Professional Documents
Culture Documents
Wadel1961 Probabilistic Manpower
Wadel1961 Probabilistic Manpower
Wadel1961 Probabilistic Manpower
co-riparv
sengl i arlp0ve qurnltsHower,nlyifthe"go- "dateisAprl1.
IRE TRAINSACTIONS ON ENGINEERING MANAGEMEANT
requiremeint
-
It
~P ~~~~~~~~~~~~P
(
t
=
M(t) P
IRE
Summary-A statistical technique is presented for estimating The expected requirement peaks at ten men during April
and May, because un*der the give assumptions the con-
0 < P < I
mj . there is 225 per celnt probability each of . Ml(t) = ith possible np
It 2p
1 2,
probability
September
M (t)p(AMj) (1)
froi a possible Jainuarv start plus 2.5 men froin a pos- EPwi)
sible Piebruary start, or a total of 5.0 meni. The complete
iabulationI thiis beeomiies For computational convenience, t is treated as a dis-
crete variable: Mi(t) and fl1(t) are assumed to be constant
tontd Expected Manpower Repiremenlt during each unit time interval (e.g., one week), changing
stepwise from one interval to the next,
Ianuary 2. 5 For each possible go-ahead date ti, a single manpower
February 5.( assignment funetion Mi (t) is chosen. Then p((Mi) becomes
Mareh 7.5 p(tS), the probabilitv of go-ahead occurring at t.
April 10.0 The p(ti), as well as P, may be estimated on the basis
;Nlay 10.0 of past experience with the particular type of contract
Ju ne, 7.5 and customer, extrapolations from ctustomer statements
July 50 made in the original request for bid and sutbsequently,
August 2.5 and whatever other information may be available.
-- If the 11i (t) are identical except for go-ahead date,
Total man-n-onths 50. 0. iI(t) may be written as M(t - ti), and (1) becomes
0.10-
40-
0.09
35 X l008-
D
0.07-
-0.06-
.0 0.05-
15- .0
0~~~~~~~~~~~~~~~~~
s0 0I0
-o.04
5- ~~~~~~~~~~~~~~~~~~~~~~~~~0.01
0
Ol i 8 9 10 11 12 13 14 15 162Jan 30 Jan 27 Feb 27Mar 24Apr 22 May
12-
10
9C t
a)CS
E7
6-
5-o
a's
2-
X~~~~~~Fg 3. 14 Aug
2 24Apr 22Moy 19Jun
30 Jon 217Feb 27Mar
Jon 17.JuI
Calendar time, t
Fig. 3.
As an example, Fig. 1 illustrates a possible M(t - ti) APPENDIX
function, while Fig. 2 shows a hypothetical plot of p(ti). If time is treated as a continuous variable, (2) is replaced
For the value of P = 0.5, M(t) has been calculated from by
(2) and plotted in Fig. 3. This, then, is the "expected" t
future manpower requirement related to one particular M(t) = P M(t - ti)p(ti) dti. (3)
contract bid.
In itself, this "expected" result is useless, since a As an analogy, it is interesting to note that if an input
specific contract will either be awarded in full on a specific signal equal to M(t) is applied to a linear filter with
date or not awarded at all. However, the total "expected" weighting function equal to p(ti), the filter output Eo
future manpower requirement may be found by summing will be4
the M(t)'s calculated for each outstanding bid.3 Ele- E
tM(t-t,)p(tj) dt. (4)
mentary statistical considerations ensure that the greater
the number of outstanding bids, the greater the relative
accuracy of this total "expectation" in estimating actual
Thus E0 equals M(t) except for a scale factor of P.
requirements. As a crude rule, the method1should not be ~4 H. M. James, et al., "Theory of Servomechanisms," McGraw-
used unless at least five bids are involved. Hill Book Co., Inc., New York, N. Y.; 1947.