41923
REPORT
STOCKPILE INVENTORY
ALL PLANT AREA
PERIOD END OCTOBER 2020
STOCK REPORT
PERIOD : 1 March 2021 to 13 March 2021
DATE : 13 March 2021
APPROVAL
DRAWING BY Signature Date
Budi Bowo Leksono
Surveyor
PREPARED BY Signature Date
Budi Bowo Leksono
Surveyor
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
Project : PT. Andesit Lumbung Sejahtera
Sheet : Stock Inventory Plant 2 & 3
Dept : Production and Engineering
Period : 15 February 2021
APPROVAL
DRAWING BY Signature Date
Budi Bowo Leksono
Surveyor
PREPARED BY Signature Date
Budi Bowo Leksono
Surveyor
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
Project : PT. Andesit Lumbung Sejahtera
Sheet : Stock Inventory Plant 2 & 3
Dept : Production and Engineering
Period : 13 March 2021
APPROVAL
REPORTED BY Signature Date
Budi Bowo Leksono
Surveyor
CHECKED BY Signature Date
Ferdiansyah
Junior Planner
CHECKED BY Signature Date
Feri Wahyudi
Foreman Stock Pile
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
STOCK REPORT
PERIOD : 1 August 2021 to 31 August 2021
DATE : 31 August 2021
APPROVAL
REPORTED BY Signature Date
Budi Bowo Leksono
Surveyor
CHECKED BY Signature Date
Ferdiansyah
Junior Planner
CHECKED BY Signature Date
Feri Wahyudi
Foreman Stock Pile
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
Project : PT. Andesit Lumbung Sejahtera
Sheet : Stock Inventory Plant 4
Dept : Production and Engineering
Period : 31 August 2021
APPROVAL
REPORTED BY Signature Date
Budi Bowo Leksono
Surveyor
CHECKED BY Signature Date
Ferdiansyah
Junior Planner
CHECKED BY Signature Date
Feri Wahyudi
Foreman Stock Pile
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
Project : PT. Andesit Lumbung Sejahtera
Sheet : Stock Inventory Plant 4
Dept : Production and Engineering
Period : 30 September 2021
APPROVAL
REPORTED BY Signature Date
Budi Bowo Leksono
Surveyor
CHECKED BY Signature Date
Ferdiansyah
Junior Planner
CHECKED BY Signature Date
Feri Wahyudi
Foreman Stock Pile
ACKNOWLEDGED BY Signature Date
Jujur Prasetyo
Manager Produksi
APPROVED BY Signature Date
Troy Fahzar
General Manager
DISTRIBUTION LIST :
- Engineering & Operation
- Crusher
- Finance
- Cost Control
Project : PT. Andesit Lumbung Sejahtera
Sheet : Stock Inventory Boulder Rom A,b dan C
Dept : Production and Engineering
Period : 14 December 2021