Mandatory Pre Check for deputation of Supervisor (GIS)

This is an essential requirement for the deputation of HYSOUNG GIS supervisor.


We, Hyosung, need the Contactor/Purchaser’s confirmation for the following site condition shown below to
eliminate any idle time when supervisor arrives and does the supervision efficiently at site.
Ticking by
No Description Contractor/Purchaser
1 All packing boxes should be available in safety before arrival of supervisor at site. If Yes □ No □
SF6 Gas can’t be delivered to site before arrival of supervisor, it should be
available within maximum 14days from the date of supervisor’s arrival.
2 Level difference should be less than 2mm for embedded I - beam between first and Yes □ No □
last one.
3 The Epoxy work has been completed in GIS Room Yes □ No □
4 Installation and Testing of Overhead crane have been completed in GIS Room and Yes □ No □
it is working properly
5 Painting of the wall inside GIS Room has been completed Yes □ No □
6 The Shutter of Entrance of GIS Room has been installed Yes □ No □
7 Scaffolding has been removed from GIS Room and GIS Room has been cleaned Yes □ No □
8 All germs have been removed from the Embedded I beam in GIS Room Yes □ No □
9 The Lighting work in GIS Room has been completed Yes □ No □
10 All opening holes on floor in GIS Room should be covered with unmovable steel Yes □ No □
plate or thick wooden plate for the purpose of safety.
11 The floor in GIS Room has been covered by Nylon plate or carpet or wooden plate Yes □ No □
as per SEC instruction.
12 When carrying in GIS Main body into GIS Room, the level of outdoor area (Length : Yes □ No □
10M X Width : 6M) should be same level with GIS Room.
13 Foundation (Concreting) for Gas Insulation Bus outside of GIS Room has been Yes □ No □
completed. If not, it should be completed within maximum 14days from the date of
supervisor’s arrival.
14 All required tools and erection / testing equipment are ready (see the attached list) Yes □ No □
15 The skilled technicians and labors should be ready as below Yes □ No □
During stage of unpacking and carrying GIS main body : 15 workers for each substation
Until the demobilization of supervisor : 7 Technicians for each substation
16 Duration of supervision will be counted from the date of supervisor’s arrival at site. Yes □ No □
Note) In case of any contrary to the above items #1~ 16 at site, instead of contractor/purchaser’s confirmation,
Hyosung has the right to demobilize supervisor after completing contractual duration of supervision
regardless of the site activity.
For the Contractor/Purchaser’s use

We, hereby fully confirm on the required site condition by ticking on item #1~16 in “Yes” of “Ticking by
Contactor/Purchaser” as mentioned above by the authorized personnel.
Name of Contactor :

Name of substation :

Name of Authorized personnel :

Signature :

Date :
1
The required tool and equipment

No. Description Specification Q'ty


Preparation
1 Site office 2Desks + 2chiars 1set
2 Refrigerator small 1ea
3 Internet available
4 Wooden table for Tools in GIS Room 2000X800X1500, 4Legs 1ea
5 Steel cabinet w/padlock Two doors 2ea
6 Wooden rack w/4step 2000(H)X500x500(D) 2ea
GIS carrying in + GIS Docking
7 Crane 50tons 1ea
8 Steel plate or wooden plate For inserting GIS into room
9 Steel pipe (roller) Dia ; 10¢, T; 10 , L ; 2M 30ea
10 Nylon rope 5tons , 8M , 4M , 3M Each 4ea
11 Nylon rope 3tons, 5M 4ea
12 Nylon rope 2tons, 2M , 1M Each 4ea
13 Shackle 5tons 4ea
14 Shackle 3tons 4ea
15 Chain Hoist 5tons 2ea
16 Chain Hoist 3tons 4ea
17 Chain Hoist 1ton 4ea
18 Lever Hoist 6tons 4ea
19 Hydraulic Jack (Not made in China) 10tons (Vertical, horizontal) Each 2ea
20 Plumb bob 500g 2ea
21 Chalk liner blue color 1ea
22 Measuring Tape 5M, 10M Each 2ea
23 Measuring Tape 50M (Steel) 1ea
24 Water level 80cm , 1m , 2m Each 2ea
25 Vacuuming pump Above 600Liter 3ea
26 Vacuuming Hose Adapter : DILO or Woosung 12ea
27 Gassing Hose (filling device) Adapter : DILO or Woosung 2ea
28 Pirani Gauge To check of vacuuming status 2ea

2
No. Description Specification Q'ty
Each 4ea
29 Ratchet wrench (Not made in China) 13,17,19, 24,30 Red Marked
8EA
30 Work light 2ea
31 Power distribution board w/MCB 50A, 10A, 4A Each 1ea
32 Torque wrench 4500QLK ,1800QLK Each 2ea
33 Torque wrench 900QLK , 450QLK Each 2ea
34 Spanner 19, 24, 30 Each 10ea
Each 4ea
35 Spanner 13, 17, 19, 24, 30, 36, 46, 55 Red Marked
8EA
36 Welding machine 1ea
37 Socket wrench Big, small Each 4ea

38 Meteoric socket (Short type) 13, 17, 19, 24, 30 Each 4ea
39 Meteoric socket (Long type) 17, 19, 24 Each 4ea
40 Hex key set 2sets
41 Adjustable wrench 8, 10, 12, 15, 24 (Inch) Each 4ea
42 Hack Saw 2ea
43 Hammer (claw) 1pc
44 Long nose pliers 4ea
45 Cutting pliers 4ea
46 Cable cutter for cable pulling 2ea
47 Screw driver +, - Each 8ea
48 Clamping tool for 2.0, 4.0, 5.5sq wire 4ea
49 Vacuuming cleaner Large 2ea
50 Vacuuming cleaner small 4ea
51 Flexible hose for Vacuuming cleaner 50M 1roll
52 Cotton rags 10kg
53 Extension coder for electric 4ea
54 Step Ladder High : 2M 4ea
55 Metric caliper 1ea
56 Peeler gauge 1ea
57 File 2ea
58 Sand paper 400, 600 , 800 Each 40ea
59 Steel brush 2ea 3
No. Description Specification Q'ty
60 Squeeze spray bottle (plastic) 20ea
61 Canvas bucket 10ea
62 Broom 5ea
63 Painting brush 1, 2, 4 (Inch) Each 6ea
64 Plastic cover (Vinyl) Request of SV
65 Plastic tape w : 2cm Request of SV
66 Knife 10ea
67 Plastic water pump 4ea
68 WD 40 Request of SV
69 Speed cutter Electric 1ea
70 Hydraulic knockout punch 1ea
71 Electric drill 1ea
Testing equipment
72 Dew point/purity tester Refer to testing list 1ea
73 Insulation tester (Megger) Refer to testing list 1ea
74 Gas Detector Refer to testing list 1ea
75 Micro Ohm Meter Refer to testing list 1ea
Above test equipment is required during erection to check the status of GIS Erection
Note : If additional equipment/materials ,that were not mentioned above, are required, the contactor/purchaser
will prepare accordingly based on the supervisor’s request.
Note : Regarding vacuum pump & vacuum hoses and pirani gauge ,please refer to the below photos.
The contactor/purchaser will prepare 3SET for vacuuming and internal check.
Also please refer to the below gassing hose for reference.

(DILO 1SET) (WOOSUNG 1SET)

4
(Gassing hose)

----- Nothing follows ----

5
GIS SITE TEST EQUIPMENTS LIST
Quality Control Team_Switchgear
Manufacture
No. Test Items Equipment Name Equipment Picture Specification
& Model No.

- Main Input : 100~240VAC


Resistance Digital Main Contact MEGGER - Measuring range : 0 – 999.9 mΩ
1 Measurement of Main resistance PROGRAMMA - Outputs Range : 5 – 600 A DC
Circuit Measurement (Mjolner 600) - Output voltage (max) 5.25 V DC at 600 A
- Inaccuracy : ±1%

SF6 Gas Leakage SF6 GAS Leak DILO


2 - Sensitivity : 5 g/yr
Test Detector (3-033-R002)

- Input : 100 – 240 V AC, 50 / 60 Hz


- Range : 200 s at 10 kHz sample rate
MEGGER
Mechanical Operation - Max. sample rate : 40kHz(25µs)
3 Breaker Analyzer PROGRAMMA
Test - Inaccuracy : 0.01%(0.1ms)
(TM1800/1760)
- Timing of main and resistive contacts
Main < 10 Ω <PIR < 10 kΩ < Open

- Insulation resistance range : 100kΩ ~ 1TΩ


Measurement of MEGGER - Test voltage DC : 250V,500V,1KV,2.5kV,5kV
4 Insulation Tester
insulation resistance (BM5200) - Accuracy : ± 5.0%
- Short Current : 1.4 mA ± 0.5 mA

- Input : 220V, 1ø, 500VA 50/ 60Hz


- Output voltage : 0 ~ 5kV
Dielectric test of Digital Dielectric KIKUSUI - Output Current : 100mA
5
Auxiliary circuit Tester (TOS 5200) - Proble
Max Voltage : 4kV(Pistol probe type)
- Test time : 0.1s ~ 999s

- Measuring : SF6 purity, H2O


- Input pressure : 0.3bar ~ 9bar
Moisture content
DILO - Operating temperature : -10°C ~ +50°C
6 measurement in SF6 SF6 Multi Analyzer
(3-038R-R303) - Measuring time : max. 15min
Gas
- Dew point : -60°C ~ +20°C
- Input:AC 100~240V AC, 50 / 60 Hz

- Input : 400V±10%, 200kVA, 50/60Hz


Power Frequency
AC High Volt Test HIGHVOLT - Output : 690kV
7 Withstand Voltage
System (7400-1000SR) - Output Current : 3.7 amps max
Test
- Resonant type : Variable frequency

- Input : 195 - 250 V/ 47~66 Hz


- Range : 0~1.5GHz
Agilent - Sweep time : 1ms ~ 4000S
8 Partial Discharge Test Spectrum Analyzer
(4401B) - Maximum input level :
Peak : + 30dbm
DC : 100V

- Input : 100 V ~ 240 V AC, 16 A


- Output
OMICRON voltage source(AC) : 0~2kV max 1.25 A
9 CT/VT Test CT/VT Tester
(CPC 100) Current source(AC) : 800 A @ 6.0 V
Current source(DC) : 400 A @ 6.5 V
- Function : CT / VT test

- Determines All Relevant Current Transformer Values


- Measurement of transient behavior of TPS, TPX, TPY
and TPZ type CTs
OMICRON
10 CT Test CT Tester - Automatic Assessment According to IEC 60044-6
(CT Analyser)
- Knee-point voltage from 1 V up to 30 kV can be
measured
- Data Aquisition Unit(Laptop) shall be included
Note) Above mentioned Test Equipment is for reference. It can be change at the site condition, but the function of test equipment should be equivalent or more.