شريطة أن،غير تلك الواردة في وثائق العطاء المقدمة
considered provided that a Tender fully complying تتوافق المناقصة البديلة تماما مع الشروط المنصوص
with the conditions laid down in the tender ينبغي على المناقص أن يقدم.عليها في وثائق العطاء
documents is also submitted. The Tenderer shall
تفاصيل كاملة عن مثل هذه المواصفات البديلة مع
give full details of such alternative specifications
together with the effect, if any, on the Tender التأثيرات على قيمة المناقصة (إن وجدت) ولصاحب
Sum. The Employer shall be free to accept .العمل مطلق الحرية في قبول أي منهما
whichever Tender he may choose. Alternative
يجب أن تقدم المناقصات البديلة على النحو المبين في
Tenders must be submitted in the manner stated
) من هذه التعليمات إلى المناقصين16( ) و14( البندين
in Clause 14 and 16 of these Instructions to
Tenderers and be endorsed "Alternative No. 1" "1 ويبين أنه "البديل رقم
12. Currency
العملة.12
The currency of the Contract will be the U.A.E.
Dirham. عملة العقد هي الدرهم اإلماراتي
13. Language
اللغة.13
During the period of tendering all correspondence
with the Engineer shall be in the Arabic/English تكون جميع المراسالت في مرحلة المناقصة باللغة
language. .اإلنجليزية/ العربية
right to instruct the successful Tenderer to stamp يحق لصاحب العمل الطلب من المناقص الفائز توقيع
and initial every page prior to the formal award of .وختم جميع الصفحات قبل إصدار خطاب ترسية العقد
the Contract.
يجب التوقيع على المناقصة من رئيس الشركة أو من
The Tender must be signed by the principal of the
firm or by a person properly authorized for the الشخص المخول بالتوقيع مع تدوين اسمه وعنوان
purpose and the registered name and address of المناقص والذي يجب أن يكتب بخط اسود وبحروف
the Tenderer must be printed in block capitals in .كبيرة في المكان المخصص
the space provided.
باإلضافة إلى الوثائق الصادرة إلى المناقصين لتقديم
Instructions to Tenderers (CESMM – RM-Cons.)
ECS March 2022,
A6
OPEN DATA / بيانات مفتوحة
In addition to the documents issued to the قد يطلب من المناقصين تقديم الوثائق،المناقصة
Tenderer for the purpose of submitting a Tender,
:التالية بعد تقديم المناقصة
the following documents may be requested after
(أ) بيان الخطوط العريضة لألساليب المقترحة
submission of the Tender:
(a) An outline statement of the methods .إلنشاء األعمال
proposed for the construction of the في مخطط شريطي أو،(ب) البرنامج الزمني
works.
والتي تبين تسلسل اإلنشاء وتاريخ،شكل شبكة
(b) A program, in bar chart or network form,
.(تواريخ) إنجاز األشغال أو أجزاء منها
showing the sequence of the construction
and completion date / s for the Works or (ج) قائمة البنود الرئيسية لألجهزة أو المعدات
parts thereof. .التي ستستخدم مع أعدادها وأنواعها وقدراتها
(c) A list of the major items of plant or
(د) مخطط يوضح الجهاز الفني المقترح في
equipment to be used with numbers, types
وعدد المشرفين،الموقع إلدارة وتنظيم العمل
and capacities.
(d) A chart showing the proposed site staff والعمال بما في ذلك تلك التي ستستخدم من
and management organization for the .قبل المقاولين الفرعيين
work, and the numbers of supervisors and
(هـ) قائمة المقاولين الفرعيين والموردين
labor including those to be employed by
مع، بما في ذلك الشركات المحلية،المقترحة
the sub-contractors.
(e) A list of proposed sub-contractors and .تفاصيل العمل الذي ستقوم به
suppliers, including local firms, with (و) المصادر المقترحة من المواد المحلية
particulars of the work which shall be
.الطبيعية والركام
undertaken by them.
.(ز) أي وثائق أخرى الزمة لتوضيح التقديم
(f) The proposed sources of local naturally
occurring materials and aggregates.
(g) Any other documentation required to clarify
the submission.
تقديم المناقصة.17
17. Delivery of Tender
Submission of the Tender will be online through تقدم المناقصة الكترونيا من خالل نظام التوريد
eSupply of Dubai Government االلكتروني لحكومة دبي
In case, off-line Tender (If requested by Dubai (إذا طلب ذلك من قبل:في حال التقديم غير االلكتروني
Municipality), the submission must comprise the :بلدية دبي) يجب أن يشمل التقديم ما يلي
following:
Employer or the Engineer to discover any error إن عدم ا كتشاف صاحب العمل أو المهندس أي خطأ
during the checking of the tender shall not entitle أثناء تدقيق المناقصة ال يعطي للمناقص الفائز الحق (أو
the successful tenderer (or any other tenderer) to أي مناقص آخر) في تقديم مطالبة للدفع ضد الخطأ إذا
make a claim for payment against the error if it is .تم ا كتشافه في وقت الحق
subsequently discovered.
القبول.19
19. Acceptance
صاحب العمل غير ملزم بقبول أقل العروض سعرا أو أي
The Employer does not bind himself to accept the
lowest or any Tender and will not state a reason مناقصة ويحق له قبول أو رفض المناقصة دون إبداء
for the acceptance or rejection of a Tender. األسباب
Performance Security is received from him. The )) من النِّهائي التأمين التنفيذ10( منه وفقا للمادة
Tender Bonds will be returned to bidders if the ،يٌرد ضمان المناقصة (التأمين كما الشروط العامة للعقد
tender is cancelled, their tenders are disqualified, أو المناقصة إلغاء عند االبتدائي) لمقدِّمي العروض
or the tender is postponed for more than sixty (60) استبعاد،روضهم
ِ تزيد على لمدّة المناقصة تأجيل أو ع
days. )60( ستين.يوما
The gravity storm network designed to serve Nadd تم تصميم شبكة تصريف مياه األمطار لتخدم منطقة ند
Al Shiba development, Al Manama road and a small
area of Al Warsan 2&3 during the storm event, this .3 و2 الشبا وشارع المنامة وجزء صغير من الورسان
network is the downstream of International City
سيتم إستخدام الخط الرئيس المقترح بشارع المنامة
and Al Warsan 2&3, the main line of the drainage
system proposed in Al Manama Road will operate لتفريغ بركة المياه الحالية بالمدينة العالمية والبرك
as an evacuation line to evacuate the existing
International city pond and the proposed ponds in . في أوقات ذروة األمطار3 و2 المقترحة بمنطقة الورسان
Al Wasran 2&3 areas in the off-peak storm event.
ال يشتمل نطاق األعمال لبلدية دبي على المجاري
The scope of work under Dubai Municipality (DM) إال أنه يشتمل على خطوط التوصيل، )gullies( الصغيرة
does not include the gullies, however tapping lines
)land drains( بين غرف التفتيش ومناطق الصرف
from the manholes / land drain pipes have been
سيتم تركيب المجاري الصغيرة ضمن عقد أعمال
provided, the gullies installation will be along with
الطرق
the road contract.
Construction of the proposed Nadd Al Shiba Storm تشتمل األعمال أيضا على إنشاء محطة ضخ مياه
Water Pump Station (near the existing pumping
DB- األمطار بند الشبا (بالقرب من محطة الضخ الحالية
station DB-21)
شروط العقد.28
28. Conditions of Contract
The General Conditions of Contract shall be the الشروط العامة للعقد هي شروط بلدية دبي ألعمال
Dubai Municipality Conditions of Contract for .1999 مايو20 إنشاءات الهندسة المدنية طبعة
Works of Civil Engineering Construction Edition Dubai Municipality Conditions of Contract for Works
May 20, 1999. of Civil Engineering Construction Edition May 20,
1999.
29. Details of Other Contracts at the Site. تفاصيل العقود األخرى في الموقع.29
NIL ال شيء
Provisional Sum unless clearly indicated otherwise. باستثناء المبالغ،المناقصة) على كافة بنود األشغال
2. Any Offer delivered to the DM after the لن يستلم أو يقبل أي عرض فني يقدم إلى بلدية.2
Deadline for Submission of Offers will not be
.دبي بعد الموعد النهائي لتقديم العروض
received or accepted.
Instructions to Tenderers (CESMM – RM-Cons.)
ECS March 2022,
A16
OPEN DATA / بيانات مفتوحة
3. All requirements of the technical evaluation
criteria must be submitted together with their يجب تقديم جميع متطلبات معايير التقييم الفني.3
supporting documents not later than the time مع الوثائق الداعمة لها في موعد ال يتجاوز الموعد
and date stipulated to Submit Offers. .النهائي لتقديم العروض
considered zero, any supporting document مع التأكيد على عدم قبول أي وثيقة،المعيار صفرا
submitted after the deadline for submitting .داعمة تقدم بعد الموعد النهائي لتقديم العروض
Offers will not be accepted.
PART-B
CONDITIONS OF CONTRACT
Part 1 – General Conditions
The General Conditions of Contract applicable الشروط العامة للعقد هي شروط بلدية دبي لعقد أشغال
to this project shall be the Dubai Municipality 20 ،الشروط العامة- الجزء األول،إنشاءات الهندسة المدنية
Conditions of Contract for Works of Civil 1999 مايو
Engineering Construction, Part I – General (Dubai Municipality Conditions of Contract for
Conditions of May 20, 1999, which is not Works of Civil Engineering Construction, Part I –
attached with the Tender Documents and is General Conditions of May 20, 1999)
available on Dubai Municipality Website: والتي لم ترفق ضمن وثائق العطاء والمتاحة على الموقع
www.dm.gov.ae. www.dm.gov.ae :االلكتروني لبلدية دبي
General Conditions 1
ECS March 2022
OPEN DATA / بيانات مفتوحة
Sub
APPENDIX TO TENDER رقم البند ملح ـ ـ ـ ــق العط ـ ـ ـ ـ ــاء
Clause
Number of copies of claim analysis report to be نسخ تقرير تحليل المطالبة المتوجب تقديمها لصاحب
12.4 (F) 12.4 (F)
submitted to the Employer (Original + Copy). .) نسخة+ العمل (أصل
Time for submission of programme of Works
الوقت المخصص لتقديم برنامج األعمال بعد تاريخ
after the date of letter of Acceptance: - (14 14.1 (A) 14.1 (A)
.) يوم14( خطاب الترسية
Days).
Time for submission of Cash flow estimate after الوقت المخصص لتقديم تقدير السيولة النقدية بعد
14.3 14.3
the date of letter of Acceptance: - (28 Days). .) يوم28( تاريخ خطاب الترسية
Insurance of works, etc:- الحد األقصى القابل للحسم:التأمين على األعمال الخ
21.1 (a) 21.1 (a)
Deductible limits for Employer's risk (Nil). .)عن مخاطر صاحب العمل (ال يوجد
(5%) of the contract price for professional fees
21.1 (b) 21.1 (b) .) من قيمة العقد لقاء األتعاب المهنية الخ%5(
etc.
Minimum amount of Third Party Insurance: :الحد األدنى لمبلغ التأمين عن الطرف الثالث
22.1(b) 22.1(b)
Dhs. 1,000,000.00 per occurrence with the الن ممر ع ممن دره ممم لح ممل حاد ممظ بعم م1,000,000.00
& 23.2 & 23.2
number of occurrences unlimited. .الحوادث
________________________________________________________________________
T&A-CONS C3
ECS March 2022
2 OPEN DATA / بيانات مفتوحة
Percentage for Adjustment of Provisional Sums
(NIL) 59.4 (c) 59.4 (c) )النسبة المئوية لتعديل المبالغ االحتياطية (ال شيء
Number of diskettes on Monthly Statement to 60.1 60.1 عم م ممدد األقم م ممراو المرنم م ممة لح م م مموتات الدتعم م ممة ال م م ممهرية
be submitted: - (2 Nos). (A - c) (A - c) )2 المتوجب تقديمها (عدد
Number of Copies of Engineers Payment ع ممدد نس ممخ ش ممهادات الدتع ممة الص ممادرة م ممن المهن ممد
Certificate and other document to be 60.2 (C) 60.2 (C) + والمسم م ممتندات األخم م ممرد المتوجم م ممب تقم م ممديمها (أصم م ممل
submitted:- (Original + Copy). .)نسخة
________________________________________________________________________
T&A-CONS C4
ECS March 2022
OPEN DATA / بيانات مفتوحة
PART D
AGREEMENT
اﻻﺗﻔﺎﻗﻴﺔ
PART E
As Messrs. COMPANY NAME has declared that they have been awarded a contract
for the Construction, Completion and Maintenance of
_________________________________________________ with a contract price of
AED. _____________________ (UAE Dirhams ________________________) and in
consideration of Dubai Municipality making an advance payment of AED.
___________________ (UAE Dirhams ____________________) to the Contractor,
we hereby undertake to hold at your disposal the sum of AED.
________________________ (UAE Dirhams _________________) as bank
guarantee submitted as soft copy .
This guarantee and shall be free of interest and payable in cash on your first demand
in the manner ordered, without the Contractor or any person on his behalf or ourselves
having the right to suspend or delay payment or to object there to for any reason
whatsoever.
It is understood that our liability towards you will be progressively reduced by the
amount repaid to THE COMPANY by DUBAI MUNICIPALITY as contained in the
Certificates and payments against the said advance payment.
Yours faithfully.
الموضوع :ضمان حسن التنفيذ ( رقم الضمان +رقم العقد/امر الشراء /رقم
الطلب ( RFQبمبلغ .....درهم .
ُيقر السادة (اسم مقدم الطلب) ( ُيشار إليهم بعبارة مقدم الطلب) ،الكائن مكتبهم المسجل في
(عنوان مقدم الطلب) ،أنهم قد حصلوا على عقد إنشاء وإنجاز وصيانة (تفاصيل المشروع) ،وتبلغ
قيمة العقد (حدد العملة) (حدد المبلغ رقما)؛ و حيث أنه مقابل قيام (بلدية دبي) (يشار إليها بعبارة
المستفيد) الكائن مكتبها المسجل (عنوان بلدية دبي) بتسديد دفعة مقدمة بقيمة (المبلغ ،العملة)
إلى المقاول بموجب العقد رقم ××××××××× .فإننا نتعهد بموجبه أن نحتفظ بالمبلغ المذكور أعاله
على سبيل ضمان بنكي تحت تصرفكم وسيتم تقديمه كنسخة الكترونية.
ال يحمل هذا الضمان أي فائدة ،ويستحق الدفع نقدا ً عند أول مطالبة به من جانبكم وبالطريقة الواردة
في الطلب ،ومن دون أي حق للمقاول أو ألي شخص نيابة عنه أو عنا بتعليق أو تأجيل التسديد أو
معارضة ذلك ألي سبب مهما كان.
من المفهوم أن مسؤوليتنا تجاهكم سوف تتقلص تدريجيا ً من خالل المبلغ المدفوع مسبقا ً إلى مقدم
الطلب من قبل المستفيد وذلك كما هو مذكور في الشهادات والدفعات مقابل الدفعة المقدمة
المذكورة.
االسم االسم
التوقيع المعتمد التوقيع المعتمد
ختم البنك
As Messrs.(COMPANY NAME) has declared that their tender for the above named Works
has been accepted by Dubai Municipality, we hereby undertake to hold at your disposal
the sum of AED.____________ ( Dirhams_______________) being 10% of the total
contract price, as a Performance Security. This Security shall be free of interest and
payable in cash on your first written demand in the manner ordered, without the Contractor
or any person on his behalf or ourselves having the right to suspend or delay payment or to
object thereto for any reason whatsoever.
This Security will be presented as a soft copy the status will be active in our system from
__________ (contract commencement date) until / / (schedule time for completion
date as per the letter of acceptance) and shall, before expiry, be automatically renewed
until advised by you with written letter that the contract has been fulfilled.
Yours faithfully.
Designations Designations
الموضوع :ضمان حسن التنفيذ ( رقم الضمان +رقم العقد/امر الشراء /رقم
الطلب ( RFQبمبلغ .....درهم .
بناءا َ على طلب (اسم مقدم الطلب) (يشار إليه هنا فيما بعد بعبارة المقاول) ،عنوان مكتبه المسجل
في (عنوان مقدم الطلب) الذي أق َر أن بلدية دبي (المستفيد) الكائن مقر مكتبها المسجل (عنوان البلدية)
قد وافقت على مناقصتهم بخصوص المشروع (اسم +رقم المشروع) ،فإننا نتعهد بموجبه أن نحتفظ
بمبلغ قدره (المبلغ والعملة) بنسبة %01من القيمة اإلجمالية لسعر العقد ،وذلك على سبيل ضمان
حسن التنفيذ .علما ً أن هذا الضمان ال يحمل أي فائدة ،ويستحق الدفع عند أول مطالبة لكم وبالشكل
الذي يتم فيه الطلب؛ ومن دون أي حق للمقاول أو ألي شخص نيابة عنه أو عنا في تعليق أو تأجيل الدفع
أو االعتراض على ذلك ألي سبب مهما كان.
سيتم تقديم هذا الضمان كنسخة الكترونية و ستكون حالة الضمان ساري المفعول في انظمتنا من
تاريخ ( اليوم /الشهر /العام ) حتى تاريخ (اليوم/الشهر/العام) (الوقت المحدد في الجدول لإلنجاز
حسب خطاب القبول) وسيتم تجديده تلقائياً ،قبل تاريخ االنتهاء ،إلى حين استالم إشعار من طرفكم
. يفيد بأنه قد تم تنفيذ العقد والوفاء به
االسم االسم
التوقيع المعتمد التوقيع المعتمد
ختم البنك
Dubai Municipality,
P.o.Box 67,
Dear Sirs,
At the request of M/S………….. (Hereinafter called the Tender), P.O.Box…....., Dubai,UAE. We, the
bank name …...herby unconditionally agree to hold at your disposal the sum of AED…, as a
Tender bond. This Tender bond shall be free of interest and payable on your first written
demand in the manner ordered, without the Tenderer or any person on his behalf or ourselves
having the right to suspend or delay payment or to object thereto for any reason whatsoever.
This Tender Guarantee will be presented as a soft copy and will be valid for 120 calendar days
from … (date of tender opening) to … …. and renewable before expiry for a further 30 calendar
days if requested in writing by Dubai Municipality.
This Guarantee will be null and void after expiry date without a written notification.
Yours Faithfully,
CONDITIONS OF CONTRACT
1.1(c)(i) & (ii) Commencement Date Delete both sub-clauses and substitute with the
following (to read 1.1 (c ),i):
“Commencement Date” means the date stated
in the notice to commence issued by the
Engineer pursuant to Clause 41.1(A)
41.1(A) Commencement Delete the text of first line and substitute with the
following:
The Employer shall fix the date by which the
contractor is to commence execution of the works
on site and the Engineer shall issue a notice to this
effect to the Contractor.
____________________________________________________________________________________________
COC-Part II (RM)-Consultant F1
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
45.2(B) Engineer’s Over Time Delete line 4 from “Annex III of the Appendix to
Tender” and insert “Schedule of Engineer’s
Overtime Rates” as shown in the tender
documents”.
53.5(A) Payment of Delete sub clauses (b) and (c) and substitute
Claims with following:
60.7(A) Advance Payment Delete the text of lines 7, 8,9,10 and 11 i.e. from
“The Employer ……….... are met” and substitute
with the following:
____________________________________________________________________________________________
COC-Part II (RM)-Consultant F2
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
receive advance payment provided the following
conditions are met.
60.8 (A) Time of Payment Delete the text of lines 5, 6 and 7 i.e. from
“Employer to………….. for Certification”, and
substitute with the following:
“Employer to pay the Contractor within 60 days from the
date of receipt of Engineer’s Payment Certificate.
60.8 (C) Time of Payment Delete the text of lines 4, 5 and 6 i.e. from
“Employer to………..…. for certification,” and
substitute with the following:
“Employer to pay the Contractor within 60 days
from the date of receipt of Engineer’s Final
Payment Certificate, provided the Contractor’s……
____________________________________________________________________________________________
COC-Part II (RM)-Consultant F4
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
(b) on or before the twentieth (20th) day
after the day on which the said period of
30 days expired,
____________________________________________________________________________________________
COC-Part II (RM)-Consultant F5
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
67.3 Conciliation Delete this clause in its entirety and substitute with the
following:
67.5 Failure to
Comply with the
Engineer’s Decision Delete this clause in its entirety and substitute
with the following:
____________________________________________________________________________________________
COC-Part II (RM)-Consultant F6
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
68.1(b) Notice to Contractor Delete the text line 1 and 2 i.e from “If specifically
……….. Tender and substitute with the following:
or left at the Contractors principal place of business
or such other address as the Contractor shall
nominate for the purpose. The Contractor shall,
within 7 days of the acceptance of his tender by the
Employer notify the Employer and the Engineer of
the registered address of his office in Dubai to
which he may require notice to be served.
X Y
Note:
Y = any hours worked on weekend day-offs & Public Holidays and from 21.00 to 04.00 any day.
G1
PART H
SCHEDULE OF CONSULTANT’S
MONTHLY SUPERVISION FEES
_____________________________________________________________________
June 2022 H1
PART J
SCHEDULE OF CONSULTANT’S
SITE OFFICE FACILITIES
The Contractor shall provide, maintain and keep clean, temporary site offices with all associated
equipment, fittings and services for the engineer’s satisfaction and for the exclusive use of the
Engineer's Representative and his staff, from commencement until one month after the completion of
the whole of the Works.
The temporary site offices shall be either prefabricated portable unit/s or alternatively of some other
form of weatherproof design and construction to the approval of the Engineer.
The offices shall have full partitions and room sizes shall be as shown in the attached Schedule of
offices. All rooms shall have individual entrance doors.
The offices shall be air-conditioned with the exception of the Toilet, Shower and Kitchen areas.
All rooms shall have glazed windows complete with fly screens.
Adequate fitted hardware, electrical switches, sockets, lighting and plumbing fittings, sanitary ware
and fittings and fixtures etc., shall be provided as necessary for the different areas.
The electrical installation shall provide for simultaneous use of all electrical appliances.
The Contractor may either arrange for a temporary power supply to the offices or alternatively
provide and maintain adequate diesel generator sets. All electricity bills shall be paid by the
Contractor.
The Contractor may either arrange for a temporary mains water supply or alternatively provide
tankered water supply. All water bills shall be paid by the Contractor.
A telephone line with extensions shall be provided for the offices as shown in the Schedule of Fittings
and the Contractor shall pay all installation and rental charges and call charges within the U.A.E. An
Independent Fax line including equipment and Internet/E-mail connection shall be provided.
The Contractor shall submit any necessary drawings and calculations for the construction of the
offices for the Engineer's approval before commencing construction and shall be responsible for
ensuring that the offices are structurally sound. The Engineer may request alterations at this
stage. The drawings shall be approved in writing by the Engineer before installation/construction
shall commence.
The offices shall be completed and all the equipment provided by the end of the Mobilisation Period.
The Contractor shall provide all items listed in the attached Schedules.
Throughout the duration of the Contract, the Contractor shall ensure an uninterrupted supply of gas,
water and electricity to the offices.
___________________________________________________________________________
SOFFICE-CONS J1
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
SCHEDULE OF OFFICES
Room
No. Description Size Requirement
11 Toilet 4m x 2m Yes
12 Shower 2m x 2m Yes
13 Kitchen 4m x 2m Yes
* Delete as necessary
___________________________________________________________________________
SOFFICE-CONS J2
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
SCHEDULE OF FITTINGS
The fittings required under this Contract for the site offices indicated in the schedule of
offices, shall be to the Engineer's approval and are as follows:
2 Conference table to No - - 1 - - - - - - - - - -
accommodate 12 people with
revolving chairs
3 Desk with two locking drawers No - - - 1 1 2 1 2 2 - - - -
and chair
4 Visitor's chair - steel frame No 2 2 12 2 2 2 2 2 2 2 - - 2
8 Sample cupboard No 1 - - - - - - - - - - -
11 In/Out Tray No 1 1 - 1 1 2 1 2 2 1 - - -
___________________________________________________________________________
SOFFICE-CONS J3
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
Room No and Quantity
Item Description Unit 1 2 3 4 5 6 7 8 9 10 11 12 13
16 Maximum-minimum thermometer No - 1 - - - - - - - - - - -
18 Water filter No - - - - - - - - - - - - 1
19 Sink Unit No - - - - - - - - - - - - 1
20 Electric Kettle No - - - - - - - - - - - - 1
The consumable items, such as kitchen equipment, glasses, cups, plates, food, coffee, drinks, and
stationary items such as office supplies, paper, cartridges, ribbons, etc. will be provided by the
Consultant at his own cost.
___________________________________________________________________________
SOFFICE-CONS J4
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
SCHEDULE OF EQUIPMENT
The equipment required on site under this contract shall be to the Engineer’s approval and is as
follows:
e 2m ranging poles
___________________________________________________________________________
SOFFICE-CONS J5
ECS March 2022
OPEN DATA / ﺑﻴﺎﻧﺎت ﻣﻔﺘﻮﺣﺔ
PART K
LIST OF DRAWINGS
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 07 27 03 30 24 28 05 21 23
Project Element Month 02 04 06 06 08 09 10 11 12
Area / Room Year 22 22 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
GENERAL
COVER SHEET G 0 0 0 N N N N N N N
LIST OF DRAWINGS (NAD AL SHEBA) G 0 0 1 N N N N N T1 T2 T2 T2
PROJECT LOCATION PLAN G 0 1 0 N N N N N N N
GENERAL NOTES G 0 1 1 N N N N N N N
12/23/2022 1 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 07 27 03 30 24 28 21 23
Project Element Month 02 04 06 06 08 09 11 12
Area / Room Year 22 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
SEWERAGE&STORM WATER NETWORK LAYOUT SHEET 21 S E W 2 1 N N N N N N N
SEWERAGE&STORM WATER NETWORK LAYOUT SHEET 22 S E W 2 2 N N N N N N N
12/23/2022 2 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 07 27 03 30 24 28 21 23
Project Element Month 02 04 06 06 08 09 11 12
Area / Room Year 22 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
SEWERAGE PROFILE SHEET 12 (LINE PR-NB23, PR-NB24, PR-
S E W PR 1 2 N N N N N N N
NB25, PR-NB26 & PR-NB27)
SEWERAGE PROFILE SHEET 13 (LINE PR-NB28, PR-NB29 & PR-
S E W PR 1 3 N N N N N N N
NB30)
SEWERAGE PROFILE SHEET 14 (LINE PR-NB2-PSV (1 OF 2) S E W PR 1 4 N N N N N N N
SEWERAGE PROFILE SHEET 15 (LINE PR-NB2-PSV (2 OF 2) S E W PR 1 5 N N N N N N N
SEWERAGE PROFILE SHEET 16(LINE PR-ND1(1 OF 4)&(2 OF 4) S E W PR 1 6 N N N N N N N
SEWERAGE PROFILE SHEET 17(LINE PR-ND1(3 OF 4)&(4 OF 4) S E W PR 1 7 N N N N N N N
DETAIL
PROPOSED CONNECTION DETAIL TO EXISTING MAHOLE
S E W DT 0 1 N N N N N N
V/2/4/9
STORMWATER DRAINAGE PROFILES
STORMWATER DRAINAGE PROFILES (SHEET 01) (LINE PR- {1
S W D PR 0 1 N N N N N N N
OF 5} & {2 OF 5}
STORMWATER DRAINAGE PROFILES (SHEET 02) (LINE PR- {3
S W D PR 0 2 N N N N N T1 T1 T1
OF 5} & {4 of 5})
STORMWATER DRAINAGE PROFILES (SHEET 03) (LINE PR- {5
S W D PR 0 3 N N N N N N N
OF 5}
STORMWATER DRAINAGE PROFILES (SHEET 04) (LINE PR-01,
S W D PR 0 4 N N N N N N N
PR-02, PR-03, PR-04, PR-06 & PR-07)
STORMWATER DRAINAGE PROFILES (SHEET 05)(LINE PR-05 &
S W D PR 0 5 N N N N N N N
PR-08)
STORMWATER DRAINAGE PROFILES (SHEET 06)(LINE PR-09,
S W D PR 0 6 N N N N N N N
PR-10, PR-11, PR-12 & PR-14)
STORMWATER DRAINAGE PROFILES (SHEET 07)(LINE PR-13,
S W D PR 0 7 N N N N N N N
PR-15 & PR-16 (1 OF 2)
STORMWATER DRAINAGE PROFILES (SHEET 08)(LINE PR-16
S W D PR 0 8 N N N N N N N
{2 OF 2}, PR-17, PR-18 & PR-20)
Distribution Number of Copies
HARD
CLIENT A3 SIZE
DIGITAL
HARD
PROJECT MANAGER A3 SIZE
DIGITAL
HARD
TENDER - *ADDENDUM A3 SIZE
DIGITAL 1 1 1 1 1 1
HARD
CONTRACT - (SITE USE) A3 SIZE
DIGITAL 1 1
HARD
CONSTRUCTION - (CONTRACTOR) A3 SIZE
DIGITAL
HARD
AUTHORITIES A3 SIZE
DIGITAL
Company Confidential Trade Secret and Proprietary Information of K&A (U.A.E.)
12/23/2022 3 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 07 27 03 30 24 21 23
Project Element Month 02 04 06 06 08 11 12
Area / Room Year 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
STORMWATER DRAINAGE PROFILES (SHEET 09)(LINE PR-19,
S W D PR 0 9 N N N N N N N
PR-21, PR-22 & PR-23)
STORMWATER DRAINAGE PROFILES (SHEET 10)(LINE PR-24,
S W D PR 1 0 N N N N N N N
PR-25, PR-26, PR-27 & PR-28)
STORMWATER DRAINAGE PROFILES (SHEET 11)(LINE PR-30,
S W D PR 1 1 N N N N N N N
PR-29, PR-31 & PR-32)
STORMWATER DRAINAGE PROFILES (SHEET 12)(LINE PR-33,
S W D PR 1 2 N N N N N N N
PR-33-1, PR-33-2, PR-33-3 & PR-33-4)
STORMWATER DRAINAGE PROFILES (SHEET 13)(LINE PR-34
S W D PR 1 3 N N N N N N N
& PR-35)
STORMWATER DRAINAGE PROFILES (SHEET 14)(LINE PR-36
S W D PR 1 4 N N N N N N N
{1 OF 2}
STORMWATER DRAINAGE PROFILES (SHEET 15)(LINE PR-36
S W D PR 1 5 N N N N N N N
{2 OF 2}, PR-37, PR-38 & PR-40)
STORMWATER DRAINAGE PROFILES (SHEET 16)(LINE PR-39
S W D PR 1 6 N N N N N N N
& PR41)
STORMWATER DRAINAGE PROFILES (SHEET 17)(LINE PR-42
S W D PR 1 7 N N N N N N N
{1 OF 2, 2 OF 2}, PR-43 & PR-44)
STORMWATER DRAINAGE PROFILES (SHEET 18)(LINE PR-45,
S W D PR 1 8 N N N N N N N
PR-46, PR-47, PR-48 & PR-49)
STORMWATER DRAINAGE PROFILES (SHEET 19)(LINE PR-50,
S W D PR 1 9 N N N N N N N
PR-51, PR-52 & PR-53)
STORMWATER DRAINAGE PROFILES (SHEET 20)(LINE PR-54,
S W D PR 2 0 N N N N N N N
PR-55, PR-56 & PR-57 {1 OF 2}
STORMWATER DRAINAGE PROFILES (SHEET 21)(LINE PR-57
S W D PR 2 1 N N N N N N N
{2 OF 2}
STORMWATER DRAINAGE PROFILES (SHEET 22)(LINE PR-58,
S W D PR 2 2 N N N N N N N
PR-59, PR-60, PR-61 & PR-62)
12/23/2022 4 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 07 27 03 30 24 28 05 21 23
Project Element Month 02 04 06 06 08 09 10 11 12
Area / Room Year 22 22 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
STORMWATER DRAINAGE PROFILES (SHEET 23)(LINE
S W D PR 2 3 N N N N N N N
PR-63, PR-64, PR-65, PR-66, PR-67 & PR-68)
STORMWATER DRAINAGE PROFILES (SHEET 24)(LINE
S W D PR 2 4 N N N N N T1 T1 T1
PR-69 {1 OF 6}
STORMWATER DRAINAGE PROFILES (SHEET 25)(LINE
S W D PR 2 5 N N N N N T1 T1 T1
PR-69 {2 OF 6} & {3 OF 6}
STORMWATER DRAINAGE PROFILES (SHEET 26)(LINE
S W D PR 2 6 N N N N N N N
PR-69 {4 OF 6)
STORMWATER DRAINAGE PROFILES (SHEET 27)(LINE
S W D PR 2 7 N N N N N N N
PR69 {5 OF 6} & {6 OF 6)
STORMWATER DRAINAGE PROFILES (SHEET 28)(LINE
S W D PR 2 8 N N N N N N N
PR-70 {1 OF 2)
STORMWATER DRAINAGE PROFILES (SHEET 29)(LINE
S W D PR 2 9 N N N N N N N
PR-70 {2 OF 2}, PR-71)
STORMWATER DRAINAGE PROFILES (SHEET 30)(LINE
S W D PR 3 0 N N N N N N N
PR-72 {1 OF 2}, {2 OF 2)
STORMWATER DRAINAGE PROFILES (SHEET 30)(LINE
S W D PR 3 1 N N
PR-72 {1 OF 2} & {2 OF 2}
STORMWATER DRAINAGE PROFILES (SHEET 30)(LINE
S W D PR 3 2 N N
PR-72 {1 OF 2} & {2 OF 2}
DETAIL
POND DB 21 OVER FLOW & EVACUATION LINE PLAN &
S W D DT 0 1 N N N N N T1 T1 T1
SECTIONS
DETAILS OF OVERFLOW MANHOLE S W E DT 0 2 N N
12/23/2022 5 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 27 03 30 24 28 21 23
Project Element Month 04 06 06 08 09 11 12
Area / Room Year 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
PUMP STATION
CIVIL
STORM WATER PUMP STATION-3 DB21New - LOCATION S W D PS 3 0 0 N N N N N N
& LAYOUT PLAN
STORM WATER PUMP STATION-3 DB21New - S W D PS 3 0 1 N N N N N N
SECTIONAL & TOP PLAN
STORM WATER PUMP STATION-3 DB21New - SECTION A- S W D PS 3 0 2 N N N N N N
A
STORM WATER PUMP STATION-3 DB21New - SECTION B- S W D PS 3 0 3 N N N N T1 T1 T1
B, C-C & D-D
STORM WATER PUMP STATION-3 DB21New - SCREEN S W D PS 3 0 4 N N N N N N
CHAMBER PLAN, SECTIONS & DETAILS
ARCHITECTURAL
SWD PS 3- GENERAL NOTES , LEGEND & EXTERNAL S W D PS 3 2 0 N N N N N N
FINISHES
SWD PS 3- GENERAL LAYOUT PLAN S W D PS 3 2 1 N N N N N N
SWD PS 3- GROUND FLOOR PLAN & ROOF PLAN S W D PS 3 2 2 N N N N N N
SWD PS 3- SECTION A-A, B-B, OPENING SCHEDULE & S W D PS 3 2 3 N N N N N N
ROOF DETAILS
SWD PS 3 - ELEVATIONS S W D PS 3 2 4 N N N N N N
SWD PS 3- MECHANICAL LAYOUT S W D PS 3 2 5 N N N N N N
SWD PS 3 - HVAC SYSTEM LAYOUT S W D PS 3 2 6 N N N N N N
ELECTRICAL
STORM WATER PUMPING STATION DB21 New - S W D PS 3 4 0 N N N N T1 T1 T1
ELECTRICAL LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - SINGLE S W D PS 3 4 1 N N N N T1 T1 T1
LINE DIAGRAM - MCC 1
Distribution Number of Copies
HARD
CLIENT A3 SIZE
DIGITAL
HARD
PROJECT MANAGER A3 SIZE
DIGITAL
HARD
TENDER - *ADDENDUM A3 SIZE
DIGITAL 1 1 1 1 1
HARD
CONTRACT - (SITE USE) A3 SIZE
DIGITAL 1 1
HARD
CONSTRUCTION - (CONTRACTOR) A3 SIZE
DIGITAL
HARD
AUTHORITIES A3 SIZE
DIGITAL
Company Confidential Trade Secret and Proprietary Information of K&A (U.A.E.)
12/23/2022 6 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 27 03 30 24 28 05 21 23
Project Element Month 04 06 06 08 09 10 11 12
Area / Room Year 22 22 22 22 22 22 22 22
Size of Drawings DM SIZE Stage of the Project T T T T T T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
STORM WATER PUMPING STATION DB21 New -
S W D PS 3 4 2 N N N N N N
LIGHTING LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - POWER
S W D PS 3 4 3 N N N N N N
LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - FIRE
S W D PS 3 4 4 N N N N N N
ALARM & EMERGENCY LIGHTING LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - MCC
S W D PS 3 4 5 N N N N T1 T2 T2 T2
ROOM SECTIONAL DETAILS
STORM WATER PUMPING STATION DB21 New -
S W D PS 3 4 6 N N N N N N
LIGHTNING PROTECTION LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New -
S W D PS 3 4 7 N N N N N N
ELECTRICAL LOAD SCHEDULE
STORM WATER PUMPING STATION DB21 New -
S W D PS 3 4 8 N N N N T1 T1 T1
EARTHING LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - CABLE
S W D PS 3 4 9 N N N N N N
DRAWPIT & CABLE TRENCH DETAILS
STORM WATER PUMPING STATION DB21 New - STREET
S W D PS 3 5 0 N N N N N N
LIGHTING LAYOUT PLAN
STORM WATER PUMPING STATION DB21 New - P & I
S W D PS 3 5 1 N N N N T1 T1 T1
DIAGRAM
STORM WATER PUMPING STATION DB21 New - P & ID
S W D PS 3 5 2 N N N N N N
TYPICAL DETAILS
STORM WATER PUMPING STATION DB21 New - P & ID
S W D PS 3 5 3 N N N N N N
LEGEND SHEET
STORM WATER PUMPING STATION DB21 New - SYSTEM
S W D PS 3 5 4 N N N
ARCHITECTURE
STRUCTURAL
STORM WATER PUMPING STATION-3 GENERAL NOTES
S T 0 0 1 N N N
AND DETAILS (SHEET 1 OF 2)
STORM WATER PUMPING STATION-3 GENERAL NOTES
S T 0 0 1 N N N
AND DETAILS (SHEET 2 OF 2)
Distribution Number of Copies
HARD
CLIENT A3 SIZE
DIGITAL
HARD
PROJECT MANAGER A3 SIZE
DIGITAL
HARD
TENDER - *ADDENDUM A3 SIZE
DIGITAL 1 1 1 1 1 1
HARD
CONTRACT - (SITE USE) A3 SIZE
DIGITAL 1 1
HARD
CONSTRUCTION - (CONTRACTOR) A3 SIZE
DIGITAL
HARD
AUTHORITIES A3 SIZE
DIGITAL
Company Confidential Trade Secret and Proprietary Information of K&A (U.A.E.)
12/23/2022 7 of 8
WET UTILITIES
DRAWING ISSUE SHEET Discipline
Project Name DS196 - 2 NADD AL SHIBA 3RD SEWERAGE AND STORMWATER SYSTEM
Project No. DU1849 Drawing Issue No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Project Location DUBAI - UAE Day 24 21 23
Project Element Month 08 11 12
Area / Room Year 22 22 22
Size of Drawings DM SIZE Stage of the Project T
N = Non Revised Issue {SD1,SD2,SD3..} Schematic Revisions,
Drawing Title Drawing No. {DD1, DD2,DD3…} Design Develop. Revisions {T1, T2, T3,…)
Tender Revisions {C1,C2,C3....} Construction Revisions
12/23/2022 8 of 8
PART L
Satisfactory Unsatisfactory
Is the External Party financially
sound?
01/02/2020 V1.0
Shared Confidential Page 1 of 4
Organization Unit: Dubai Municipality : حدة التنظيمية
Form sheet title: External Party Risk Assessment Form : اسم النموذج
Doc Ref. DM-ISMS-F11-TPRRF : رقم النموذج
Risk Assessment
Parameters Remarks
Physical access to premises required If Yes – For Implementing the solution:
01/02/2020 V1.0
Shared Confidential Page 2 of 4
Organization Unit: Dubai Municipality : حدة التنظيمية
Form sheet title: External Party Risk Assessment Form : اسم النموذج
Doc Ref. DM-ISMS-F11-TPRRF : رقم النموذج
DM Point of Contact:
Name:
EMP ID:
Department:
Section:
Conducted Authorized By:
By: Department
Head
Signature: Signature:
Date: Date:
01/02/2020 V1.0
Shared Confidential Page 3 of 4
Organization Unit: Dubai Municipality : حدة التنظيمية
Form sheet title: External Party Risk Assessment Form : اسم النموذج
Doc Ref. DM-ISMS-F11-TPRRF : رقم النموذج
High: This could result in MAJOR Data leakage / Data Loss / Financial loss / Image &
Medium: This could result in MODERATE Data leakage / Data Loss / Financial loss / Image
Low: This would result in MINIMAL / No Data leakage / Data Loss / Financial loss / Image &
01/02/2020 V1.0
Shared Confidential Page 4 of 4
PART Q
ﻧﻘﺎط رﻗﻢ
اﻟﻨﻘﺎط ﻣﻌﺎﻳﻴﺮ اﻟﺘﻘﻴﻴﻢ وﺻﻒ اﻟﺘﻘﻴﻴﻢ
اﻟﺘﻘﻴﻴﻢ اﻟﺒﻨﺪ
ﻳﺘﻢ ﺗﻘﻴﻴﻢ ﻫﺬا اﻟﻤﻌﻴﺎر ﻛﻤﺎ ﻳﻠﻲ :
-1ان ﻳﻜﻮن ﻧﻮع اﻟﻤﺸﺮوع ﻣﺪرج ﺿﻤﻦ ﻓﺌﺎت ﺗﺼﻨﻴﻒ ﻧﺸﺎﻃﺎت اﻟﺸﺮﻛﺔ )ﺷﺒﻜﺎت اﻟﺼﺮف
15 15 اﻟﺼﺤﻲ وﺗﺼﺮﻳﻒ ﻣﻴﺎه اﻷﻣﻄﺎر ،ﻣﺤﻄﺎت ﻣﻌﺎﻟﺠﺔ ﻣﻴﺎه اﻟﺼﺮف اﻟﺼﺤﻲ ،ﻣﺤﻄﺎت اﻟﻀﺦ( اﻟﺮﺧﺼﺔ اﻟﺘﺠﺎرﻳﺔ 1
ﻓﻲ ﺣﺎل وﺟﻮد اﻟﻨﺸﺎط اﻟﻤﻄﻠﻮب ﻓﺴﻴﻜﻮن اﻟﺘﻘﻴﻴﻢ = 15
ﻓﻲ ﺣﺎل ﻋﺪم وﺟﻮد اﻟﻨﺸﺎط اﻟﻤﻄﻠﻮب ﻓﺴﻴﻜﻮن اﻟﺘﻘﻴﻴﻢ = 0
)ﻋﺪد ﻫﺬه اﻟﻤﻌﺪات ﻟﺪى اﻟﻤﻘﺎول /أ ﻛﺒﺮ ﻋﺪد ﻣﻘﺪم ﻣﻦ ﻫﺬه اﻟﻤﻌﺪات( * 3
ﻳﺘﻢ ﺗﻘﻴﻴﻢ ﻫﺬا اﻟﻤﻌﻴﺎر ﺣﺴﺐ ﺷﺮوط اﻟﻌﻘﺪ ﻛﻤﺎ ﻳﻠﻲ :
ﺗﻘﺪﻳﻢ اﻟﺴﻴﺮ اﻟﺬاﺗﻴﺔ ﻟﻔﺮﻳﻖ ﻋﻤﻞ
6 -1ﻣﺆﻫﻼت وﺧﺒﺮات ﻣﺪﻳﺮ اﻟﻤﺸﺮوع -ﻣﻬﻨﺪس ﻣﺪﻧﻲ -ﺑﺪون ﺷﻬﺎدات ﻣﻬﻨﻴﺔ ) 4ﻧﻘﺎط( أو
اﻟﻤﺸﺮوع ﻋﻠﻰ إﻗﺎﻣﺔ اﻟﺸﺮﻛﺔ )ﻣﺪﻳﺮ
) 6ﻧﻘﺎط( ﻓﻲ ﺣﺎل وﺟﻮد ﺷﻬﺎدة ﻣﻬﻨﻴﺔ certified PMP
15 اﻟﻤﺸﺮوع ،ﻣﺪﻳﺮ اﻟﺘﻨﻔﻴﺬ ،ﻣﻬﻨﺪﺳﻲ 6
3 -2ﻣﺆﻫﻼت وﺧﺒﺮات ﻣﺪﻳﺮ اﻟﺘﻨﻔﻴﺬ ) 3ﻧﻘﻄﺔ (
اﻟﺘﻨﻔﻴﺬ واﻻﻟﻜﺘﺮوﻣﻴﻜﺎﻧﻴﻚ ،ﻣﻬﻨﺪس
4 -3ﻣﺆﻫﻼت وﺧﺒﺮات ﻣﻬﻨﺪﺳﻲ اﻟﺘﻨﻔﻴﺬ ) 4ﻧﻘﻄﺔ (
ﺗﺨﻄﻴﻂ(
2 -4ﻣﺆﻫﻼت وﺧﺒﺮات ﻣﻬﻨﺪس اﻟﺘﺨﻄﻴﻂ ) 2ﻧﻘﻄﺔ (
ﻳﺘﻢ ﺗﻘﻴﻴﻢ اﻟﻮﺿﻊ اﻟﻤﺎﻟﻲ واﻹداري ﻛﻤﺎ ﻳﻠﻲ :
2 -1ﺗﻘﺪﻳﻢ ﻗﺎﺋﻤﺔ ﻣﻦ وزارة اﻟﻌﻤﻞ ﺗﻮﺿﺢ اﻟﺘﺰام اﻟﻤﻘﺎول ﺑﺼﺮف رواﺗﺐ اﻟﻤﻮﻇﻔﻴﻦ ﻵﺧﺮ 3
أﺷﻬﺮ ) 2ﻧﻘﻄﺔ(
2 13 -2ﻋﺎﺋﺪات اﻟﺸﺮﻛﺔ آﺧﺮ ﺧﻤﺲ ﺳﻨﻮات ) 2ﻧﻘﻄﺔ( اﻟﻮﺿﻊ اﻟﻤﺎﻟﻲ واﻹداري ﻟﻠﺸﺮﻛﺔ 7
2 -3أرﺑﺎح اﻟﺸﺮﻛﺔ آﺧﺮ ﺧﻤﺲ ﺳﻨﻮات ) 2ﻧﻘﻄﺔ(
2 -4ﺗﻮﻓﺮ ﺗﺄﻣﻴﻦ ﻟﻤﺸﺎرﻳﻊ اﻟﺘﻨﻔﻴﺬ ) 2ﻧﻘﻄﺔ (
5 ) 5ﻧﻘﺎط( -5ﺗﻮﻓﺮ اﻋﺘﻤﺎد أﻧﻈﻤﺔ ﺟﻮدة وﺳﻼﻣﺔ "أﻳﺰو"
ﻳﺘﻢ ﺗﻘﻴﻴﻢ اﻟﻤﻘﺎول ﻛﻤﺎ ﻳﻠﻲ :
3
-1ﻋﺪد اﻟﻤﺸﺎرﻳﻊ اﻟﻤﻨﻔﺬة ﺑﺎﻟﻮﻗﺖ اﻟﻤﺤﺪد ﺑﺂﺧﺮ ﺛﻼث ﺳﻨﻮات ) 3ﻧﻘﺎط(
ﺗﻘﻴﻴﻢ اﻟﻤﻘﺎول ﻟﺪى إدارة ﻣﺸﺎرﻳﻊ
3 12 -2ﻋﺪد اﻟﺤﻮادث اﻟﻤﺴﺠﻠﺔ ﺑﺂﺧﺮ ﺛﻼث ﻣﺸﺎرﻳﻊ ) 3ﻧﻘﺎط( 8
اﻟﺼﺮف اﻟﺼﺤﻲ
3 -3ﻋﺪد ﺷﻬﺎدات ﻋﺪم اﻟﻤﻄﺎﺑﻘﺔ ﺑﺂﺧﺮ ﺛﻼث ﻣﺸﺎرﻳﻊ ) 3ﻧﻘﺎط(
3 -4ﻋﺪد اﻟﻤﻄﺎﻟﺒﺎت اﻟﻤﻘﺪﻣﺔ ﻟﺒﻠﺪﻳﺔ دﺑﻲ ﺑﺂﺧﺮ ﺛﻼث ﺳﻨﻮات ) 3ﻧﻘﺎط(
100 ﻣﺠﻤﻮع اﻟﺘﻘﻴﻴﻢ اﻟﻔﻨﻲ )ﻋﻼﻣﺔ اﻟﻨﺠﺎح %70وأ ﻛﺜﺮ(
40 اﻟﺘﻘﻴﻴﻢ اﻟﻔﻨﻲ ﻣﻦ % 40
60 اﻟﺘﻘﻴﻴﻢ اﻟﻤﺎﻟﻲ = )ﻗﻴﻤﺔ اﻗﻞ ﻋﻄﺎء /ﺳﻌﺮ اﻟﻤﻨﺎﻗﺺ(*60
100% اﻟﺘﻘﻴﻴﻢ اﻟﻨﻬﺎﺋﻲ )ﻣﺎﻟﻲ وﻓﻨﻲ( ) %40ﻟﻠﺘﻘﻴﻴﻢ اﻟﻔﻨﻲ %60 +ﻟﻠﺘﻘﻴﻴﻢ اﻟﻤﺎﻟﻲ(
PART R
APPENDICES
APPENDICES
Contents
3. Letter of Acceptance
PROJECT: DS 196/2
NADD AL SHIBA 3rd SEWERAGE & STORMWATER SYSTEM
28 SEPTEMBER 2022
Employer:
PROJECT: DS 196/2
rd
NADD AL SHIBA 3 SEWERAGE & STORMWATER SYSTEM
The Notice to Tenderers No.1 is issued to add/amend the followings. The Tenderers should
replace the affected pages with the revised pages attached herewith, which have been marked
“Notice to Tenderers No.1”.
(Revised items have been marked with ** and revised pages with 1 symbol)
1. Volume 1 Tender & Contract Conditions: Please replace the following revised pages:-
Annexure 1
Propeller Pumps Specifications (New Annexure added)
Appendix 5
Dubai Municipality Standard (New Appendix added)
Details for Sewerage, Drainage &
Irrigation Construction
5. Revised Drawings: The revised drawings listed under column 27/09/2022 in the drawing
issue sheet are issued and shall supersede drawings of the same number issued previously.
____________________________________________________________________________
Notice to Tenderers No.1
1
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
PROJECT: DS 196/2
NADD AL SHIBA 3rd SEWERAGE & STORMWATER SYSTEM
Notice to Tenderers No.1 is issued to respond to the tender queries received from the
tenderers. The Queries received from Tenderers are replied to in the Clarification Sheet below.
SL.
Nr.
Tender Query Response to Tender Queries
1. Kindly arrange a pre-tender site visit in order to The pre-tender site visit is scheduled for
familiarize with the site conditions and get better September 29 2022. Please contact Khatib
understanding of scope of work. Alami Eng. Abdul Malick Jinnah (Contact No:
050 222 7381) for further details.
2. Please provide the excel copy of the BOQ. Tenderer can download the excel BOQ from
the e-supply portal.
4. We request for the Tender Bond value for Tender Bond value mentioned in invitation
submission purpose. leeter and on the main page of Tender link.
5. Kindly provide Standard Details for the Manholes, Please refer to Volume 2-Part 3 of 3
for the Contract DS-196/2 Nadd Al Shiba 3rd. Appendix No.5 DM Standard Details issued
Sewerage & Storm Water System. with this NTT1.
6. Please provide us Service Reservation Cross Please refer to Service Reservation Cross
Section for the Contract "DS-196/2 - Nadd Al Section Details issued with this NTT1.
Shiba 3rd. Sewerage & Storm Water System".
7. Please confirm that the load schedule does not Capacitor Bank load include in the schedule
include capacitor bank. refers to drawing SWD PS341.
9. We refer to the above mentioned Tender due for The revised tender opening date is Oct 04/
submission on 27 September 2022. 2022.
10. Item d/lB/14 B Fence 2-2.5m Height,Please Refer to revised drawing PS 351.
provide drawing for the same.
____________________________________________________________________________
Notice to Tenderers No.1
1
OPEN DATA / بياانت مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
11. Kindly note that the items below in the screenshot Refer to Preamble Page b/6 Clause A,
are missing in the BOQ, General Items. Please mentioning that Method-Related Charges are
revise and include the below items in the BOQ. not measured & paid separately. However, it
is the tenderer's responsibility to allocate
adequate staff and resources to complete
the contract's scope of work satisfactorily.DM
consider the technical proposal and staff
chart of the project to be part of the
evaluation; and if the contractor fails or
changes the required services mentioned in
the contract, then the Penalty shall be
imposed as per the contract condition
12. Further to the above query ,kindly note that,in Refer to Preamble Page b/6 Clause A,
case the contractor include the cost related to the mentioning that Method-Related Charges are
above items in the regular unit rates where the not measured & paid separately.
given quantities are reduced during remeasure, it
constitutes huge loss to the contractor.
13. Please share the Bid bond value since it is not Tender Bond value mentioned in invitation
available in the invitation. leeter and on the main page of Tender link.
____________________________________________________________________________
Notice to Tenderers No.1
2
OPEN DATA / بياانت مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
14. As per BOQ - d/6B/ 9 - Item C (Flanged Flap Flap Valve is not required Stormwater Pump
Valve - Nominal bore: 1,200mm - 3 Nos.) but station, Refer to revised BOQ Page d/6B/9.
it is not showing in the Tender Drawings for
STORM WATER PUMP STATION-3. Kindly
clarify.
As per Tender Drawing Ref. SWD PS351- Refer to revised drawing no. SWD SP351
STORM WATER PUMP STATION-3 DB21New - rev.01
15. P & I DIAGRAM is not matching with Mechanical
Drawings. Kindly clarify.
Referred item measures "Submersible Propeller Please refer to the Annexure 1 - Propeller
Pump" however, there is no specification for Pump Specification (Volume 2 Part 2 of 3)
Propeller type Submersible Pump. issued herewith.
18. Kindly provide the specification or confirm only
the General specification requirement to be
followed.
Referred drawing indicates penstock 1200mm All the items detailed in drawings SWD-DT01
dia for Pond DB21. However, the same is not i.e., Pipes, chambers, and Penstock with all
measured in the BOQ. associated works complete to be priced as a
19.
Kindly clarify. lump sum item in the BOQ item A on Page
d/6B/24
Referred item measures "Air Inlet/ Outlet Duct Refer Dwg No.PS302 & BOQ Page d/6B/10
Dia 400", however this "Duct" is not shown on the Item-C related to Air inlet/Outlet, pipe
drawing and is not measured in the BOQ. material GRP.
20.
Kindly clarify and indicate the type of pipe to be
used.
Referred drawing indicates stilling tube dia 200 Cost of Stilling tube to be included in the
and dia 400, however, the same items are not respective works item i.e., float switch &
measured in the BOQ. Hydrostatic Level Transmitter Item in the
21.
Kindly incorporate the same and revise the BOQ BOQ Item A & CA on Page d/6B/21
accordingly.
Referred drawing "SWD PS 302" fitting schedule The confirmed pipe dia is 250mm. Refer to
and BOQ indicates size for pipes, fittings, valves, the revised Dwg No. SWD PS 303 Rev T1
dismantling joints as 250mm dia, however, issued with this NTT1.
drawing "SWD PS303" indicates the sizes for all
22. items as 300mm.
Kindly provide the pressure rating and stiffness Refer to Volume -2 part 1 clause 4.1.1 for the
for the pipes per the area of applications. pipe pressure rating.
23.
____________________________________________________________________________
Notice to Tenderers No.1
3
OPEN DATA / بياانت مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
Referred drawing shows Operator Workstation, Refer to DWG No. SWD -PS340 Rev 01 for
Engineering Workstation, 55'' Screens, 42U layout and SWD-PS354 rev 00 for the
Rack, Color Printer in the SCADA Room, system architecture for SCADA scope and
25. I Interface. Refer to the revised BOQ Page
however this is not measured in the BOQ.
Kindly provide us with revised BOQ including the No.d/6B/32 Item D issued with this NTT1.
same.
Referred BOQ items measures interfacing of the For interfacing of the SCADA and control
regional telemetry Outstation to controller in system refer to DWG No. SWD-
MCC, However there is no specification or details PS354.Please refer to the DM standard
provided for the regional Telemetry specification in Volume 2 part 2 Section 14.
26.
Outstation.
Kindly provide details and specifications for the
same.
Referred BOQ items description measures For scope, Matrix refers to updated DWG
complete work for Package substation including No. SWD-PS341 Rev 01. However, the
Switchgear, transformer & associated cabling. As Contractor scope starts from terminating the
per standard DEWA practice, Switchgear, incoming cable to the proposed 11KV DEWA
transformer & associated cabling will be supplied package substation. Refer to the revised
27.
and installed By DEWA. Our scope is limited to BOQ page no.d/6B/24 issued with this NTT1
other electrical works like earthing, lighting,
Wiring accessories & Fire alarm system, kindly
Confirm.
Referred BOQ item descriptions states Refer to revised BOQ page no.d/6B/30
''3CX16mm2 Cu/XLPE/SWA/PVC +1CX120mm2 issued with this NTT1
28. ECC'', According to standard the ECC Cable size .
should be 1CX16mm2 ECC, please clarify.
Referred BOQ item descriptions states Refer to revised BOQ page no. d/6B/31
''4CX16mm2 Cu/XLPE/SWA/PVC +1CX120mm2 issued with this NTT1.
29. ECC'', According to standard the ECC Cable size
should be 1CX16mm2 ECC, please clarify.
Referred BOQ item shows telephone points & For interfacing of the SCADA and control
Wiring to regional telemetry outstation. system refer to DWG No. SWD-PS354.
Contractor scope is only passive part. Any live
30.
connectivity and its associate cost in not part
of this tender scope. Kinldy confirm
Referred BOQ items description measures Please refer to the reply to query no.27.
complete work for Package substation including
Switchgear, transformer & associated cabling.
These are inbuilt integrated item of package
31.
substaion supplied & Installed by DEWA.
Contractor scope is limited to civil works &
coordination for Electrical Works. Kinldy Confirm
Referred drawing shows 55" Screen for CCTV Refer to DWG No. SWD -PS340 Rev 01 for
system. However there are no CCTV Cameras layout and SWD-PS354 rev 00 for the
32.
shown anywhere in the layouts & CCTV system system architecture for SCADA scope and
is not measured in the BOQ. Interface. Refer to the revised BOQ page
____________________________________________________________________________
Notice to Tenderers No.1
4
OPEN DATA / بياانت مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
Kinldy clarify if CCTV system is required for this no.d/6B/32 Item D issued with this NTT1.
project or not. If yes, kinldy provide layouts,
specifications & BOQ for the same.
Refer to DWG No. SWD -PS340 Rev 01 for
Referred drawing shows 42U Rack . However
layout and SWD-PS354 rev 00 for the
there are no details provided for the 42U Rack,
system architecture for SCADA scope and
33. active switches and related items. Request you to
Interface. Refer to the revised BOQ page
provide complete details of the Rack.
no.d/6B/32 Item D issued with this NTT1.
Referred BOQ items describes '' 1CX630mm2 Confirmed Confirmed. Refer to DWG No.
X3 cable /phase +1CX300mm2 X2 cable for SWD-PS340 Rev01 and also refer to the
Neutral. Our understanding is that it is revised BOQ page no.d/6B/30 Item A issued
34.
9RX1CX630mm2 +2RX1CX300mm2 cable. with this NTT1.
Kindly Confirm.
Referred drawing indicates the pipes inside Refer to DWG PS 351-Rev 01 for required
Lifting station as Stainless steel and ductile iron, ratings.
however, the grades for both the pipes are not
mentioned in any of the drawing and
35.
specification.
Kindly provide grade, pressure rating for SS and
Ductile iron pipes.
As per Dwg No. SWD PS340, MV Switchgear Refer to the Revised DWG No. SWD PS340
(MV-001) is shown in Electrical Switchgear –Rev 01
Room. You are requested to clarify if there is typo
37. error as it is not matching with Single Line
Diagram provided in SWD PS341 as all output
feeders are fed by LV MCC-03.
You are requested to provide the distance The length from the Package substation to
between substation and Electrical Switchgear MCC is approx.70 meters.
38.
Room.
As per Dwg No. SWD PS341, Portable DG set is Confirmed, Portable DG set is out of the
shown. Please confirm if it is out of contractor's contractor's scope of work.
39.
scope of work.
As per BOQ Line Item No. 3.138.4, 1C x Please refer item description mention that 9
630mm2 x 3cable phase + 1C x 300mm2 x runs of 630 sqmm + 2runs of 300 sqmm are
2cable for Neutral CU/XLPE/SWA/PVC (from to be the price for each Linear meter of item
New Package Substation to MCC-03 & from provide in the BOQ.
40. Portable DG Set to MCC-03), only 100mtrs
length is provided in the BOQ which seems to be
insufficient considering project requirements.
Please clarify where to incorporate the price for
additional length.
As per Dwg No. SWD PS341, ATS seems to be MCC panel is to be provided with built-in
the part of MCC-03 Panel. You are requested to ATS.
please clarify if MCC panel is to be provided with
41. built in ATS (option-1) or a separate ATS Panel
needs to be placed close by MCC Panel from
there it will be looped (option-2). Please clarify
which option to consider as per project
____________________________________________________________________________
Notice to Tenderers No.1
5
OPEN DATA / بياانت مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
requirement.
You are requested to confirm that input power Confirmed Feed cable from existing S/S to
feed cable (11kV) for Package Unit Substation is Package Unit Substation is out of
42.
out of contractor's scope of work. contractor's scope of work.
BOQ ITEM d/4/2 - C - Please provide the detailed Please refer to the revised BOQ page no.
43. drawing for this item. d/4/2 issued with this NTT1.
BOQ ITEM d/5/15 A to C - Please advise no. of Please refer to the revised BOQ page no.
44. backdrops to be provided. d/5/15 issued with this NTT1.
BOQ ITEM d/5/18 A to D - Please advise no. of Please refer to the revised BOQ page no.
45. backdrops to be provided. d/5/18 issued with this NTT1.
BOQ ITEM d/5/19 A to F - Please advise no. of Please refer to the revised BOQ page no.
46. backdrops to be provided. d/5/19 issued with this NTT1.
BOQ ITEM d/5/23 A to J - Please advise no. of Please refer to the revised BOQ page no.
47. backdrops to be provided. d/5/23 issued with this NTT1.
6. BOQ ITEM d/5/24 A to D - Please advise no. Please refer to the revised BOQ page no.
48. of backdrops to be provided. d/5/24 issued with this NTT1.
BOQ ITEM d/5/27 A to C - Please advise no. of Please refer to the revised BOQ page no.
49. backdrops to be provided. d/5/27 issued with this NTT1.
Reference to BILL No. 6B - STORM WATER Please refer the Revised BOQ in the Portal.
DRAINAGE PUMPING STATION # 3 d/6B/10,
please confirm that work description of Item
52.
Code No 3.118.3 is the continuation of Item
code No 3.118.3 and need not to be price.
____________________________________________________________________________
Notice to Tenderers No.1
6
OPEN DATA / بياانت مفتوحة
PROJECT: DS 196/2
NADD AL SHIBA 3rd SEWERAGE & STORMWATER SYSTEM
05 OCTOBER 2022
Employer:
PROJECT: DS 196/2
rd
NADD AL SHIBA 3 SEWERAGE & STORMWATER SYSTEM
The Notice to Tenderers No.2 is issued to add/amend the followings. The Tenderers should
replace the affected pages with the revised pages attached herewith, which have been marked
“Notice to Tenderers No.2”.
(Revised items have been marked with ** and revised pages with 2 symbol)
1. Volume 1 Tender & Contract Conditions: Please replace the following revised pages:-
a/1
d/1/2, d/1/3, d/1/11
d/4/1, d/4/2, d/4/5
d/5/37
d/6A/48
d/6B/32
Section - G Schedule of Price Breakdown
3. Revised Drawings: The revised drawings listed under column 05/10/2022 in the drawing
issue sheet are issued and shall supersede drawings of the same number issued previously.
____________________________________________________________________________
Notice to Tenderers No.2
1
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
PROJECT: DS 196/2
NADD AL SHIBA 3rd SEWERAGE & STORMWATER SYSTEM
Notice to Tenderers No.2 is issued to respond to the tender queries received from the
tenderers. The Queries received from Tenderers are replied to in the Clarification Sheet below.
SL.
Nr.
Tender Query Response to Tender Queries
1. Please provide an Updated Road cross-section NOC received during the design stage
since we had observed that 132kv is under issued to the tenderer in NTT1 however if
construction parallel to our corridor. any update information regarding existing
utilities will be provided to the Successful
tenderer during the Construction stage.
2. We had observed that some existing roads ( road Reinstatement is required for existing roads
base only) are available, please advise whether refer to BOQ Page d/4/4 – Item C & D,
the reinstatement is required or not. d/5/28 – Item A & B, d/5/29 – Item A & B,
and d/6a/35 – Item A to G, d/6a/36 – Item A
to D.
3. Kindly advise the disposal location for excess Disposal location for excess materials shall
material. be within Dubai City Landfill area.
4. Refer to Profile Drawings Huge cut and fill Refer revised BOQ page d/5/37 Item G & H
required but no item has been provided to quote, and d/6a/48 Item E & F for Pipe works
please advice. additional fill quantity.
5. With reference to the BOQ item D/6B/24B, The For scope, Matrix refers to updated DWG
standard procedure for Dewa substation works No. SWD-PS341 Rev 01 issued in NTT1.
are, Substation Room construction including However, the Contractor scope starts from
lighting and Small power with required trenches, terminating the incoming cable to the
and coordination with Dewa for the collection, proposed 11KV DEWA package substation.
installation, Testing, and commissioning of Refer to the revised BOQ page no.d/6B/24
Substation will be the scope of the contractor and issued in NTT1.
Client will pay the estimate from Dewa for the
equipment to Dewa. Please clarify.
6. Refer to House connection Scope, Kindly provide Scope of work is limited to Constructing the
a separate item for Wet and dry connection. House connection Chamber, the pipe
installation & end cap up to the plot limit.
Refer to revised BOQ page d/4/1, d/4/2 &
d/4/5.
7. As per the line, we might cross the existing As per NOC received no permanent
network which required Permanent Diversion diversion or/and protection is required
or/and protection, please confirm that any however if any permanent diversion or/and
permanent protection /diversion will be paid as protection is required based on the Site
variation items. condition then this will be treated as per DM
standard.
8. Kindly provide the Drawing with a coordinate for CAD Drawings with coordinates will be
more study ( Diversion, etc). provided to the Successful tenderer as part
of Good For Construction drawings.
____________________________________________________________________________
Notice to Tenderers No.2
1
OPEN DATA / بيانات مفتوحة
Project: DS196/2
Nadd Al Shiba 3rd Sewerage & Stormwater System
____________________________________________________________________________________________________
10. In reference to tender query response and revised Confirmed CCTV system is not in the scope
drawing SWD PS340 rev T1, our understanding is of this project.
the CCTV system is not included in the scope of
this project. Kindly Confirm.
11. As per tender query response and revised drawing Confirmed 42U rack is not in the scope of
SWD PS340 rev T1, our understanding is the 42U this project. Refer to revised BOQ Page
rack is not included in the scope of this project. d/6B/32 Item D.
Kindly Confirm.
12. Referred drawing shows 3X600mm MV Cable MV cable ladder shall be 3 x 450mm refer
Ladders in the MCC Room, however, it is not revised drawings SWD PS345 –Rev T2.
measured in the BOQ. Request you to kindly
revise your BOQ to incorporate the same.
13. Referred Specifications for Propeller pumps Soft Starter to be used as per the SLD
specifies that motor should be designed for VFD
operation, However the referred drawing shows
Soft Starter for motor operation.
Kindly clarify if we should consider Soft starter or
VFD for motor operation.
14. Referred drawing indicates Propeller Pumps are Contractor with manufacturer to include in
fixed inside Stainless Steel Pipes. the O&M. the pumps are equipped with SS
Kindly clarify how the pumps maintenance will be chains to be lifted from tubes once required
carried out.
15. Kindly confirm pressure rating PN6 is acceptable PN6 is acceptable for stilling tube due to no
for Stilling tubes for float switch and hydro level pressure requirement.
transmitter.
16. Referred drawing indicates both pressure ratings PN6 is acceptable for the vent pipe due no
PN16 and PN6 for Air Outlet GRP Pipes. pressure requirment
Kindly clarify which pressure rating to be used.
17. Referred drawing indicates Pond DB 21 Overflow Refer revised drawings SWD DT01-Rev 1
and Evacuation Line plan and sections, however, and SEW-SWD05 Rev-1 for the location of
location for the same is not provided. Evacuation line issue with this NTT2.
Kindly provide the plan/layout indicating the
location of the Evacuation line.
18. We request you to extend the Tender Submission The revised tender opening date is Oct 11/
date by at least 3 weeks form the current 2022.
submission date of 4-10-2022.
____________________________________________________________________________
Notice to Tenderers No.2
2
OPEN DATA / بيانات مفتوحة
اﻟﻤﺮﺟﻊDM072022-1683658 : اﻟﺘﺎرﻳﺦ2022/11/16 :